Vega v. Scheyer
Cases that cite this one
4 later published cases cite this decision.
- Leitner v. Town of Oyster Bay Planning & Development Department (Appellate Division of the Supreme Court of New York 2016)
- Cutalo v. Zoning Board of Appeals of Town of Huntington (Appellate Division of the Supreme Court of New York 2008)
- R & V Development, LLC v. Town of Islip (Appellate Division of the Supreme Court of New York 2007)
- Fiume v. Chadwick (New York Supreme Court 2007)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Ordered that the judgment is affirmed, with costs.
Town Law § 267-c (1) states, in pertinent part, that a proceeding pursuant to CPLR article 78 to review a determination of a zoning board of appeals “shall be instituted within [30] days after the filing of a decision of the board in the office of the town clerk.” Here the petitioners did not commence their proceeding until more than five months after the respondents’ decision was filed.
Contrary to the petitioners’ contention, the statute of limitations was not tolled due to some minor procedural irregularities in the process followed by the respondents in rendering their determination (see Matter of Kennedy v Zoning Bd. of Appeals of Vil. of Croton-on-Hudson, 78 NY2d 1083; Matter of Crepeau v Zoning Bd. of Appeals of Vil. of Cambridge, 195 AD2d 919 [1993]; cf. Matter of McCartney v Incorporated Vil. of E. Williston, 149 AD2d 597 [1989]). Accordingly, the Supreme Court properly dismissed the proceeding as time-barred (see Town Law § 267-c [1]; Matter of Ficalora v Planning Bd. of Town of E. Hampton, 262 AD2d 320 [1999]).
The petitioners’ remaining contention is without merit. Florio, J.P., S. Miller, Santucci and Spolzino, JJ., concur.