Pheasant Meadow Farms, Inc. v. Town of Brookhaven
Opinion of the Court
In a proceeding, inter alia, pursuant to CPLR article 78 in the nature of mandamus to compel the Department of Planning, Environment, and Development of the Town of Brookhaven to place an application for preliminary approval of a subdivision plat on the calendar of the Planning Board of the Town of Brookhaven, the petitioner appeals from a judgment of the Supreme Court, Suffolk County (Loughlin, J.), entered April 26, 2005, which denied the petition and dismissed the proceeding.
Ordered that the judgment is affirmed, with costs.
The time within which a planning board must act upon a preliminary subdivision plat application does not commence until the application is deemed complete (see Town Law § 276 [5] [c]; Matter of Sun Beach Real Estate Dev. Corp. v Anderson, 98 AD2d 367 [1983], affd 62 NY2d 965 [1984]). A preliminary plat is not considered complete until either “a negative declaration has been filed or until a notice of completion of the draft environmental impact statement has been filed in accordance with the provisions of the state environmental quality review act” (hereinafter SEQRA) (Town Law § 276 [5] [c]; see ECL 8-0109 [2]; Matter of Sun Beach Real Estate Dev. Corp. v Anderson, supra). Here, neither filing has occurred as the required SEQRA review is ongoing (see Town Law § 276 [5] [b]), and the respondents continue to glean relevant information to assess the environmental impacts of the proposed project.
The project presents significant environmental concerns with
The petitioner’s remaining contentions are without merit. Florio, J.E, Skelos, Fisher and Dillon, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.