Tishman Westwide Construction LLC v. ASF Glass, Inc.
Opinion of the Court
Order, Supreme Court, New York County (Karla Moskowitz, J.), entered on or about June 2, 2005, which granted defendant surety’s motion for summary judgment dismissing the complaint against it and denied plaintiffs’ cross motion for partial summary judgment, unanimously affirmed, with costs.
The conditions of the bond with which plaintiff owner failed to comply went directly to the surety’s liability, and required strict compliance (see 120 Greenwich Dev. Assoc., LLC v Reliance Ins. Co., 2004 WL 1277998, *11-13, 2004 US Dist LEXIS 10514, *33-37 [SD NY 2004]; see also Northeast Constr. Group, Inc. v Deconstruction, Inc., 16 AD3d 357 [2005], lv denied 5
We have considered plaintiffs’ other contentions and find them unavailing. Concur—Andrias, J.E, Marlow, Gonzalez, Sweeny and Catterson, JJ.