Schietinger v. Tauscher Cronacher Professional Engineers
Cases that cite this one
13 later published cases cite this decision.
- Finch v. Inspectech, LLC (W. Va. 2012)
- Ryan v. IM Kapco, Inc. (Appellate Division of the Supreme Court of New York 2011)
- Johnston v. MGM Emerald Enterprises, Inc. (Appellate Division of the Supreme Court of New York 2010)
- Corbett v. FIRSTLINE SECURITY, INC. (District Court, E.D. New York 2009)
- Mancuso v. Rubin (Appellate Division of the Supreme Court of New York 2008)
- Smith-Hoy v. AMC Property Evaluations, Inc. (Appellate Division of the Supreme Court of New York 2008)
- Clement v. Delaney Realty Corp. (Appellate Division of the Supreme Court of New York 2007)
- Astoria Generating Co., LP v. Riley Power, Inc. (Appellate Division of the Supreme Court of New York 2020)
- Princetel, LLC v. Buckley (Appellate Division of the Supreme Court of New York 2012)
- Lawrence v. Kennedy (New York Supreme Court 2011)
- Goldstein v. Carnell Associates, Inc. (Appellate Division of the Supreme Court of New York 2010)
- Finsel v. Wachala (Appellate Division of the Supreme Court of New York 2010)
- Pleasant Hill Developers, Inc. v. Foxwood Enterprises, LLC (Appellate Division of the Supreme Court of New York 2009)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Ordered that the order is affirmed, with costs.
The plaintiffs, Elena Schietinger and George Schietinger, hired the defendant, an engineering company, to conduct a prepurchase inspection of their home and prepare a report. Under the terms of the agreement, if the defendant was found liable for any loss or damage arising out of the inspection and report, its liability would be limited to the fee paid for these services, which was $1,705. The plaintiffs subsequently commenced this action against the defendant contending that the company negligently performed its inspection by failing to disclose that the roof of the house was in such poor condition that it would have to be replaced, that the roof shingles were composed partially of asbestos, and that a sill plate was rotted and needed to be replaced. The defendant moved for partial summary judgment limiting its liability to the sum of $1,705, and the Supreme Court granted the motion.
Contrary to the plaintiffs’ contention, the Supreme Court properly found that the defendant’s liability should be limited to the sum paid for the prepurchase inspection and report. A clear contractual provision limiting damages is enforceable absent a special relationship between the parties, a statutory prohibition, or an overriding public policy (see Sommer v Federal Signal Corp., 79 NY2d 540, 553 [1992]; Rector v Calamus Group, Inc., 17 AD3d 960, 961 [2005]; Peluso v Tauscher Cronacher Professional Engrs., 270 AD2d 325 [2000]), none of which was demonstrated here. Moreover, while a party may not
Finally, the plaintiffs argue that George Schietinger should not be bound by the contract’s limitation of liability provision because it was only signed by Elena Schietinger. However, the contract was made for the benefit of both plaintiffs, they were both present during the inspection, they both received the inspection report, and they purchased the house together. Therefore, George Schietinger was bound by the contract’s terms as a third-party beneficiary (see Rector v Calamus Group, Inc., supra at 962). Mastro, J.P., Santucci, Krausman and Carni, JJ., concur.