Sorbara Construction Corp. v. AIU Insurance
Cases that cite this one
4 later published cases cite this decision.
- The Travelers Indemnity Company v. Northrop Grumman Corporation (District Court, S.D. New York 2020)
- Travelers Indemnity Co. v. Northrop Grumman Corp. (District Court, S.D. New York 2014)
- McGovern-Barbash Associates, LLC v. Everest National Insurance (Appellate Division of the Supreme Court of New York 2010)
- Liberty Moving & Storage Co. v. Westport Insurance (Appellate Division of the Supreme Court of New York 2008)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Concurring Opinion
concurs in a separate memorandum as follows: I concur in the result but write separately because while I believe that Great Canal Realty Corp. v Seneca Ins. Co., Inc. (5 NY3d 742 [2005]), the decision by which we are constrained today, was wrongly decided, I nonetheless agree with the majority that in this case, it would not have made a difference even had the Court affirmed our decision in Great Canal. In that case, the time lapse between occurrence and plaintiffs notifica
Opinion of the Court
Order, Supreme Court, New York County (Marcy Friedman, J.), entered January 18, 2007, which denied plaintiffs motion
Where a liability insurance policy requires notice of an occurrence to the carrier as soon as practicable, such notice must be given within a reasonable period of time, and the insured’s noncompliance in this respect constitutes failure of a condition precedent (Great Canal Realty Corp. v Seneca Ins. Co., Inc., 5 NY3d 742 [2005]), thus vitiating the contract as a matter of law, without a showing of prejudice (Argo Corp. v Greater N.Y. Mut. Ins. Co., 4 NY3d 332, 339 [2005]).
Plaintiff became aware of its employee’s accident and his ensuing lawsuit almost immediately, but did not notify defendant excess insurer for some 5 1/2 years, until after the defendants in the underlying matter had instituted a third-party action against it. “[W]here a reasonable person could envision liability, that person has a duty to make some inquiry” (White v City of New York, 81 NY2d 955, 958 [1993]). Although a good-faith belief in nonliability may excuse the failure to give timely notice (see Great Canal Realty Corp. v Seneca Ins. Co., Inc., 5 NY3d 742 [2005]), there is no indication plaintiff ever took any action to ascertain the possibility of its own liability for the accident prior to the commencement of the third-party action. Accordingly, there is no basis for a good-faith belief in its nonliability. Moreover, plaintiffs own duty to provide notice to the excess insurer is not negated by the insurer’s actual knowledge acquired from another source (Ocean Partners, LLC v North Riv. Ins. Co., 25 AD3d 514, 515 [2006]; Travelers Ins. Co. v Volmar Constr. Co., 300 AD2d 40 [2002]). Notice under a workers’ compensation policy does not constitute notice under a liability insurance policy (see Nationwide Ins. Co. v Empire Ins. Group, 294 AD2d 546, 548 [2002]). Plaintiffs protracted delay in giving defendant insurer the requisite contractual notice relieved the insurer of its obligation to defend or indemnify plaintiff. Concur—Marlow, J.P., Williams, Gonzalez and McGuire, JJ.