Conmas, Inc. v. Tully Central School District
Opinion of the Court
Appeal from an order of the Supreme Court (Rumsey, J.), entered February 21, 2006 in Broome County, which, inter alia, denied defendant’s motion for summary judgment dismissing the complaint.
Flaintiff was one of several prime contractors on a project to construct additions and make alterations at defendant’s high school and elementary school. Flaintiff s contract involved general construction, masonry and site conditions. During 2003 and the first eight months of 2004, plaintiff had several disputes with defendant’s architect and construction manager concern
On March 16, 2005, plaintiff served a notice of claim
Our analysis begins with the statute. Education Law § 3813 (1) requires there to be an allegation in a complaint against a school district that a written verified claim was presented to the
Here, plaintiffs claim must be analyzed using a two-step process as it involves items in addition to those included within change proposal No. 61, including, among other things, a claim for contract retainages. First, inasmuch as the construction manager, the agent for defendant, unequivocally rejected change proposal No. 61 on November 5, 2004, in effect, payment was denied on that date and plaintiffs cause of action accrued (see Lenz Hardware, Inc. v Board of Educ. of Van Hornesville-Owen D. Young Cent. School Dist., 24 AD3d 1278, 1279 [2005]). As a consequence, plaintiff’s March 2005 notice of claim was untimely with respect to those items contained in change proposal No. 61, and Supreme Court should not have held in abeyance plaintiff’s cross motion for leave to file a late notice of claim with respect to those items.
Second, unlike change proposal No. 61, which was clearly for extra work not included in the contract, the balance of the March 2005 notice of claim contains an item identified as ££[n]onpayment of approved and pending applications for payment in the amount of approximately $87,180.” It represents a claim “for monies due arising out of contract” (Education Law § 3813 [1]), and did not accrue until the dates payments were denied (see Albany Specialties v Shenendehowa Cent. School Dist., 307 AD2d 514, 514-515 [2003]). Defendant did not allege when denial of payment occurred and, on this record, it does not appear to be possible to determine whether or when plaintiff’s requisitions were denied. Accordingly, Supreme Court’s denial of summary judgment should be affirmed to this extent.
Lastly, because plaintiff did allege filing of a notice of claim and stated that defendant had “recently” refused payment, the complaint’s omission of a further allegation that the notice was
Crew III, J.E, Carpinello, Rose and Kane, JJ., concur. Ordered that the order is modified, on the law, without costs, by reversing so much thereof as denied defendant’s motion for summary judgment with respect to the items contained in change proposal No. 61; matter remitted to the Supreme Court for consideration of plaintiffs cross motion for leave to file a late claim with respect to change proposal No. 61; and, as so modified, affirmed.
Notably, on July 15, 2005, plaintiff filed an additional notice of claim alleging damages in a sum yet to be determined for defendant’s refusal to allow plaintiff to complete its contract and for other alleged interferences with its work. Obviously, this claim postdates the complaint and is not a part of this action.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.