Clemens Realty, LLC v. New York City Department of Education
Cases that cite this one
5 later published cases cite this decision.
- Kramer v. LOCKWOOD PENSION SERVICES, INC. (District Court, S.D. New York 2009)
- Pintauro v. Saybrook Univ. (New York Supreme Court, Queens County 2025)
- Blaize v. New York City Dept. of Educ. (Appellate Division of the Supreme Court of New York 2022)
- Great Northern Insurance Company v. ADT LLC (District Court, N.D. New York 2022)
- Angelo Capobianco, Inc. v. Brentwood Union Free School District (Appellate Division of the Supreme Court of New York 2008)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Queens County (Kelly, J.), dated January 5, 2007, which granted the defendant’s motion to dismiss the complaint pursuant to CPLR 3211 (a) (5) and (7) and denied its cross motion for leave to amend its complaint.
Ordered that the order is affirmed, with costs.
Education Law § 3813 (2-b) provides that no action or special proceeding shall be commenced against a school district more than one year after the cause of action arose. A breach of contract cause of action arises when the “party seeking payment should have viewed his claim as having been constructively rejected” (Henry Boeckmann, Jr. & Assoc. v Board of Educ., Hempstead Union Free School Dist. No. 1, 207 AD2d 773, 775 [1994] [internal quotation marks omitted]; see James McCullagh Co., Inc. v South Huntington Union Free School Dist., 39 AD3d 480, 481 [2007]; Matter of Mahopac Cent. School Dist. v Piazza Bros., Inc., 29 AD3d 699, 700 [2006]; Capstone Enters, of Port Chester, Inc. v Valhalla Union Free School Dist., 27 AD3d 411, 411-412 [2006]; Dodge, Chamberlin, Luzine, Weber Architects v Dutchess County Bd. of Coop. Educ. Servs., 258 AD2d 434 [1999]). Here, the defendant established that the plaintiffs claim was constructively rejected more than one year before commencement of the action (see James McCullagh Co., Inc. v South Huntington Union Free School Dist., 39 AD3d at 481; D.J.H. Mech. Assoc., Ltd. v Mahopac Cent. School Dist., 21 AD3d 521, 522 [2005]; Dodge, Chamberlin, Luzine, Weber Architects v Dutchess County Bd. of Coop. Educ. Servs., 258 AD2d 434 [1999]). Accordingly, the Supreme Court properly dismissed this cause of action as time-barred.
In addition, the Supreme Court also correctly dismissed the second cause of action seeking to recover damages for breach of duty of care. “[A] simple breach of contract is not to be
In light of this determination, the plaintiff’s remaining contention has been rendered academic. Rivera, J.P., Spolzino, Carni and McCarthy, JJ., concur.