Sirius America Insurance Co. v. Vigo Construction Corp.
Cases that cite this one
17 later published cases cite this decision.
- Spectrum Painting Contractors, Inc. v. Kreisler Borg Florman General Construction Co. (Appellate Division of the Supreme Court of New York 2009)
- Matter of Kemper Independence Ins. Co. v. Brennan (Appellate Division of the Supreme Court of New York 2017)
- QBE Insurance v. Adjo Contracting Corp. (Appellate Division of the Supreme Court of New York 2014)
- QBE Insurance v. Adjo Contracting Corp. (Appellate Division of the Supreme Court of New York 2013)
- QBE Insurance v. Adjo Contracting Corp. (Appellate Division of the Supreme Court of New York 2013)
- ACF Hillside, LLC v. Lambrakis (Appellate Division of the Supreme Court of New York 2012)
- Alejandro v. Liberty Mutual Insurance (Appellate Division of the Supreme Court of New York 2011)
- Blum v. Valentine (Appellate Division of the Supreme Court of New York 2011)
- Stout v. 1 East 66th Street Corp. (Appellate Division of the Supreme Court of New York 2011)
- Brady v. Sintyago (Appellate Division of the Supreme Court of New York 2010)
- Mid City Construction Co. v. Sirius America Insurance (Appellate Division of the Supreme Court of New York 2010)
- Cooper v. Cooper (Appellate Division of the Supreme Court of New York 2010)
- New York Central Mutual Fire Insurance Co. v. Ramirez (Appellate Division of the Supreme Court of New York 2010)
- 161 Hudson v. Sirius America Insurance (Appellate Division of the Supreme Court of New York 2009)
- Guzman v. Nationwide Mutual Fire Insurance (Appellate Division of the Supreme Court of New York 2009)
- Pramco III, LLC v. Partners Trust Bank (Appellate Division of the Supreme Court of New York 2008)
- Quest Builders Group, Inc. v. Deco Interior Construction, Inc. (Appellate Division of the Supreme Court of New York 2008)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Ordered that the cross appeal of the defendant Vigo Construction Corp., is dismissed, as that defendant is not aggrieved by the order (see CPLR 5511); and it is further,
Ordered that the order is reversed insofar as appealed from, on the law, and the cross motion of the defendant Martin C. Gonzalez for summary judgment is granted; and it is further, Ordered that the order is affirmed insofar as cross-appealed from by the plaintiffs; and it is further,
Ordered that one bill of costs is awarded to the defendant Martin C. Gonzalez payable by the respondents-appellants appearing separately and filing separate briefs; and it is further,
Ordered that the matter is remitted to the Supreme Court, Queens County for the entry of a judgment declaring that the plaintiff Sirius America Insurance Company is obligated to defend and indemnify the defendant Vigo Construction Corp., in an underlying action entitled Gonzalez v Vigo Construction Corp., pending in the Supreme Court, Queens County, under index No. 04/10349.
Preliminarily, we note that the cross appeal of the defendant Vigo Construction Corp. (hereinafter Vigo), must be dismissed, because only an “aggrieved party” has standing to appeal (CPLR 5511). Vigo did not seek any relief in the Supreme Court, and the plaintiffs’ motion for summary judgment, which Vigo opposed, was denied (see Anspach v Miller Bluff’s Constr. Corp., 280 AD2d 564 [2001]). Additionally, merely because the order appealed from contains language or reasoning that a party
Insurance Law § 3420 (d) requires an insurer to provide a written disclaimer “as soon as is reasonably possible.” The reasonableness of any delay in providing such written disclaimer is measured from the time when the insurer “has sufficient knowledge of facts entitling it to disclaim, or knows that it will disclaim coverage” (First Fin. Ins. Co. v Jetco Contr. Corp., 1 NY3d 64, 66 [2003]). The insurer bears the burden of justifying any delay (id. at 69). In the instant case, Sirius relied upon a disclaimer dated November 3, 2004 and sent 34 days after it knew or should have known of the basis for denying coverage. Since there was no explanation for that delay, the 34-day delay in disclaiming coverage was unreasonable as a matter of law and thus ineffective (see Matter of Allstate Ins. Co. v Swinton, 27 AD3d 462 [2006]; Pawley Interior Contr., Inc. v Harleysville Ins. Cos., 11 AD3d 595 [2004]; Moore v Ewing, 9 AD3d 484 [2004]; cf. Farmbrew Realty Corp. v Tower Ins. Co. of N.Y., 289 AD2d 284 [2001]; Brooklyn Hosp. Ctr. v Centennial Ins. Co., 258 AD2d 491 [1999]). Under these circumstances, the defendant Martin C. Gonzalez was entitled to judgment as a matter of law on the issue of whether Sirius was required to defend and indemnify Vigo in an underlying action entitled Gonzalez v Vigo Construction Corp., pending in the Supreme Court, Queens County, under index No. 04/10349. Since this is a declaratory judgment action, the matter must be remitted to the Supreme Court, Queens County for the entry of a judgment declaring that Sirius is obligated to defend and indemnify Vigo Construction Corp. in that action (see Lanza v Wagner, 11 NY2d 317, 334 [1962], appeal dismissed 371 US 74 [1962], cert denied, 371 US 901 [1962]). Ritter, J.P., Florio, McCarthy and Dickerson, JJ., concur.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.