RPI Professional Alternatives, Inc. v. Citigroup Global Markets Inc.
Opinion of the Court
Judgment, Supreme Court, New York County (Ira Gammerman, J.H.O.), entered November 5, 2008, awarding plaintiff damages in the principal sum of $1,023,646.14 and dismissing defendant’s counterclaims, unanimously modified, on the law, the principal award reduced to $723,646.14, the first counterclaim reinstated except as it sought recovery of fees already paid under section 22.2 of the agreements, and otherwise affirmed, without costs, and the matter remanded for further proceedings consistent herewith.
Although defendant submitted evidence that it objected to the quality of plaintiffs work on the two projects undertaken for defendant’s Corporate and Investment Banking (CIB) division, there is no evidence of objection to particular invoices or the overall amount billed thereon. Instead, plaintiff offered evidence that defendant actually extended plaintiff’s time to complete those projects and continued to accept the work of its employees. Although the amounts billed thereon exceeded the total estimated costs set forth in the contracts, the parties’ course of dealing may waive a contractual requirement (see Beatty v Guggenheim Exploration Co., 225 NY 380 [1919]). Plaintiff was thus entitled to judgment on the claims related to the CIB projects.
On the other two projects (Smith Barney and Citigroup Private Bank), however, there was a legitimate dispute, timely raised, as to invoices amounting to about $300,000, and judgment was improperly granted thereon.
Since defendant cross-moved for summary judgment on the merits of its breach-of-contract counterclaim, the court had authority to search the record and grant summary judgment in favor of plaintiff, the nonmoving party, to the extent the record established its entitlement thereto (CPLR 3212 [b]; DCA Adv. v Fox Group, 2 AD3d 173 [2003]). The court properly dismissed so much of the first counterclaim as sought recovery of fees paid, since the record establishes that defendant did not comply with the contractual prerequisites for such recovery, namely, providing plaintiff with notice of the claimed defects in its work prod-
The provision of the contract precluding plaintiff from collecting interest or late fees on overdue payments does not bar the court from assessing prejudgment interest as mandated by CPLR 5001 (b) to compensate plaintiff (id.). However, under the terms of the contract, the earliest ascertainable date on which the account-stated cause of action existed was 60 days after the last invoice was sent, or May 27, 2006 (see Richard Friedman Assoc., CPA PC v Jereski, 26 AD3d 296 [2006]). Concur—Gonzalez, P.J., Tom, Sweeny and Acosta, JJ.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.