Isacowitz v. Halpern Construction, Inc.
Opinion of the Court
Summary judgment is precluded by triable issues of fact including whether plaintiff breached its contracts with the construction manager by failing to pay its material suppliers; whether plaintiff failed to perform its contracts in accordance with their time-of-the-essence provisions; whether the construction manager properly terminated plaintiff for untimely performance; and whether the construction manager’s noncompliance with the agreements’ three-day notice to cure requirement was excusable on the ground of plaintiffs alleged abandonment of the project. Concur—Tom, J.P., McGuire, Acosta and Freedman, JJ. [Prior Case History: 2009 NY Slip Op 30180(U).]