Town of Islip v. H.T. Schneider Associates
Opinion of the Court
In an action to recover damages for breach of contract, negligence, and continuing nuisance, the defendants appeal, as limited by their brief, from so much an order of the Supreme Court, Suffolk County (R. Doyle, J.), dated October 7, 2008, as denied that branch of their motion which was for summary judgment dismissing, as time-barred, the third cause of action to recover damages for a continuing nuisance.
Ordered that the order is reversed insofar as appealed from, on the law, with costs, and that branch of the defendants’ motion which was for summary judgment dismissing the third cause of action to recover damages for a continuing nuisance as time-barred is granted.
In this action, the plaintiff, Town of Islip, alleged that the defendant construction companies entered into a contract with the County of Suffolk to construct a sewer system and related improvements, of which it was a third-party beneficiary. The plaintiff claimed that, during the course of constructing the sewers, the defendants improperly backfilled sewer trenches and, in doing so, failed to provide adequate support for roadways and other surface structures. The plaintiff further claimed that, as a result, it incurred costs in repairing those roadways and structures. The plaintiff asserted three causes of action against the defendants to recover damages for breach of contract, negligence, and continuing nuisance. The Supreme Court granted those branches of the defendants’ motion which were for summary judgment dismissing the causes of action sounding in breach of contract and negligence on the ground that those causes of action were barred by the statute of limitations. However, the Supreme Court denied that branch of the motion which was for summary judgment dismissing the cause of action sounding in continuing nuisance, and the defendants appeal from that portion of the order. We reverse the order insofar as appealed from.
“[N]o matter how a claim is characterized in the complaint—negligence, malpractice, breach of contract—an owner’s claim arising out of defective construction accrues on date of completion, since all liability has its genesis in the
Case-law data current through December 31, 2025. Source: CourtListener bulk data.