New York Trenchless, Inc. v. Hallen Construction Co.
Opinion of the Court
The plaintiff then commenced this action against the defendant, seeking, inter alia, in effect, to recover damages incurred as a result of delay in the performance of the contract. The alleged damages included the sum of $205,402.53 in damages for delays, lost time, and extra work. The defendant moved, inter alia, for summary judgment dismissing that part of the complaint, on the ground that this claim was barred by the exculpatory clause in the Subcontract. In support, it submitted the Subcontract, and the claim the plaintiff filed with National Grid, in which the plaintiff stated that it had followed National Grid’s drilling plan. In opposition, the plaintiff submitted the affidavit of its president, who stated that the defendant acted in bad faith by providing the plaintiff with faulty drilling plans. In the order appealed from, the Supreme Court, inter alia, granted that branch of the defendant’s motion which was for summary judgment dismissing so much of the complaint as, in effect, sought to recover damages incurred as a result of delay in the performance of the contract. We affirm the order insofar as appealed from.
Clauses in construction contracts which bar contractors from recovering damages for delay in the performance of the contract
Here, the defendant demonstrated, prima facie, that the exculpatory clause should be enforced (see generally Zuckerman v City of New York, 49 NY2d 557, 562 [1980]). In opposition, the plaintiff submitted an affidavit that was conclusory, vague, and contradicted by documentary evidence. Such conclusory allegations are insufficient to raise a triable issue of fact in opposition to a motion for summary judgment (see McGrath v Parker, 4 AD3d 457 [2004]).
The plaintiffs remaining contentions are without merit.
Accordingly, the Supreme Court properly granted that branch of the defendant’s motion which was for summary judgment dismissing so much of the complaint as, in effect, sought to recover damages incurred as a result of delay in the performance of the contract. Mastro, J.E, Skelos, Leventhal and Roman, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.