25th Avenue v. Delos Insurance
Cases that cite this one
9 later published cases cite this decision.
- Tower Insurance v. Alvarado (Appellate Division of the Supreme Court of New York 2011)
- Integrated Construction Services, Inc. v. Scottsdale Insurance (Appellate Division of the Supreme Court of New York 2014)
- The Travelers Indemnity Company v. Northrop Grumman Corporation (District Court, S.D. New York 2019)
- Aspen Insurance Uk Ltd. v. Nieto (Appellate Division of the Supreme Court of New York 2016)
- Vale v. Vermont Mutual Insurance Group (Appellate Division of the Supreme Court of New York 2013)
- Vale v. Vermont Mutual Insurance Group (Appellate Division of the Supreme Court of New York 2013)
- Ocean Gardens Nursing Facility, Inc. v. Travelers Companies, Inc. (Appellate Division of the Supreme Court of New York 2012)
- Utica First Insurance v. Vazquez (Appellate Division of the Supreme Court of New York 2012)
- Columbia University Press, Inc. v. Travelers Indemnity Co. of America (Appellate Division of the Supreme Court of New York 2011)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In an action for a judgment declaring that the defendant is obligated to defend and indemnify the plaintiffs in an underlying action entitled Jaramillo v Colonial Constr., LLC, commenced in the United States District Court for the Eastern District of New York under docket No. 07-2142, the plaintiffs appeal from (1) an order of the Supreme Court, Nassau County (Falmieri, J.), entered May 4, 2010, which granted the defend
Ordered that the appeal from the order is dismissed; and it is further,
Ordered that the judgment is reversed, on the law, the defendant’s motion for summary judgment is denied, and the complaint is reinstated, and the order is modified accordingly; and it is further,
Ordered that one bill of costs is awarded to the plaintiffs.
The appeal from the intermediate order must be dismissed because the right of direct appeal therefrom terminated with the entry of judgment in the action (see Matter of Aho, 39 NY2d 241 [1976]). The issues raised on the appeal from the order are brought up for review and have been considered on the appeal from the judgment (see CPLR 5501 [a] [1]).
The plaintiff 25th Avenue, LLC (hereinafter the owner), owns premises at 45-15 25th Avenue in Queens, where the plaintiff Colonial Construction and Development, LLC (hereinafter the general contractor), managed a construction project. On June 8, 2005, Hermes Jaramillo, an employee of nonparty subcontractor Biltmore Contracting, Inc., was allegedly injured on the job. In May 2007 Jaramillo commenced the underlying action in the United States District Court for the Eastern District of New York against the owner and general contractor, alleging violations of the Labor Law. Thereafter, the plaintiffs filed a claim seeking a defense and indemnification under their insurance policy with the defendant Delos Insurance Company (hereinafter the insurer). The insurer denied coverage, inter alia, on the ground of late notice of claim.
The plaintiffs commenced this action for a judgment declaring that the insurer is obligated to defend and indemnify them in the underlying action. The insurer moved for summary judgment, and the Supreme Court granted the motion, holding that the insurer had established, prima facie, the plaintiffs’ unreasonable delay in giving notice of the occurrence, and the plaintiffs, in opposition, had failed to raise a triable issue of fact as to whether their delay was based upon a reasonable, good faith belief in nonliability. Contrary to the conclusion of the Supreme Court, we hold that the plaintiffs raised a triable issue of fact sufficient to defeat the insurer’s motion.
Where, as here, a policy of liability insurance requires that
Here, although the plaintiffs were aware on the date of the incident that Jaramillo had been injured and had obtained medical care, other evidence they submitted in opposition to the insurer’s summary judgment motion raises a triable issue as to their reasonable, good faith belief of nonliability excusing their delay in notifying the insurer, including statements by the subcontractor that Jaramillo was fine and had returned to work, the subcontractor’s proof prior to commencement of the work of its own liability and workers’ compensation insurance, the subcontractor’s entry into a “hold-harmless” agreement with the general contractor, the owner’s and general contractor’s lack of supervision or control over the work done by the subcontractor’s employees, and the small size of the plaintiffs’ businesses and the principals’ relative lack of experience in the construction industry and lack of any experience with construction site injuries. Under the particular circumstances of this case, the plaintiffs raised a triable issue of fact as to the reasonableness of their belief of nonliability (see Bauerschmidt & Sons, Inc. v Nova Cas. Co., 69 AD3d 668 [2010]; R & L Richmond Ave. Corp. v Public Serv. Mut. Ins. Co., 56 AD3d 643 [2008]; North Country Ins. Co. v Jandreau, 50 AD3d 1429 [2008]; St.