Bronx Committee for Toxic Free Schools v. New York City School Construction Authority
Opinion of the Court
By failing to make any mention of the need for long-term monitoring in the initial EIS, SCA frustrated the purpose of SEQRA, which is to subject agency actions with environmental impact to public scrutiny (see ECL 8-0109; 6 NYCRR 617.1 [c]). Indeed, there is no record evidence that SCA took the requisite “hard look” at the issue of long-term maintenance and monitoring of remediation measures until 2008, when it issued its final site management plan (see Matter of Riverkeeper, Inc. v Planning Bd. of Town of Southeast, 9 NY3d 219, 231-232 [2007]). This constitutes a failure of the agency’s obligations under SEQRA (see Matter of Pyramid Co. of Watertown v Planning Bd. of Town of Watertown, 24 AD3d 1312 [2005], appeals dismissed 7 NY3d 803 [2006]; Matter of Penfield Panorama Area Community v Town of Penfield Planning Bd., 253 AD2d 342, 349 [1999]).
Nor does the fact that SCA was acting under the BCP shield the remediation measures from SEQRA scrutiny. BCP remediation measures that “commit the . . . agency to specific future uses or actions” are subject to SEQRA review (6 NYCRR 375-3.11 [b] [1] [i]). The final site management plan provided that the Mott Haven School Campus site could be used for a school campus only, thus committing SCA to a specific site use. In any event, the BCP remediation measures applied only to the BCP area, whereas most of the site was not subject to the BCP and nonetheless was subject to SEQRA review.
We reject respondents’ contention, raised in their motion for renewal and reargument, that SCA’s development of the final site management plan (SMP), which entailed circulation of a draft for public comment, obviates any need for a supplemental EIS. The SMP is not a supplemental EIS, and respondents have not established that the development of the SMP followed the procedures for the preparation of a supplemental EIS. Since SEQRA procedures must be strictly complied with (see Matter of King v Saratoga County Bd. of Supervisors, 89 NY2d 341, 347 [1996]), SCA’s issuance of the final SMP did not cure the deficiencies in the final EIS. Concur — Gonzalez, P.J., Tom, Andrias, Moskowitz and Freedman, JJ.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.