Gorham v. Reliable Fence & Supply Co.
Opinion of the Court
Reliable moved for summary judgment dismissing the complaint and all cross claims insofar as asserted against it. Thereafter, Premier cross-moved for summary judgment dismissing the complaint and all cross claims insofar as asserted against it. Racanelli also cross-moved for summary judgment dismissing the complaint and all cross claims insofar as asserted against it. In an order dated November 10, 2009, the Supreme Court, inter alia, denied Reliable’s motion, granted those branches of the respective cross motions of Premier and Racannelli which were for summary judgment dismissing the complaint and all cross claims insofar as asserted against each of them, and granted that branch of Racanelli’s cross motion which was for summary judgment on its cross claim for contractual indemnification insofar as asserted against Reliable. In an order dated Juen 18, 2010, the Supreme Court, upon reargument, adhered to its prior determination, and granted that branch of Premier’s cross motion which was for summary judgment on its cross claim for contractual indemnification insofar as asserted against Reliable.
However, the Supreme Court, upon reargument, should not have adhered to its prior determination granting that branch of Racanelli’s cross motion which was for summary judgment dismissing Reliable’s cross claims insofar as asserted against it. Racanelli made a prima facie showing of entitlement to judgment as a matter of law by submitting, inter alia, the affidavit of its project manager, who stated, in effect, that Racanelli did not have control over the work site (see Soto v City of New York, 244 AD2d 544, 545 [1997]; cf. Keating v Nanuet Bd. of Educ., 40 AD3d 706, 708-709 [2007]). However, in opposition, Reliable raised triable issues of fact, inter alia, as to whether Racanelli had control over the work site. In this regard, Reliable submitted deposition testimony indicating that Racanelli employees inspected the subject gate to make sure that it was properly installed and that a Racanelli employee inspected all of the work of its subcontractors.
Moreover, it was premature to grant those branches of the cross motions of Premier and Racanelli which were for summary judgment on their respective cross claim and third-party cause of action for contractual indemnification against Reliable (see Brasch v Yonkers Constr. Co., 306 AD2d 508, 510-511 [2003]; Rodriguez v Savoy Boro Park Assoc. Ltd. Partnership, 304 AD2d 738, 739 [2003]).
Case-law data current through December 31, 2025. Source: CourtListener bulk data.