Doin v. Champlain Bluffs Development Corp.
Opinion of the Court
Defendant Champlain Bluffs Development Corporation is the fee owner of certain real property located on Lake Champlain in the Town of Plattsburgh, Clinton County known as Singing Sands Beach (hereinafter the beach). When this action was last before our Court (68 AD3d 1605 [2009], lv dismissed 14 NY3d
Upon remittal, in November 2010, Supreme Court held a hearing at which the parties initially vigorously disputed whether, at that point, a bona fide decision had been made by the existing property owners with deeded beach rights to restore the beach to its original condition. Plaintiffs introduced evidence of a vote taken in May 2010 by all property owners with beach rights at the time of our December 2009 decision that approved restoration by a vote of 18 to 2, with one party abstaining. Dame testified that, acting on behalf of Champlain, he had since granted beach access to 18 other existing property owners in the Bluff Point area and these grantees voted on June 1, 2010 in favor of leaving the beach in its current state.
Neither party appealed from that order. Plaintiffs, however, moved for reargument, asking the court to also declare that the votes collected by Dame were invalid because Champlain may not grant beach rights independent of a sale of the property benefitted by those rights. In opposition to that motion, Champlain successfully argued that the issue was rendered moot because the parties had stipulated that Dame’s 18 additional voters had no say in the vote to restore the property. Nevertheless, Champlain thereafter failed to post the bond required by Supreme Court’s order, prompting plaintiffs to move to modify that order, seeking a money judgment and permission to undertake the restoration themselves. Champlain and Dame opposed the motion, reviving their argument that the June 2010 vote extinguished Champlain’s obligation to restore the beach. In May 2011, the court partially granted plaintiffs’ motion in a judgment awarding each plaintiff $6,279.60 — that is, one tenth of the cost of restoring the beach to each of the 10 townhouse interests owned by plaintiffs — and vacated those portions of its December 2010 order that required Champlain to restore the beach. Thereafter, Champlain and Dame refused plaintiffs’ efforts to begin restoration of the beach, relying on the June 2010 vote. Plaintiffs now appeal, and Champlain and Dame cross-appeal, from Supreme Court’s judgment.
As a threshold matter, because the judgment appealed from is against Champlain only, and not Dame in his individual capacity, Dame is not an aggrieved party and his pro se cross appeal must be dismissed (see CPLR 5511; Smith v Town of Colonie, 60 AD3d 1121, 1122 [2009]; accord Berrechid v Shahin, 60 AD3d 884 [2009]).
Turning to the merits, we hold that Champlain unjustifiably failed to comply with Supreme Court’s directive that the beach be restored at Champlain’s expense. Champlain’s reliance on the June 2010 vote at this juncture is completely unavailing given its stipulation, after that vote, that the May 2010 vote to
Further, Champlain has proffered no evidence to support the proposition that the June 2010 vote was valid. In our prior decision, we held that Champlain could create additional voting rights “by conveying other residential properties from its remaining land holdings with rights to use the beach” (68 AD3d at 1610 [emphasis added]).
We also reject Champlain’s suggestion on appeal that, in our previous decision, we held that this provision restricting Champlain’s right to grant beach access was eliminated by the doctrine of merger. We acknowledged that because Champlain is the successor in interest to both original parties to the agree
Champlain did not appeal from Supreme Court’s December 2010 order assessing the cost of restoration and, on appeal, does not challenge the amount assessed, but rather argues that any award is inappropriate. Thus, while the amount determined by Supreme Court is not at issue and we hold that Champlain must bear the cost of restoration, we agree that the individual plaintiffs are not entitled to damages but, rather, the judgment should go to plaintiffs, collectively, to be used to restore the beach to its original condition, and Champlain shall remain responsible for any reasonable cost of restoration exceeding the amount of the judgment. Any interference by Champlain or its principal, successors or assigns with plaintiffs’ restoration of the beach or any failure on the part of Champlain or its principal, successors or assigns to cooperate fully with such efforts shall be subject to sanctions to be determined by the court. Cooperation shall include the execution of any applications for permits, if necessary to complete the restoration work.
Peters, P.J., Malone Jr., Kavanagh and Garry, JJ., concur. Ordered that the judgment is modified, on the law, without costs, by reversing so much thereof as vacated the obligation of defendant Champlain Bluffs Development Corporation to pay for any and all costs related to the restoration of Singing Sands Beach and that awarded monetary judgments to the individual plaintiffs; (1) it is declared that plaintiffs are entitled to restore the beach and said defendant, and its successors or assigns, shall cooperate and not interfere with plaintiffs’ restoration efforts, (2) the sum of $62,796 with interest from December 6, 2010 is awarded to plaintiffs, collectively, for the exclusive use of restoring the beach as contemplated by the vote taken in May 2010 by plaintiffs and the other voting property owners as of December 31, 2009, and (3) said defendant shall pay for any and all costs related to restoration of the beach; and, as so modified, affirmed.
Ordered that the cross appeal is dismissed, without costs.
. A separate action involving some of the same parties has also recently been before this Court (Doin v Dame, 82 AD3d 1338 [2011], lv denied 17 NY3d 713 [2011]).
. The agreement was incorporated into the conveyance to one of Champlain’s predecessors in title and into the conveyances to each plaintiff (see id. at 1606-1607).
. These grants were not made as part of a sale, but given to existing Bluff Point property owners, many of who, according to plaintiffs, did not purchase their property from Champlain. Dame conceded at the hearing that the only consideration he received in exchange for granting beach access was the promise of the grantee that he or she would vote against restoration of the beach.
. We also stated that “Champlain, as the successor in interest to Bluff Point Development, has the right to assign additional unexclusive beach rights when selling other residential property at Bluff Point” (68 AD3d at 1610 n 2 [emphasis added]).