Appellate Division of the Supreme Court of New York, 2012

Everest General Contractors v. New York City Housing Authority

Everest General Contractors v. New York City Housing Authority
Appellate Division of the Supreme Court of New York · Decided October 9, 2012
99 A.D.3d 479; 951 N.Y.2d 671
Everest General Contractors v. New York City Housing Authority

Opinion of the Court

Plaintiff failed to provide timely written notice of its intention to make a claim for damages arising out of defendant’s delay, a condition precedent to commencing an action pursuant to section 23 of the parties’ contract (see A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d 20, 30-31 [1998]; 4-A Gen. Contr. Corp. v New York City Hous. Auth., 28 AD3d 261 [1st Dept 2006]). Plaintiffs July 26, 2004 letter which was allegedly *480sent to defendant, does not satisfy the requirement of written notice. The letter was not designated as a notice of claim, gave no indication of an intent to make a claim, and was sent long before the March 2006 accrual of plaintiffs claim rather than within 20 days of the date the claim arose (see Bat-Jac Contr. v New York City Hous. Auth., 1 AD3d 128 [1st Dept 2003]).

We have considered plaintiffs remaining contentions and find them unavailing. Concur — Tom, J.R, Mazzarelli, Catterson, Renwick and DeGrasse, JJ.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.