Erie Materials, Inc. v. Universal Group of New York, Inc.
Opinion of the Court
In response to plaintiffs motion, Colonial argued that there were issues of fact as to whether all of the materials for which plaintiff sought payment were actually delivered to and used on the project site, as required by State Finance Law § 137 (1). Colonial submitted, among other things, an attorney affirmation and the affidavit of Donald Piel, Plank’s project manager. Piel alleged, as relevant here, that his review of invoices relating to the Malta project revealed that some of the materials supplied by plaintiff had been picked up by Universal, rather than delivered directly to the project site. In addition, based upon Piel’s inspection of the project site, it was evident that some of the materials supplied by plaintiff had not been installed on the Malta project.
However, Colonial now contends — in our view, for the first time — that the burden of showing the existence of material issues of fact never shifted to Colonial in the absence of proof that plaintiff provided the disputed roofing materials to Universal in good faith and that Universal’s alleged diversion of such materials from the project was without plaintiffs knowledge or consent. We agree with plaintiff that, inasmuch as Colonial took the position in Supreme Court that the “diversion exception” did not apply to claims under State Finance Law § 137,
We are also unpersuaded that Supreme Court erred in awarding counsel fees to plaintiff. While the fact that Colonial’s defense to the underlying claim was unsuccessful is not enough to warrant an award of counsel fees pursuant to State Finance Law § 137 (4) (c) (see Beninati Roofing & Sheet Metal Co. v Gelco Bldrs., 279 AD2d 412, 412-413 [2001]), Colonial aggressively defended against plaintiffs entire claim, although only a relatively minor portion thereof was actually in dispute. More
To the extent not specifically addressed herein, Colonial’s remaining contentions have been considered and found to be lacking in merit.
Mercure, J.P., Rose, Kavanagh and Egan Jr., JJ., concur. Ordered that the order is affirmed, with costs.
. Piel asserted that the roofing materials picked up by Universal from plaintiff as set forth on three separate invoices totaling approximately $7,500 were “neither delivered to the [pjroject site, nor used or stored” thereon. He also averred that some of the materials listed on a fourth invoice were not used in connection with the Malta project, although they were delivered to the project site.
. The diversion exception is a doctrine created under the Lien Law, which establishes an exception to the general rule that a material supplier’s entitlement to a lien requires “that the goods provided [to a subcontractor] be expended or used [so] that they become a part of the construction project” (Plattsburgh Quarries v Falcon Indus., 111 AD2d 1069, 1070 [1985]; see Giant Portland Cement Co. v State of New York, 232 NY 395, 403-406 [1922]; Matter of P.T. & L. Constr. Co. v Winnick, 59 AD2d 368, 369-370 [1977]) and permits such a lien in cases where the materials are diverted from the project without the supplier’s knowledge or consent after the supplier provided the materials in good faith and the supplier no longer had control thereof (see Giant Portland Cement Co. v State of New York, 232 NY at 403; Matter of P.T. & L. Constr. Co. v Winnick, 59 AD2d at 370). While no appellate court in New York has addressed whether the diversion exception applies to bond claims made pursuant to State Finance Law § 137, plaintiff asserts on appeal, and Colonial now concedes, that such application is proper. In view of our determination herein, we need not address the merits of that assertion.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.