Huck v. Bischoff
Opinion of the Court
The action is on a promissory note. The defense is that the note was given to plaintiff’s assignor for a gas machine, which said assignor warranted had been accepted by the Board of Fire Underwriters and was on their accepted list, and also that said assignor guarantied that said machine was safe and reliable, and made in a workmanlike manner from heavy, galvanized sheet steel. It was conceded at the trial that the machine in question was not on the accepted list of the Board of Underwriters, and defendant also •presented evidence to show that the machine was unsafe, unreliable, and worthless. The justice gave judgment .for defendant.
On appeal, plaintiff urges improper admission of evidence, a waiver ■of the breach of warranty, and that the judgment was against the
Judgment affirmed, with costs. All concur.