Sulinski v. Leahy
Opinion of the Court
This action was brought to recover the balance claimed by the plaintiff to be due him upon a contract, and arose out of the following facts: The defendant had a written con
“New York, July 14th, 1902.
“Thomas B. Leahy Esq., 9 East 42 Street—Dear Sir: We propose to furnish labor and material for laying the contract asphalt and iron clad pavement, also expanded metal for floor weighing 85 lbs per 100 square feet at Engine Company No. 9, located at 55 E. B’way; according to the plans and specifications made by Supt. of Buildings of Fire Dept. and under his direction;
“Work guaranteed for five years after date of completion; for the sum of (8965.00) Nine Hundred and Sixty-five Dollars.
“Yours truly, Eagle Artificial Stone Co.,
“Per J. Sulinski.”
The offer contained in the letter was accepted, and the plaintiff performed the work and furnished the materials called for therein.
The contract made between the city and the defendant provided that what are called “wood centers” should be used. These “wood centers” are wooden erections or false work put in place to support a concrete floor while it is setting and hardening, and are subsequently removed. Neither the plaintiff’s proposal nor the defendant’s acceptance thereof in any way refer to the “wood centers.” After the plaintiff’s proposal had been accepted, and prior to his beginning of the work thereunder, the defendant claimed that the plaintiff had agreed to furnish the wood centers, and the plaintiff denied such claim. Thereupon the defendant caused the wood centers to be made, and in this action counterclaimed for their value, viz., $57.46. This counterclaim was not allowed. The written contract being silent upon that subject, both sides had recourse to oral testimony at the trial upon the question as to whether or not the plaintiff had agreed to furnish the wood centers, and upon this question of fact the trial judge found in favor of the plaintiff.
The claim of the appellant that because his contract with the city in its plans and specifications called for “wood centers,” and the plaintiff had contracted to do certain labor and furnish certain material “according to the plans and specifications made,” etc., the plaintiff was thereby required to furnish “wood centers,” is untenable. The plaintiff’s proposal was only to “furnish labor and material for laying concrete asphalt and ironclad pavement and expanded metal floor,” and these specified articles were to be “according to plans and specifications,” and there is no claim made that, so far as these articles are concerned, he failed to perform his contract, and the plaintiff could not be required to “put in wood centers in the floor construction as required by the plans and specifications,” etc., unless he had contracted with the defendant so to do. As before stated) upon this disputed question of fact the version of the-plaintiff was believed by the trial court. The trial court also, evidently, found that the delay of the plaintiff in commencing the work was due to the defendant’s failure to insert the wood centers, and that his counterclaim for damages for such delay was unfounded.
FREEDMAN, P. J., concurs.
Dissenting Opinion
The plaintiff, according to his complaint, “made and entered into a contract with the defendant, whereby the plaintiff agreed to furnish material for laying concrete floor, asphalt, and ironclad pavement, also expanded metal for floor, weighing 85 pounds to the hundred square feet, at Engine Co. No. 9 house, located at 55 East Broadway, Manhattan, New York City, in accordance with the plans and specifications made by the superintendent of buildings of the fire department,” and “duly completed the same in accordance with said plans and specifications, and furnished the materials and performed the labor therein called for.” In his action to recover balance due, the defendant counterclaims, among other things, for $57.46, for the failure and refusal of the plaintiff “to put in wood centering in the floor construction as required by the plans .and specifications of the superintendent of buildings of the fire department,” and that the defendant, in consequence of such failure, was obliged to and did put in the same himself. This the trial justice disregarded, notwithstanding the admission of the plaintiff at the trial that he (the plaintiff) did not lay the wood centering, and that^'it is called for in the specifications.”- Pleading his claim upon a contract according to specific plans and specifications and performance thereunder, the plaintiff may not prove an earlier understanding with reference to his obligations which have been reduced to writing and by himself admitted to be in the specifications with reference to which he contracted. The judgment in his favor, in 'disregard of the claim of the defendant pleaded and proved, was therefore improper, and so should be modified by deducting therefrom the sum of $57.46, and, as thus modified, affirmed, without costs to either party upon this" appeal.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.