City of New York v. American Railway Traffic Co.
Opinion of the Court
The city of ¡New York brought this action to recover from the defendants $300 for damages alleged to have been sustained by it as a result of a breach on the part of the defendants of a contract bearing date - October 28, 1902. The contract was originally made between the plaintiff and one Kennedy: and attached to the contract and
On September 4, 1903, the original contract was assigned with the consent of the plaintiff and the sureties to the American Railway Traffic Company, a Rew Jersey corporation; and, on April 1, 1904, the original contract was assigned with the consent of the same parties to the American Railway Traffic Company, a Rew York corporation, and one of the defendants in this action.
The claim of the plaintiff is predicated upon clause TJ of the original contract. This clause provides as follows:
“ (U) That the contractor during the performance of this contract shall take all necessary precautions and place proper guards for the prevention of accidents; and shall so conduct and carry on the dumping, placing and final disposition of the materials, garbage, etc., and so operate the dumps, dumping places, receptacles, scows, and other conveyances and plant at all times that accidents shall be prevented, and the party of the first part shall suffer no injury or damage therefrom; and shall put up and keep at night sufficient lights, and at all times proper danger signals; and shall indemnify and save harmless the said party of the first part from all damages and costs to which it may be put, by reason of injury to person or to property resulting from negligence or carelessness in the operation of the plant or in guarding the same, or from any improper materials or apparatus used in connection therewith, or by reason or on account of any act or omission of said contractor, or the agents or servants thereof; that, said contractor shall be liable for all damages to person or to property arising from his negligence or that of his employees, and for all violations of law, city ordinances or government regulations.”
The answer of the defendants pleads" a general denial and, as a separate defense, that whatever damages the plaintiff sustained were due to its own negligence or to the negligence of a third party or parties over whom the defendants had no control. The plaintiff contends that it is immaterial whether the accident was due to the plaintiff’s own negligence or the negligence of a third party, as clause U makes the contractor an insurer against any and all accidents caused by the operation of the dumps and receptacles. If we give to this clause a strict and narrow interpretation, it is evident that, whenever the city sustains a loss, it imposes liability upon the contractor in two classes of cases; first, whenever an accident happens and, second, whenever an accident happens through the negligence of the contractor, his servants or agents. Under such a strict and narrow view of the clause, it is difficult to see what necessity there was for the insertion of the provision that the contractor should be liable in case of negligence. If the contractor was intended to be made liable in all cases, what reason was there for providing, in the same clause, that he should be liable in the specific case of negligence?
We do not think that so narrow an interpretation would give effect to the intention of the parties, nor would it give effect to all parts of the clause. We think that the general and comprehensive terms in the' first part of the clause are limited by the latter portion which restricts the contractor’s liability to cases of negligence. The general part of the clause, which makes the contractor liable for all accidents causing loss to the city, is necessarily restricted by the specific -and particular statement that the contractor is liable for accidents caused by negligence. We think that the special provision providing for liability in case of ■ negli
We think, therefore, that the learned court below properly construed the contract and that, in the absence of proof of negligence, the plaintiff was not entitled to recover.
It is claimed by the appellant that the evidence established the negligence of the contractor. In reference to this contention it is sufficient to point ont that the evidence pre-. sented merely a question of fact, and that no reason exists for disturbing the conclusion reached by the trial justice.
Bijur, J., concurs j Lehman, J., concurs in result.
Judgment affirmed, with costs.