Vacuum Cleaner Co. v. Broadway Cortlandt Co.
Opinion of the Court
The complaint alleges, in substance, that the plaintiff contracted with defendants to install a vacuum cleaner plant in a certain building, and that it should receive final payment, upon the issuance by the architect of
The allegation of complete performance of the contract, which is clearly made by the pleader, if proved, makes out a case of unreasonable refusal on the part of the architect to furnish the certificate, and, therefore, excuses its production as a condition precedent to payment. Ross v. City of New York, 85 App. Div. 611, 612; Bowery Savings Bank v. Mayor, 63 N. Y. 336.
Judged by the pleading alone, there seems also to be a sufficient allegation of acceptance of the plant (the character of which is not disclosed by the complaint) to constitute a waiver by defendants of the issuance of the certificate as a prerequisite to payment. See Smith v. Alker, 102 N. Y. 87; Duell v. McCraw, 86 Hun, 331; Tilden v. Buffalo Office-Bldg. Co., 27 App. Div. 510.
Seabury and Guy, JJ., concur.
Judgment reversed and new trial granted, with costs to appellant to abide event.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.