Levy v. O'Reilly
Opinion of the Court
The action is for work, labor, and services; the defense, a general denial.
Plaintiff testified that he was engaged to do the work necessary “to vacate” a tenement house department “violation” on an unfinished fire escape, for which he gave an estimate of $180. He says he completed the work, and was paid only $90, and that the contract “was a verbal conversation.”
Defendants produced a written contract in the form of a proposal by plaintiff and an acceptance by defendant "to remove fire escape violation No. 28,822/09” for $180 “to be paid as follows: Ninety dollars ($90) on completion of work. Ninety dollars ($90) when J have obtained all dismissals on said violation from the tenement Louse department.” Plaintiff’s name appears affixed thereto by a rubber stamp.
In lieu of a certificate that the violation had been dismissed, plaintiff produced a letter from the department to himself, setting forth that the construction of the new fire escape conforms to the
Plaintiff asserted he was in the habit of signing all his letters with a rubber stamp. Two other letters, besides the contract, were produced so signed. Defendant Dahn says that the contract was dictated by him to plaintiff’s stenographer over the telephone. It was subsequently signed and mailed to them from plaintiff’s office. They received it the next day.
A representative of the tenement house department testified that all the work covered by the violation had not been done. Some of it still remains to be done. The violation has never been dismissed.
Plaintiff’s stenographer testified that the contract was dictated to her over the telephone; that she signed it in plaintiff’s name with the rubber stamp, with which plaintiff always signs his letters— she did not know why. She also said she mailed the letter right away before the plaintiff returned; that she had been in his office four years, and during that time had always stamped all his letters and contracts with the rubber stamp signature.
The violation has never been removed. Plaintiff cannot recover until this condition of the contract has been complied with.
The judgment must be reversed, with costs, and the complaint dismissed, with costs. All concur.