Kuhn v. Ebstein Bros.
Opinion of the Court
The record on this appeal is meager and does not satisfactorily bring but the relations between the parties. Plaintiff sues for the value of certain display cards and “cut-outs” tendered to defendant pursuant to a contract and refused. It appears that on August 15, 1912, the defendant signed a contract calling for the delivery of 1,000 “cut-outs.” This was on an order blank of the plaintiff which contained a printed notice reading in part that the plaintiff—
“does not bind itself to the exact date of delivery, but goods will be delivered as near date specified as possible; that we shall not be held liable for any failure or delay or interruption in the performance of this contract caused by strike,” etc.
The defendant testified that it was expressly agreed that delivery was to be made not later than September 20th, and it is apparent from the whole record that there were prior negotiations in which September 20th was frequently mentioned as the date of the delivery. Proofs were presented to defendant in September at a date which does not appear, and were approved by him. On October 8th defendant wrote plaintiff, canceling the contract for failure to make delivery. At or about that time, at a date which does not clearly appear, but was probably October 12th, plaintiff notified defendant by telephone that he had 300 or 400 “cut-outs” ready for delivery, but defendant refused to accept them. Either immediately subsequent to October 8th or October 12th, and at a time that does not clearly appear, plaintiff sent defendant six “cut-outs” which were retained by defendant. This is not contradicted. Tender of the remainder of the contract was made on November 12th and refused.
As the record stands, this court cannot attempt to state what was the effect of the strike clause in the contract, or what was the effect of the
A new trial will undoubtedly amplify the meager record on the important matter of the sequence of negotiations and the dates thereof, and possibly on the circumstances surrounding the delivery of the six “cut-outs.”
Judgment reversed, and a new trial ordered, with costs to appellant to abide the event. All concur.