Levenson Wrecking Co. v. New York Central & Hudson River Railroad
Opinion of the Court
The action is brought to recover the value of certain lumber delivered to the defendant to transport to the plaintiff as consignee from White Plains, in this state, to the place of business of the plaintiff in Hoboken, N. J. The lumber was delivered to the defendant at White Plains and carried by it to Hoboken. The defendant refused to deliver the lumber until certain charges for demurrage were paid by plaintiff, which the latter declined to pay. The determination of the issues depends upon the point as to whether under the circumstances the defendant was justified in refusing so to make delivery. I do not think the proof supports the judgment for the plaintiff. The plaintiff refused to pay said demurrage because it had not been duly notified of the 'arrival of the shipment, and because in any event a higher rate of demurrage was demanded than would have been payable had the contract been properly performed by defendant. The plaintiff contended that the contract called' for an all rail transportation and that the defendant acted without authority in using a barge, for part of the way. Accordingly it should not have been asked to pay demurrage at the boat rate, which was ten dollars a day, instead of the car rate, which was one dollar a day.
The claim that the plaintiff was not- seasonably in- ' formed of the arrival of the goods was not sustained on the trial. It is uncontradicted that the lumber arrived at Hoboken on the 30th of June, 1915. Although the president of the plaintiff testified that up to the
There was nothing in the bill of lading that prevented the defendant from using a barge for the purpose of finally transporting the goods to the place of destination and in fact it is difficult to see how such a delivery could have been made, in ordinary course from White Plains to Hoboken without the use of water transportation. The charge for demurrage demanded was proper in the circumstances and the defendant was right in refusing to deliver the goods until it was paid.
Guy and Page, JJ., concur.
Judgment reversed and new trial ordered, with thirty dollars costs to appellant to abide event.