Weinberg v. Gash
Opinion of the Court
In July, 1914, the defendant ordered from the plaintiff 20,000 boxes. These boxes were to be made to order and the order included a partition and two fillers for each box. For some reason the plaintiff did not begin delivery of the boxes until December, 1914. At the trial the defendant’s counsel conceded that upon this order “ we received, on the 12th day of December, 1914,12,500 cartons; that thereafter we received and, within say about a week, we received about 500 fillers and about the 8th day of January, 1915, we received 10 bundles of fillers, or altogether about 6,000 fillers. 6,500 altogether; that we received all of the 20,000 partitions.” It appeared at the trial that while these deliveries were being made the plaintiff demanded payment of the entire amount of the order on the ground that the defendant himself had prevented the plaintiff from completing the order. promptly after the contract was made. The evidence clearly establishes that the defendant objected to these bills, though there is a conflict of testimony as to the nature of these objections. It is not disputed, however, that the bill which was rendered was for the sum of $444.22 and was made up of charges for 21,893 boxes at $19.70 per 1,000, and that the defendant claimed that he had ordered only 20,000 boxes at $19 per 1,000. On January 16,1915, the defendant wrote to the plaintiff “According to conversation had with you over the telephone to-day I am enclosing herewith check for $150.00 on account of your corrected invoice for $380.00 less 2%. As soon as you will deliver the balance of the boxes and partitions we will send you the
“ If Incorrect Please Return
“As per your corrected bill.............. $380 00
“ 1/16/15 on account................... 150 00
“ Due you balance................. $230 00
2% ” ... = — ^
The plaintiff refused to accept this check because she claimed that the indorsement thereon did not represent the understanding of the parties, and immediately began an action for the agreed price of the boxes. She discontinued this action after it appeared at the trial that complete delivery under the contract had not been made and the trial judge had intimated that the action was prematurely brought. Thereafter on February 13, 1915, she tendered delivery of the remainder of the order but the delivery was refused. Upon this record the trial justice has rendered judgment for the defendant.
Upon this appeal we must consider only two questions. First. Was the plaintiff in default prior to February 13th so that the delivery tendered on that date was too late? Second. If the plaintiff was in default on that date is she entitled to a recovery for the deliveries previously made and accepted?
The contract contains no clause fixing the date of delivery and, therefore, it required delivery only within a reasonable time. It appears undisputed that the parties did not consider the plaintiff in default on January sixteenth, when the defendant wrote the letter quoted above. That letter fixed no definite date for
The contract called for the delivery of 20,000 boxes. It failed to provide when these boxes were to be delivered or paid for. In such a case it is well established that delivery of the goods called for by the contract and payment for these goods are concurrent conditions. In the case of Catlin v. Tobias, 26 N. Y. 217, the Court of Appeals laid down the rule that where a contract required the delivery of a certain quantity of goods in certain specified months the contract at least as to each month “ was entire and called for an entire perform
In the present case the contract called for one entire delivery and in that respect it differs from the case of Catlin v. Tobias, supra, where deliveries were to be made constantly. The defendant in the present case had a right therefore to refuse partial deliveries. He not only, however, did not refuse these partial deliveries, but himself sent to the plaintiff for “ fillers ” so that he might be able to use the boxes delivered. At all times he evinced an intent not to pay for any boxes or platforms which were delivered without such “ fillers ” and he cannot be held to have waived the requirement that each box delivered should be complete with two such fillers, but I think that it is equally clear that he evinced an intent that he should pay for any boxes delivered complete with platforms and fillers without waiting for the delivery of the entire order. Throughout the case it appears that his objections to the plain
The appellant is therefore entitled to a new trial upon which the issues of the amount of fillers delivered and accepted and the agreed price per box may be determined.
Judgment is, therefore, reversed, and new trial ordered, with ten dollars costs to appellant to abide the event.
Weeks and Delehaxty, JJ., concur.
Judgment reversed and new trial ordered, with costs to appellant to abide event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.