Patrizio & Hendrickson, Inc. v. McDerMott & Hanigan, Inc.
Opinion of the Court
The plaintiff has recovered a judgment against the defendant by default. The defendant thereafter moved to open the default and its motion was granted on terms. The plaintiff now appeals from this order opening defendant’s default.
There is a sharp conflict as to the reason why the default was. originally suffered by the defendant. The plaintiff claims that the defendant admitted that it had no defense. The defendant on the other hand denies that it ever made such "an admission and claims that it was lulled into security by conversations with the plaintiff’s attorney. It is impossible to say with any certainty which side is telling the truth but if the defendant’s affidavits and answer show some prob
The defendant is the general contractor for the building of a garage. The plaintiff agreed to do certain work for a subcontractor but it refused to make this agreement unless and until it received a guaranty of payment from the general contractor. The defendant executed the contract of guaranty in writing and agreed to pay any and all sums “ as the same may properly accrue ” if the subcontractor should fail to pay them. The plaintiff’s contract with the subcontractor provided that “ the final payment shall be made within thirty days after the completion of the work included in this contract and acceptance by architects.” The plaintiff has pleaded that it has fully performed each and every term of the contract and that on the 17th day of August, 1916, the architects named in its contract accepted the work and certified that it had been properly performed and completed. “ Thereafter and on said 17th day of August, 1916, as requested by said Architects in their certificate so issued as aforesaid ” the plaintiff executed a guaranty of their work for one year and “ said architects did then and there accept said instrument as full performance by plaintiff herein of the condition expressed in said certificate.” The defendant now seeks to interpose an answer denying these allegations. It is quite evident, I think, that if the architects have accepted this work then the defendant who has guaranteed payment of the plaintiff’s contract cannot go back of the architects’ certificate. . That certificate if unimpeached will conclusively establish the performance of the work. The plaintiff’s affidavits show without denial that the architects on August 17, 1916, gave the following cer
Whitaker and Finch, JJ., concur.
Order reversed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.