Pape v. B. & B. Construction Co.
Opinion of the Court
This action was brought upon two promissory notes made by the defendant the B. & B. Construction Company, payable to the Mugler Iron Works, and transferred to the plaintiff. The case came on for trial on May 4, 1916, both sides declared themselves to be ready, and the trial proceeded. The plaintiff proved the making and delivery of the notes, and the purchase of them by the plaintiff; in fact, the defendant conceded substantially the entire case of the plaintiff. It appeared in the course of the cross-examination of one Mugler, the president of the Mugler Iron Works, the payee of the notes, that they had been sold to one Waldo, before maturity and for value, and that the plaintiff had purchased them from Waldo, after maturity.
The defendant thereupon asked for an adjournment of the trial, claiming that he was not aware, until then, that the notes had been sold
“The defendant answers ready and asks for a dismissal of the complaint: is that it? Defendants’ Attorney: Yes. The Court: The motion will be granted.”
Clearly, the court had no power thus to throw the plaintiff out of court. The plaintiff had presented his entire case, and the trial was with the defendant. The minutes of the previous day’s proceedings were in court, subject to the use of the justice, if needed by him, and not the slightest grounds were presented for a new trial, or even for a mistrial. The defendants should have been directed to proceed with the trial. Should this court merely reverse the judgment and order a new trial, the defendant would thereby profit by his own refusal to proceed.
Judgment reversed, with $30 costs, and judgment directed for the amount of the notes sued upon, with interest and appropriate costs in the court below. All concur.