Bryant v. Damiano
Opinion of the Court
OPINION OF THE COURT
Memorandum.
Judgment affirmed without costs.
Plaintiff commenced this small claims action, based on breach of contract, negligence and fraud, to recover $3,000 for water damage to her landscaping, patio and driveway resulting from defendant’s installation of an allegedly defective drainage system. At trial, plaintiff argued that although defendant completed the work 18 years before the action commenced, the critical defect, a capped drainpipe that should have been connected to the main drainage system, lay undetected for over 16 years and constituted a latent defect, thereby rendering the action timely. The court disagreed and dismissed the action on the ground that it was barred by the statute of limitations (see CPLR 213 [2]). Plaintiff appeals and we affirm.
Plaintiff’s claim based on breach of contract is time-barred. As a general rule, a cause of action against a contractor for construction defects “accrues upon completion of the actual physical work” (Cabrini Med. Ctr. v Desina, 64 NY2d 1059, 1061 [1985]; see also Rite Aid of N.Y., Inc. v R.A. Real Estate, Inc., 40 AD3d 474 [2007]; Breslin v Reality Roofing Inc., 4 Misc 3d 134[A], 2004 NY Slip Op 50759[U] [App Term, 9th & 10th Jud Dists 2004]). There is no dispute that the physical work on plaintiffs drainage system ended 18 years before plaintiff commenced the action, and as there is no indication that any factors exist that would extend the accrual date, the statute of limitations barred plaintiffs breach of contract claim (CPLR 213 [2]).
Insofar as plaintiffs claim was based on theories of negligence and fraud, it was also time-barred. As the Court of Appeals cautioned in Cabrini Med. Ctr., assertions of negligence and fraud “contained within” a breach of contract claim “cannot serve to extend the Statute of Limitations” where such allegations “are incidental to its complaint for breach of contract” (64 NY2d at 1061-1062). “[S]ince all liability has its genesis in the contractual relationship of the parties ... [a] cause of action alleging fraud cannot be maintained when the fraud charged relates to a breach of contract” (Middle Country Cent. School Dist. v O’Healy Constr. Corp., 230 AD2d 777, 778 [1996] [cita
Accordingly, we affirm the judgment since substantial justice was done between the parties according to the rules and principles of substantive law (UJCA 1807; Williams v Roper, 269 AD2d 125, 126 [2000]).
Rudolph, PJ., Molía and Scheinkman, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.