Gillen v. Hubbard
Opinion of the Court
The defendant agreed that if the contractor should, at any time during the progress of the work to be done under the contract, refuse or .neglect to supply a sufficiency of materials or workmen, that he should have the power to provide the materials and workmen after “ three days’ notice in writing being given to finish the work,” and that the expense would be deducted from the amount of the contract. And the defendant, acting upon this part of the contract, and after the alleged abandonment of the work by the contractors, notified them that they were required to supply the requisite materials and workmen for the completion of the contract, and that in default thereof he would supply the same, and deduct the expense thereof from the contract price. The penalty for a failure or refusal to supply materials and workmen appears to have been determined by the contract, and to have been understood and acted upon by the defendant. If the contract had been silent upon the subject, there would be no difficulty in relieving the defendant from any of his alleged grievances, because, the contractors having failed to perform their contract, the plaintiff, as
It seems, from the testimony in this case, that the principal-omissions of the contractors were the painting, and the construction of one cedar closet;' and by the terms of the contract the penalty for such omissions was regulated. If one cedar closet was omitted, the sum of one hundred dollars was to be deducted from the amount of the contract; and if the painting was omitted, the sum of four hundred dollars was to be deducted in like manner. It may be said, with propriety, in reference, to this part of the contract, that it gave to the contractors, if they thought proper so to do, the right to omit one cedar closet and the painting, and thus qualified the engagement to finish the building according to the plans and specifications of which these things were a part. But whether that be so or not, "the defendant cannot claim for those items more than he has agreed to accept, and cannot ask more than a reduction of the amounts agreed upon for these omissions. In determining the obligation of the contractors, the whole contract must be considered; and thus considered, it is an agreement to erect and furnish all the carpenter’s work of a dwelling house on or before the 1st of April following its date, with a proviso that if the contractors should refuse or neglect to supply a sufficiency of materials or workmen, the defendant should have the power, on a notice of three days, to finish the work and deduct the expense from the amount of the contract. And with a further proviso, that if one closet were omitted, and the painting omitted, a deduction of five hundred dollars, could be made by the defendant in the manner before stated. These features of the agreement gave the defendant the means of preventing any unnecessary delay in the performance of the work contemplated, and the power of substituting himself for the contractors upon the happening of the contingencies expressed. Doubtless he might have disregarded the power thus conferred, and have rested upon his right to have the work performed at the time agreed upon; but he did not adopt that
The referee finds that the rent of the house was $2,000 per annum, but does not find that the defendant sustained any damages by reason of the contractors’ failure to finish the premises on 1st April. Indeed there is no finding on that subject. The de
Judgment affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.