Norton v. Shields
Norton v. Shields
Opinion of the Court
This is a motion to set aside a verdict and for a new trial. The action was brought on an alleged contract by which the plaintiff agreed to lay certain pipes in the Boulevard, in New York City, between 125th street and 104th street.
It is claimed that the verdict was excessive. This point is based upon the amount allowed by the jury uñder the fourth cause of action, which was a claim for damages, consisting of the loss of profits caused by the defendant’s refusal to permit the plaintiff to perform the work under the alleged contract, between 114th street and 104th street. The plaintiff claimed, and gave evidence to support the claim, that the contract price for the work was $6,695.50; that the cost of doing the work would have been $2,697.03; and that the profit, therefore, would have been the difference, or $3,998.47; and the jury rendered a verdict upon the fourth cause of action for that amount. The defendant’s counsel claims that this verdict was excessive, and argues that it is incredible that any contract should have been made between these parties which would have given Norton a profit of 148 per cent. If a contract was made between the parties, the fact that the profits under it were large is immaterial. Whether the profits were large or small, both parties were bound by the contract. The only materiality of the fact that the profits were large is its bearing on the credibility of the plaintiff’s testimony that the contract was made. But there is substantially no contradiction in the testimony as to those provisions of the contract which fixed the rate of profit. There was admittedly at the outset a specific contract
The real difference between the parties as to the amount of the profits does not arise from any controversy as to the terms of the contract. If Norton had done the work between 114th street and 104th street under the contract as he claimed it to be, there is no doubt that the allowance of $6,695.50, which he claims would have been payable under it, is substantially correct. The real difference between the parties as to the amount of profit arises from the apparent discrepancy between the evidence offered by the plaintiff that the fair cost of the work from 114th street to 104th street was $2,697.03, and the evidence offered by the defendant that the cost of the work, as he performed it, amounted to $5,834.59. But adequate evidence was offered by the plaintiff in support of his claim as to what the cost of the work would have been. There were various grounds on which the plaintiff’s counsel claimed that the defendant’s figures of the cost of the work were too high, and of course the actual cost to Shields of doing the work was not conclusive.
The defendant also claims that the court erred in submitting to the jury the meaning of the provision in the contract that Norton should make all connections. It was necessary at certain stages of the work to make connection between the new pipe and the old pipe. By the terms of the contract Norton was to make the connections, but in order to make the connections it was necessary that the city authorities should cut off the water. To have this done involved some expense. A controversy arose between the parties as to who should pay such expense; Shields claiming that Norton’s agreement to make the connections made it obligatory upon him to pay whatever was necessary to be paid as a preliminary to making the connections, and Norton claiming that he was simply obliged to make the connections when the pipes were in such a condition that the connections could be made. Shields paid $228.33 for the charges for shutting off the water, and claimed that Norton should reimburse him for that amount. I submitted to the jury the question of the meaning of the provision that Norton should make the connections on the theory that it was a mixed question of fact and law. The provision that Norton should make all connections, as used in the contract, is capable of either one of two meanings, and, in order to determine in what sense the parties used it, it seemed to me that it was necessary to consider the circumstances when the contract was made and the actual construction put upon the contract by the acts of the parties. The fact that Shields was to deliver the pipe alongside the trench, and that Norton was not under any obligation to do any work in laying the pipe until the pipe to be laid was ready at hand, and the fact that Shields applied to have the water shut off and paid to the city officials the charges for shutting it off, and made no claim on Norton for such payments until some time subsequently, were circumstances, in my opinion, which the jury had a right to take into consideration in determining the intention of the parties in the provision in the contract that Norton should make the connections. The general rule is undoubtedly that the construction of a written instrument is a question of law for the court to determine, but to that rule there are exceptions. When the language employed in a contract is not free from ambiguity, or when its interpretation depends upon the sense in which the words were used in view of the subject to which they relate, the relation of the parties and the surrounding circumstances properly applicable to it, the intent of the parties becomes a matter of enquiry, and-the interpretation of the language used is a mixed question of law and of fact, to be determined by a jury. Kenyon v. K. T. & M. M. A. Ass’n., 122 N. Y. 254, 25 N. E. 299; Smith v. Coe, 55 N. Y. 678; White v. Hoyt, 73 N. Y. 512; First National Bank v. Dana, 79 N. Y. 116.
Under the circumstances, I cannot see that any adequate ground i» shown for setting the verdict aside. The motion for a new trial is denied.
Reference
- Full Case Name
- NORTON v. SHIELDS
- Status
- Published