In re Hudson River Water Power Co.
In re Hudson River Water Power Co.
Opinion of the Court
Prior to the filing of the petition in bankruptcy, the National Contracting Company, the main petitioning creditor, éntered into a written contract with the Hudson River Water Power Company whereby it agreed to construct for the latter company a masonry dam across the Hudson river at a designated point in consideration of certain compensation to be paid from time to time, and which was to be ascertained in certain ways with certain named prices for work as a basis'.
The contracting company entered on the performance of the contract, and in all respects complied with its requirements down to a time when the Hudson River Company undertook to make certain changes in the form and material of the dam, viz., by substituting an earth dam with a masonry core for the masonry dam the contracting company had agreed to build. The officers of the Hudson River Company claimed and asserted to the contracting company that it had decided to make, and had made, the change, and demanded and required that the contracting company proceed with and complete the work in accordance with the changed or new plans and specifications. The contracting company denied the right of the Hudson River Company to make these changes or require it to proceed under and in accordance there*with, insisting that the changes were fundamental and made a new contract, one they had not assented to, one the parties had mutually agreed they would not make. The contracting company insisted that, while it had agreed to changes in form and material such as the Hudson River Company might from time to time determine upon, still, these were limited to changes, etc., and material in the construction of a masonry dam, and did not authorize the substitution of an earth dam with a mere core of masonry. The Hudson River Company insisting and demanding the new construction, and, in effect, forbidding the construction in any other way, the contracting company insisted the Hudson River Company had broken the contract, and thereupon aban-
The defendant, Hudson River Company, denied a breach on its part, and alleged a breach by the plaintiff, the contracting company, and counterclaimed its alleged damages. A trial o'f the action before Rx-Judge Bookstaver as referee resulted in a judgment in favor of the National Contracting Company against the Hudson River Water Power Company on the 12th day of April, 1905, for $51-7,696.10, of which $97,-126.77 was for work done and not: paid for.
After the referee had made his report and just before the entry of the judgment, the defendant, Hudson River Water Power Company, mortgaged all its property to certain other companies for about $7,000,000, a sum largely in excess of the value of all its property, real and personal,' including all property lights and franchises o f every kind and nature. This was not based on any new or present consideration and the contention was that the mortgages were without any consideration whatever. Kxecution was issued and returned unsatisfied and these proceedings in bankruptcy were then instituted. The mortgagees under the state law immediately procured the appointment of a receiver and purported to take possession’ of all the property. This court, on the filing of the petition in bankruptcy, duly appointed a receiver 'who took possession of all the property he could find, but same, including all rights and franchises, was evidently of insufficient value to satisfy any considerable part of the mortgages. A motion was made to dismiss the proceedings and an answer denying insolvency was interposed, and it was also denied that the petitioners were creditors, etc. This court appointed a special master to take evidence and report the facts. A large amount of evidence was taken and reported to the court, and the matter was about to be submitted on .argument when the petitioning creditors and the alleged bankrupt and all directly interested in the proceeding entered into a stipulation and agreement, in substance that, pending the final adjudication and determination in the state courts of the claim of the National Contracting Company against the said Hudson River Water Power Company, certain moneys and securities should be placed and left with a designated person and trust company, appointed and approved by this court, as security for such claim and any judgment the contracting company might obtain against the Hudson River Company thereon. The money, etc., so deposited is to be applied to the payment of the claim or to the payment of such part of it, if any, as the contracting- company may be adjudged entitled to. An appeal by the Hudson River Company from the judgment first mentioned establishing such claim was then pending, and the stipulation expressly covered the contingency of a reversal and the granting of a new trial and of a protracted litigation over the claim with possible varying results in the different appellate courts. It was expressly contemplated by the parties and by the court, in making its order ratifying and approving the stipulation and agreement, that the judgment might be reversed; that a result adverse to the National Contracting Company might be reached on a new trial in the trial court and that appeals might he necessary, and even a third trial had
In the action"between the construction company and the Hudson Riven Companjr the defendant denies breach of the contract by it, and alleges •• breach of the contract by plaintiff, and that the contract pro-vidednn-express terms for a reference of all disputes between the two companies and of all questions arising under the contract to a referee o.r. referees named, and that plaintiff has not sought, offered, or ten-, clered; a - submission of the disputes and questions referred to such referees, and that such reference has not been refused, and hence plaintiff cannot 'maintain the action. To- this last defense a demurrer was interposed by plaintiff, but it -was overruled by the court of last resort, the Court of Appeals of the state of New York. Reave to withdraw the demurrer was riot then given and the parties went to the trial of the action with that adjudication on the demurrer. It was contended by defendant that this adjudication determined the action as the demurrer,- not withdrawn, admitted the facts stated in that defense and that the admission stood upon the record, and the judgment of the Court of Appeals was a final determination that the facts pleaded and
Again, suppose the pending suit goes off on the proposition that the remedy of the contracting company is to resort to the reference, is it too late for it to avail itself of that remedy? There can he no claim that the stipulation and agreement was entered into, and the order of the court made, under any misapprehension of the law or of the facts. All were well known and fully considered, both by the parties and by this court. There was no fraud, coercion, or concealment. It was a voluntary stipulation and the Hudson River Water Power Company and the other parties were represented by able atttorneys of record and by eminent and able counsel. As the case stood, this court had full-power to determine all the facts and adjudicate the questions of the validity or invalidity of the claim. The petitioner, National Contracting Company, accepted the stipulation and the remedies under it and took its security, which action changed its situation and it is impossible to restore the parties to their former status, rights, and remedies. Using a common expression, the fact that “the boot is on the other leg” at present is not a good reason for depriving the National Contracting Company of its security. Should it succeed in the suit, if that is done, its claim would be worthless or uncollectible.
If it clearly appeared now that the National Contracting Company has no claim I would relieve the Hudson River Company from the stipulation. But such is not the case. First, even should it be held the pending action cannot be maintained because resort was not had to the reference provided for in the contract, may not the contracting
The application is denied with leave to renew on the same papers and additional proceedings in the case when the Appellate Division has passed on the questions involved. In the meantime, further performance under the stipulation is suspended by continuing the order made in that regard in force until the decision of the Appellate Division is rendered.
Reference
- Full Case Name
- In re HUDSON RIVER WATER POWER CO.
- Cited By
- 1 case
- Status
- Published