Gwathmey Siegel Kaufman & Associates Architects, LLC v. Rales
Gwathmey Siegel Kaufman & Associates Architects, LLC v. Rales
Opinion of the Court
OPINION AND ORDER
I. INTRODUCTION
Gwathmey Siegel Kaufman & Associates Architects, LLC (“Gwathmey”), an architecture firm, seeks injunctive relief and summary judgment against defendant Mitchell Rales, a former client. The defendant opposes the motion for preliminary injunction and moves to stay or dismiss the action pending arbitration. For the reasons stated below, plaintiff’s motion for injunctive relief and summary judgment are denied. Defendant’s motion to stay the action pending arbitration is granted.
II. BACKGROUND
A. The Project
On September 19, 2002, Gwathmey and Rales entered into an architectural service agreement (“the Agreement”).
B. The Agreement
The Agreement contains an arbitration clause requiring some claims to be submitted to arbitration and incorporating the American Arbitration Association’s Construction Industry Arbitration Rules (“AAA rules”):
(Article 7.1) Claims, disputes or other matters in question between the parties to this Agreement arising out of or relating to this Agreement or breach thereof shall be subject to and decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise.9
The AAA rules include a provision providing the arbitrator with the power to rule on his or her own jurisdiction as well as on objections to the scope of the arbitration Agreement.
(Article 7.2) Demand for arbitration shall be filed in writing with the other party to this Agreement with the American Arbitration Association. A demand for arbitration shall be made within a reasonable time after the claim, dispute or other matter in question has arisen. In no event shall the demand for arbitration be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statutes of limitations.11
The Agreement also contains a provision requiring the application of the substantive state law of New York, the principal place of business of Gwathmey.
C. The Arbitration Demand
On May 28, 2010, Rales notified Gwathmey by letter of certain defects in the project.
III. LEGAL STANDARD
A. Summary Judgment
Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
In a summary judgment setting, “[t]he burden is on the moving party to demonstrate that no genuine issue respecting any material fact exists.”
In deciding a motion for summary judgment, a court must “ ‘construe the facts in the light most favorable to the non-moving party and must resolve all ambiguities and draw all reasonable inferences against the movant.’ ”
B. Preliminary Injunction
“ ‘The district court has wide discretion in determining whether to grant a preliminary injunction....’”
‘“To satisfy the irreparable harm requirement, [petitioner] must demonstrate that absent a preliminary injunction [it] will suffer an injury that is neither remote nor speculative, but actual and imminent, and one that cannot be remedied if a court waits until the end of trial to resolve the harm.’ ”
IV. APPLICABLE LAW — ARBITRA-BILITY
The determination of whether a dispute is arbitrable under the Federal Arbitration Act (“FAA”)
Because there is “a strong federal policy favoring arbitration ... where ... the existence of an arbitration Agreement is undisputed, doubts as to whether a claim falls within the scope of that Agreement should be resolved in favor of arbitrability.”
any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration. Accordingly, [fjederal policy requires us to construe arbitration clauses as broadly as possible. We will compel arbitration unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute.46
However, although federal policy favors arbitration, it is a matter of consent under the FAA.
Y. DISCUSSION
A. Summary Judgment Is Denied Because the Plaintiff Is Not Entitled to Judgment as a Matter of Law
There are no disputes of material fact in this case.
The plaintiffs argument that a court should determine timeliness would have merit if the parties had not incorporated the AAA rules into their Agreement.
B. No Preliminary Injunction Is Warranted
Plaintiff argues that being forced to arbitrate claims that it did not agree to arbitrate constitutes irreparable harm.
The plaintiff has shown a likelihood of success on the merits of the timeliness issue. The facts demonstrate that the Agreement precludes the arbitration of time-barred claims,
VI. CONCLUSION
For the foregoing reasons, plaintiffs motion for a preliminary injunction and summary judgment is denied. Defendant’s motion to dismiss is granted without prejudice.
SO ORDERED.
. See 4/10/12 Affidavit of Robert Siegel in Support of Plaintiff's Motion for Preliminary Injunction and Summary Judgment ("Siegel Aff.”) ¶ 4. See also 9/19/02 Agreement Between Owner and Architect ("Agreement”), Ex. 1 to Siegel Aff., at 1.
. See Siegel Aff. ¶ 4.
. See Defendant’s Memorandum of Law in Support of Motion to Stay, or in the Alternative, Dismiss the Action and Opposition to Plaintiff's Motion for Preliminary Injunction ("Def. Mem.”) at 2.
. See 4/21/12 Affidavit of Mitchell Rales in Support of Defendant’s Motion to Stay, or in the Alternative, Dismiss the Action ("Rales Aff.”) ¶ 4.
. See 8/05/06 Punch List No. 6, Ex. 2 to Siegel Aff., at 1.
. See 8/10/06 Punch List No. 6-Studio, Ex. 3 to Siegel Aff., at 1.
. See Siegel Aff. ¶¶ 7-8.
. See id. ¶ 9.
. Agreement at 10.
. See R-9 Jurisdiction AAA Rule ("Rule R-9”), Ex. 1 to 4/25/12 Affidavit of Alexander N. Lamme, defendant’s counsel, at 13.
. Agreement at 11.
. See id. at 12; Siegel Aff. ¶ 4.
. See Siegel Aff. ¶ 10.
. See id. ¶ 11
. See 7/06/10 Tolling Agreement, Ex. 6 to Siegel Aff., at ¶ 3.
. See Siegel Aff. ¶ 12; 9/19/11 Demand for Arbitration, Ex. 7 to Siegel Aff., at 2.
. See Siegel Aff. ¶ 13.
.See id. ¶ 14.
. 3/19/12 Amended Answering Statement, Ex. 9 to Siegel Aff., at 1.
. Fed.R.Civ.P. 56(a).
. Sanchez v. Connecticut Natural Gas Co., 421 Fed.Appx. 33, 34 (2d Cir. 2011) (quoting Nabisco, Inc. v. Warner-Lambert Co., 220 F.3d 43, 45 (2d Cir. 2000)).
. Carter v. Incorporated Village of Ocean Beach, 415 Fed.Appx. 290, 292 (2d Cir. 2011) (quoting McCarthy v. Dun & Bradstreet Corp., 482 F.3d 184, 202 (2d Cir. 2007)).
. Mavrommatis v. Carey Limousine Westchester, Inc., 476 Fed.Appx. 462, 463-64 (2d Cir. 2011) (citing Gallo v. Prudential Residential Servs., L.P., 22 F.3d 1219, 1223 (2d Cir. 1994)).
. Cordiano v. Metacon Gun Club, Inc., 575 F.3d 199, 204 (2d Cir. 2009).
. Brown v. Eli Lilly & Co., 654 F.3d 347, 358 (2d Cir. 2011) (quoting Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986)).
. Id. (quoting Federal Deposit Ins. Corp. v. Great Am. Ins. Co., 607 F.3d 288, 292 (2d Cir. 2010)).
. Brod v. Omya, Inc., 653 F.3d 156, 164 (2d Cir. 2011) (quoting Williams v. R.H. Donnelley Corp., 368 F.3d 123, 126 (2d Cir. 2004)).
. Kaytor v. Electric Boat Corp., 609 F.3d 537, 545 (2d Cir. 2010) (quoting Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150, 120 S.Ct. 2097, 147 L.Ed.2d 105 (2000)) (emphasis removed).
. Brod, 653 F.3d at 164 (quoting Wilson v. Northwestern Mut. Ins. Co., 625 F.3d 54, 60 (2d Cir. 2010)).
. International Bus. Mach. Corp. v. Johnson, 355 Fed.Appx. 454, 455 (2d Cir. 2009) (quoting Moore v. Consolidated Edison, 409 F.3d 506, 511 (2d Cir. 2005)).
. Sussman v. Crawford, 488 F.3d 136, 139-40 (2d Cir. 2007) (quoting Mazurek v. Armstrong, 520 U.S. 968, 972, 117 S.Ct. 1865, 138 L.Ed.2d 162 (1997)).
. County of Nassau, N.Y. v. Leavitt, 524 F.3d 408, 414 (2d Cir. 2008) (quoting NXIVM Corp. v. Ross Inst., 364 F.3d 471, 476 (2d Cir. 2004)).
. Winter v. Natural Res. Def. Council, Inc., 555 U.S. 7, 24, 129 S.Ct. 365, 172 L.Ed.2d 249 (2008) (citation omitted).
. Bank of N.Y. Co. v. Northeast Bancorp, 9 F.3d 1065, 1067 (2d Cir. 1993).
. Grand River Enter. Six Nations, Ltd. v. Pryor, 481 F.3d 60, 66 (2d Cir. 2007) (quoting Freedom Holdings, Inc. v. Spitzer, 408 F.3d 112, 114 (2d Cir. 2005)).
. Hoblock v. Albany County Bd. of Elections, 422 F.3d 77, 97 (2d Cir. 2005) (quoting Shapiro v. Cadman Towers, Inc., 51 F.3d 328, 332 (2d Cir. 1995)). Accord Jayaraj v. Scappini, 66 F.3d 36, 39 (2d Cir. 1995) (”[W]here monetary damages may provide adequate compensation, a preliminary injunction should not issue.”).
. Gibson v. U.S. Immigration & Naturalization Serv., 541 F.Supp. 131, 137 (S.D.N.Y. 1982) (citation omitted).
. See 9 U.S.C. §§ 1-14.
. Hartford Acc. & Indem. Co. v. Swiss Reinsurance Am. Corp., 246 F.3d 219, 226 (2d Cir. 2001) (quotation marks omitted).
. Genesco, Inc. v. T. Kakiuchi & Co., 815 F.2d 840, 845 (2d Cir. 1987).
. Id.
. Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S.Ct. 588, 154 L.Ed.2d 491 (2002) (quotation marks omitted).
. Genesco, 815 F.2d at 846.
. Shaw Grp. Inc. v. Triplefine Int'l Corp., 322 F.3d 115, 120 (2d Cir. 2003) (citing First Options of Chi., Inc. v. Kaplan, 514 U.S. 938, 945, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995)).
. ACE Capital Re Overseas Ltd. v. Central United Life Ins. Co., 307 F.3d 24, 28 (2d Cir. 2002) (quotation marks and citations omitted).
. Collins & Aikman Prods. Co. v. Building Sys., Inc., 58 F.3d 16, 19 (2d Cir. 1995) (quotation marks and citations omitted). Accord WorldCrisa Corp. v. Armstrong, 129 F.3d 71, 74 (2d Cir. 1997).
. See Louis Dreyfus Negoce S.A. v. Blystad Shipping & Trading, Inc., 252 F.3d 218, 224 (2d Cir. 2001) (quotation marks omitted).
. Shaw Grp. Inc., 322 F.3d at 120 (citing First Options of Chi., Inc., 514 U.S. at 945, 115 S.Ct. 1920).
. Id. (emphasis in original) (quoting First Options of Chi., Inc., 514 U.S. at 944, 115 S.Ct. 1920).
. See Contec Corp. v. Remote Solution, Co., 398 F.3d 205, 211 (2d Cir. 2005).
. See id.
. See Salim Oleochemicals v. M/V Shropshire, 278 F.3d 90, 92 (2d Cir. 2002).
. The statements of fact in the plaintiff's Memorandum and the defendant’s Memorandum contain no disputed factual issues. See Plaintiff's Memorandum of Law in Support of Motion for Preliminary Injunction and Summary Judgment ("PL Mem.”), at 5-9; Def. Mem. at 3-6. The disputed issues lie in the interpretation of article 7.2 of the Agreement, which raises only an issue of law. Compare PL Mem. at 17 (arguing that the parties agreed to submit questions of arbitrability to the Court), with Def. Mem. at 5 (arguing that the parties submitted all arbitrability issues to the arbitrator).
. See Def. Mem. at 3; PL Mem. at 19.
. See PL Mem. at 12.
. See id. at 12-15; Agreement at 11.
. See Agreement at 11.
. See Rule R-9 at 13. See also Louis Dreyfus Negoce S.A., 252 F.3d at 224 (holding that where the issue is one of arbitrability the federal presumption in favor of arbitration shifts to favor a court determination). But See Contec Corp., 398 F.3d at 211 (finding an exception to this reversed presumption when the parties have incorporated AAA rules).
. See Rule R-9 at 13.
. See Agreement at 11.
. Id.
. See 398 F.3d at 211. See also Shaw Grp. Inc., 322 F.3d at 124-125 (finding that where the parties had incorporated the rules of the International Court of Arbitration, which empowers arbitrators to decided issues of arbitrability, the parties had assented to arbitrate issues of arbitrability).
. See Pyke v. Cuomo, 567 F.3d 74, 76 (2d Cir. 2009) (finding that for summary judgment to be appropriate, the movant must be entitled to judgment as a matter of law).
. See PL Mem. at 10.
. See supra Part V.A.
. See Agreement at 11.
. See Pl. Mem. at 11; C.P.L.R. § 214(6).
. See Pl. Mem. at 11.
. See Tolling Agreement ¶ 3
. See County of Nassau, N.Y., 524 F.3d at 414 (finding that a motion for preliminary injunction must demonstrate: "(1) irreparable harm in the absence of the injunction and (2) either (a) a likelihood of success on the merits or (b) sufficiently serious questions going to the merits to make them a fair ground for litigation and a balance of hardships tipping decidedly in the movant's favor”) (citation and quotation marks omitted).
. See Alford v. Dean Witter Reynolds, Inc., 975 F.2d 1161, 1164 (5th Cir. 1992); Alter v. Englander, 901 F.Supp. 151, 155 (S.D.N.Y. 1995); Hart Enterprises Int’l, Inc. v. Anhui Provincial Import & Export Corp., 888 F.Supp. 587, 591 (S.D.N.Y. 1995).