Rich Marine Sales, Inc. v. United States
Rich Marine Sales, Inc. v. United States
Opinion of the Court
INTRODUCTION
Plaintiffs Rich Marine Sales, Inc. and Rich Marina Corp. ("Plaintiffs") commenced this action on July 27, 2018, alleging that the United States of America (the "United States") and Luedtke Engineering Company ("Luedtke") (collectively, "Defendants") negligently dredged the Black Rock Channel (the "Channel") along the Niagara River in Buffalo, New York. (See Dkt. 1). On August 29, 2018, Luedtke filed an Answer to the Complaint and cross-claimed against the United States for indemnification and contribution in the event Luedtke was found liable to Plaintiffs. (Dkt. 10 at 17).
Presently before the Court is the United States' motion to dismiss the cross-claims for lack of subject matter jurisdiction, or, alternatively, for judgment on the pleadings for failure to state a claim. (Dkt. 16). For the following reasons, the United States' motion is granted and Luedtke's cross-claims are dismissed for lack of subject matter jurisdiction.
BACKGROUND
Plaintiffs own and operate a marina on the Channel opposite the United States Army Corps of Engineers' (the "Corps") Channel Locks. (Dkt. 1 at ¶ 1). The Channel "accommodates pleasure craft and commercial vessels up to 625 feet long with drafts up to 21 feet." (Id. at ¶ 20). Rich Marina Corp. owns 26 acres of property abutting the waterfront along the Channel (the "Property"), which includes the marina. (Id. at ¶ 18). The Property is protected by a "retaining wall," referred to as the "Bulkhead," which "serves as a barrier" between the Property and the Channel. (Id. at ¶¶ 4, 21).
The Corps is responsible for maintaining and repairing the Channel and has previously contracted third parties to perform dredging operations within the waterway.
*376(Id. at ¶¶ 23-24). As part of an initiative to remove "potentially contaminated sediment from the Channel," the Corps "contracted with Luedtke in 2015 to conduct a dredging project" within a section of the Channel that runs parallel to the Property (the "Project"). (Id. at ¶¶ 26-27). The Corps determined the "specifications, the planning, the scope, and the supervision" of the Project. (Id. at ¶ 28).
Plaintiffs allege that, "[u]pon information and belief, the contract between [the Corps] and Luedtke required dredging solely within the confines of the Channel." (Id. at ¶ 32). However, Luedtke allegedly "performed dredging outside of the Channel and up to the Bulkhead," and "over-dredged the Channel beyond its contractual obligations." (Id. at ¶ 33). Plaintiffs also allege, in the alternative, that the Corps "directed Luedtke to over-dredge the Channel and dredge outside of the Channel up to the Bulkhead." (Id. at ¶ 34). Allegedly due to these dredging actions, "the riverbank adjacent to and underneath the Bulkhead slid into the Channel causing unsustainable strain on the Bulkhead." (Id. at ¶ 33). Nevertheless, "Luedtke continued to dredge material in this fashion resulting in the removal of the riverbank which supported the Bulkhead." (Id. ).
As a result, "on July 28, 2016, approximately 250 feet of the Bulkhead" collapsed and fell into the Channel. (Id. at ¶ 36). In August 2016, another 100-foot section of the Bulkhead collapsed into the Channel due to the dredging activities. (Id. at ¶ 37). Finally, in April 2017, "a third section of the Bulkhead, approximately 75 feet in length, collapsed into the Channel as a direct result of the dredging performed by Luedtke." (Id. at ¶ 38). The remaining portion of the Bulkhead is allegedly "at imminent risk of collapse." (Id. at ¶ 39).
PROCEDURAL HISTORY
On July 27, 2018, Plaintiffs commenced this action, asserting several tort causes of action pursuant to the Federal Tort Claims Act,
On November 9, 2018, the United States filed a motion to dismiss Leudtke's cross-claims, seeking dismissal for lack of subject matter jurisdiction or, in the alternative, for failure to state a claim. (Dkt. 16). Specifically, the United States argues that Leudtke's cross-claims are subject to the Contract Disputes Act, 41 U.S.C § 7101 et seq. ("CDA"), and thus, Leudtke was required to exhaust its administrative remedies before asserting these claims in this lawsuit. (Dkt. 16-1 at 4-8). According to the United States, because Leudtke failed to exhaust these administrative requirements this Court is without subject matter jurisdiction to entertain the cross-claims. (Id. ). Alternatively, the United States contends that Leudtke's cross-claims are conclusory and do not satisfy the pleading standards enunciated in Bell Atl. Corp. v. Twombly ,
DISCUSSION
I. Legal Standard
"In the context of a motion to dismiss for lack of subject matter jurisdiction pursuant to Federal Rule of Civil Procedure 12(b)(1), the party seeking to invoke the Court's jurisdiction bears the burden of proving that subject matter jurisdiction exists." Hulton v. Bayerische Staatsgemaldesammlungen ,
II. The Contract Disputes Act
"The CDA creates a remedial scheme whereby persons wishing to bring a contract-based claim against the federal government must first submit their claim in writing to a contracting officer." Cohen v. Postal Holdings, LLC ,
"A 'contracting officer's decision on a claim is final and conclusive and is not subject to review by any forum, tribunal, or Federal Government agency,' except as authorized by the CDA itself." Cohen ,
III. Leudtke's Cross-Claims Fall Within the Scope of the CDA and Should be Dismissed for Lack of Subject Matter Jurisdiction
The principal dispute between Leudtke and the United States is whether Leudtke's cross-claims arise out of the dredging contract and are properly characterized as "essentially contractual," or whether they sound in tort. Leudtke argues that because its contribution and indemnification cross-claims are based on Plaintiffs' tort claims, they should also be considered tortious in nature. (Dkt. 21 at 1-2). If Leudtke is correct, "then the CDA's jurisdictional bar would not apply to its claim[s]." Cohen ,
"In order to determine whether the CDA applies, federal courts generally look to whether the dispute at issue is one of contract." United States v. J & E Salvage Co. ,
Where the right the plaintiff seeks to vindicate "stems from no independent, non-contractual source" and the remedy for violating that right is essentially a contractual remedy arising out of a contract within the scope of the CDA, then the claim is subject to the CDA notwithstanding *379a plaintiff's attempt to disguise it as a tort.
Cohen ,
Leudtke's cross-claim for contribution states, in pertinent part, that "[s]hould it be determined at the time of trial that some or all of the allegations of Plaintiffs' Complaint are true such that [Leudtke] is held liable to Plaintiffs, ... then [Leudtke] seeks contribution from co-defendant, United States of America...." (Dkt. 10 at 17). Leudtke's cross-claim for indemnification states, in pertinent part:
Any and all injuries and damages alleged by the Plaintiffs were the proximate result of the negligence, breach of warranty, strict liability and/or other liability producing conduct of the co-defendant which conduct was primary and active, and if [Leudtke] is found liable with respect to Plaintiffs' alleged injuries and damages, such liability is solely secondary, imputed, and vicarious, and the co-defendant is liable over in indemnity.
(Id. ). Lastly, Leudtke alleges that it is "also entitled to indemnification and contribution pursuant to any applicable contracts or agreements between the parties." (Id. ).
Leudtke relies heavily on the fact that its cross-claims refer to Plaintiffs' allegations and argues that because the United States is named as a joint tort-feasor in this action, its claims for indemnification and contribution are not contractual. (See Dkt. 21 at 4-7). Of course, "[t]he plaintiff's title or characterization of its claims is not controlling." RMI Titanium Co. ,
Indeed, Plaintiffs allege that Defendants' negligent dredging conduct violated the dredging contract. For example, Plaintiffs claim that Leudtke dredged "beyond its contractual obligations" and that the Corps directed Leudtke to "dredge outside the Channel" despite the fact that "the contract between [the Corps] and Luedtke required dredging solely within the confines of the Channel." (Dkt. 1 at ¶¶ 32-34). Plaintiffs' claimed damages are based on the allegations that Leudtke performed dredging activity in violation of the contractual terms. (See id. at ¶¶ 36-38, 40-42). In other words, Leudtke's cross-claims only become relevant if Plaintiffs successfully establish Leudtke's liability, and Plaintiffs' theory of liability against Leudtke is based on its alleged dredging activity in contravention of its contract with the United States. Thus, any indemnification or contribution claim by Leudtke against the United States is necessarily rooted in contract.
"Of course, the mere fact that a court has to decide some contract issues in the course of resolving a tort action does not automatically convert the claim into one sounding in contract if there is some independent basis for the tort claim." J & E Salvage Co. ,
*380Megapulse, Inc. ,
In concluding that Leudtke's cross-claims are essentially contractual in nature, the Court finds the decision in Contango Operators to be instructive. In that case, a cross-claim for negligence was asserted against the United States in an action where the plaintiffs alleged that their pipeline was damaged as a result of dredging operations conducted by the cross-claimant "under contract with" the United States. Contango Operators, Inc. ,
Here, Leudtke asserts claims against the United States for indemnification and contribution based upon the dredging operations performed under the agreement between Leudtke and the Corps. These cross-claims are "inextricably bound up" with the contractual duties between the Corps and Leudtke under the dredging contract and the alleged breach of those duties as stated in the Complaint. See Contango Operators, Inc. ,
In other words, if the United States is liable to Leudtke for damages based upon *381theories of indemnification or contribution, it is because the Corps breached contractual duties owed to Leudtke in failing to provide proper specifications, planning, scoping, or other information or direction necessary to satisfy its obligations under the dredging contract. See Contango Operators, Inc. ,
Accordingly, Leudtke has failed to establish this Court's subject matter jurisdiction to entertain the cross-claims. Because the resolution of Leudtke's cross-claims necessarily relate to and arise from the contractual relationship between itself and the Corps and require the interpretation of the agreement's terms in determining the scope of the Corps' duties, the cross-claims fall within the scope of the CDA. It is undisputed that Leudtke failed to exhaust its administrative remedies under the CDA.
To the extent Leudtke argues that principles of judicial economy warrant exempting its indemnification or contribution claims from the CDA's administrative exhaustion requirements, such arguments are unpersuasive. As Leudtke's counsel conceded at oral argument, principles of judicial efficiency will not create subject matter jurisdiction where the Court does not have it. The CDA's exhaustion provisions constitute a jurisdictional bar to this Court's subject matter jurisdiction, and thus, they must be satisfied before any claim falling within the CDA's purview may be asserted in a lawsuit.
CONCLUSION
For the foregoing reasons, the United States' motion to dismiss (Dkt. 16) is granted, and Leudtke's cross-claims are dismissed for lack of subject matter jurisdiction.
SO ORDERED.
The following facts are drawn from Plaintiffs' Complaint (Dkt. 1) and Luedtke's cross-claims (Dkt. 10 at 17) and are assumed true for purposes of this motion.
Reference
- Full Case Name
- RICH MARINE SALES, INC. and Rich Marina Corp. v. The UNITED STATES of America and Luedtke Engineering Company, Luedtke Engineering Company, Cross-Claimant v. The United States of America, Cross-Defendant.
- Cited By
- 2 cases
- Status
- Published