Bandes v. Triborough Bridge Authority
Opinion of the Court
Plaintiff sues as an assignee of moneys due under a public improvement contract, and trial was had before the court without a jury. The contract in question was known as No. 44, and was entered into by Triborough Bridge Authority on the one part and Max Hochman as the contractor on the other part, on April 8, 1935, for the demolition of additional buildings to the Manhattan approach of the Triborough Bridge. Remaining unpaid on the contract is a balance of $3,760, now in the possession of the comptroller of the city of New York. The assignment in question provided, among other things, that the contractor assigned to the plaintiff the sum of $2,000 out of payments now due or hereafter to become due to him from the Triborough Bridge Authority under and by virtue of said contract, and is dated October 25, 1935, and was filed in the comptroller’s office on November 4, 1935.
The defendant Zucker Water & Sewer Service Corp. in its answer interposes counterclaims, and demands judgment against the Triborough Bridge Authority in the sum of $1,169.14 by virtue of an instrument dated November 12, 1935, and filed in the comptroller’s office on November 21, 1935, addressed to the Triborough Bridge Authority and the finance department, New York city, requesting and requiring that out of the moneys due and to grow due under said contract that “ you pay unto Zucker Water & Sewer Service Corporation ” the sum of $1,169.14, and charge such payment against the moneys due or to grow due and owing to the contractor under said contract. Hochman, the contractor, testified he received from the plaintiff the sum of $2,000 on the execution of said assignment and used same in the work, labor and material for the completion of said contract; he further testified that the last day he worked on the job was October 26, 1935.
A concession was made by the corporation counsel, representing the Triborough Bridge Authority, that the testimony of Hochman as to the time of the completion of the job given with respect to plaintiff’s claim would be the same in reference to the claim of Zucker.
Item 22 of the contract in question, entitled “ Assignments and Sub-Contracts,” provides: “ Inasmuch as this Contract is made in reliance upon the Contractor’s personal qualifications and responsibility, and inasmuch as the payments to be made hereunder are intended to finance in part the Contractor’s performance, the Contractor shall not assign or otherwise transfer this contract or any part hereof, or any moneys due or to become due hereunder, without first obtaining the consent of the Resident Project Engineer and then without the express consent in writing of the Authority; provided, however, that the Contractor may sub-contract work to be performed hereunder to such persons as the Chief Engineer, subject to the approval of the Resident Project Engineer, may from time to time approve in writing.
“ No consent to any assignment or other transfer, and no approval of any sub-contractor shall under any circumstances operate to relieve the Contractor of any of his obligations under this contract; no Contract and no approval of any sub-contractor shall create or be deemed to create any rights in favor of such sub-contractor and against the Authority; and for all purposes hereunder, all assignees, sub-contractors, and other transferees shall be deemed to be the agents of the Contractor. Moreover, all sub-contracts and all approvals of sub-contractors, regardless of their form, shall be deemed to be conditioned upon performance by the sub-contractor in accordance with this contract; and if any sub-contractor shall fail to perform his Work to the satisfaction of the Engineer, the Chief Engineer shall have the absolute right to rescind his approval forthwith and to require the performance of such work by the Contractor personally, and /or through other approved subcontractors.
“ Nothing herein contained shall be construed to hinder, prevent or affect an assignment of any moneys due or to become due hereunder, made for the benefit of the Contractor’s creditors pursuant to law.”
Item 12 of the contract in question, entitled^ Time for Completion,” provides:
“ The Chief Engineer shall be the sole judge as to whether the Work hereunder has been completed within the time stipulated.”
Exhibit 5, introduced in evidence by the plaintiff, is a communication addressed to Col. Paul Loeser, director, and signed by Edward W. Stearns, acting chief engineer for the Triborough Bridge Authority, is dated January 3, 1936, and provides, among other things, as follows: “ The contract (No. 44) provides that the work should be completed within 120 consecutive calendar days from the date of notice to the Contractor to begin work. Such notice was given on April 19, 1935. The date for completion was, therefore, August 17, 1935. The contract was actually completed on November 15, 1935. * * * On July 30, 1935, the Contractor requested an extension of time to September 1, 1935, claiming that his delay was caused by the failure of the Authority to have all the parcels available for demolition. * * * In my opinion the Contractor suffered a delay of approximately three weeks because of the nonavailability of the parcels mentioned at the beginning of the work and the Contractor is, therefore, entitled to an extension of time to about September 7, 1935. The Work was practically completed prior to that date, the exceptions consisting of certain demolition below ground level, repairs to sidewalks and miscellaneous cleaning up which was finally completed November 15, 1935.”
In introducing that exhibit (5) the plaintiff became bound by its terms. (Jonasson v. Weir, 130 App. Div. 528; Curry v. American Railway Express Co., 214 id. 744.)
The date of the completion of the work is thus fixed as of November 15, 1935.
Plaintiff argues that it is wholly immaterial to her right of recovery whether the work under said contract was completed by the contractor on October 25, 1935, or on November 15, 1935.
The contract under consideration specifically prohibited the assignment or other transfer of the contract or any part thereof or any moneys due or to become due thereunder without the consent of the engineer and of the authority. That such consent was refused was not denied. That the contractor fully performed the contract is not denied; nor is the fact that the sum of $3,760 is still due as the balance thereon, which amount is in the possession of the comptroller.
Another case involving a similar principle is that of Snyder v. City of New York (74 App. Div. 421). There the defendant claimed that by the provisions of the contract there could be no assignment of same without the previous written consent of the commissioner of public works. Nevertheless, the court stated that the clause in question is a restriction solely upon the assignment of the contract, as such, and not of the moneys earned thereunder, which the city is bound to pay. (Citing cases.)
In the present case, however, the Triborough claims and the evidence shows that the contract was not wholly completed at the time of the assignment of the moneys to the plaintiff and the order to pay to Zucker executed by the contractor. From the dicta gathered in an examination of the authorities it is my opinion that the determination of this controversy is not dependent on the time when the assignment was made.
Adverting to the case of Fortunato v. Patten (147 N. Y. 277), we find a similar clause in the contract with the city; that the contractor shall not assign the contract nor any of the moneys payable thereunder without the consent of the city in writing, indorsed on the agreement; and that in the absence of such consent, no right to any moneys to grow due by the terms of the contract shall be asserted against the city. Referring thereto, the court said: “ We do not think that this provision is capable of any such construction [rendering void all assignments of moneys to grow due unless the consent of the city was obtained]; it was inserted in the contract solely for the benefit of the city, and prevents any claim being asserted against it in the absence of consent.”
The case of Sacks v. Neptune Meter Co. (144 Misc. 70) was one where an employee assigned his wages in violation of a stipulation prohibiting such, and is cited in the several briefs submitted by counsel here. In that case Mr. Justice Frankenthaler, in a concurring opinion, stated: “ There is an important difference between an assignment of a contract itself and an assignment of a claim for moneys due under the contract. [Citing cases.] It is only the latter with which we are concerned here.' * * * In Manchester v. Kendall (19 J. & S., 51 N. Y. Super. Ct. 460), which was affirmed by the Court of Appeals (103 N. Y. 638), a contract contained the provision that neither it nor any of the installments
“ The contention that, by reason of the provisions of subdivision 3 of section 41 of the Personal Property Law, the assignee’s only recourse is against his assignor, while it may represent the law in some States, is refused by the authorities in this State which have held that it is the debtor whose only recourse is against the assignor. (Manchester v. Kendall, supra; Reliable Loan & Investment Co. v. Delgus Co., Inc., supra.) ”
As was said by Mr. Justice Holmes in delivering the opinion of the court in the case of Portuguese-American Bank v. Wells (242 U. S. 7, 11): “ There is a logical difficulty in putting another man into the relation of the covenantee to the covenantor, because the facts that give rise to the obligation are true only of the covenantee — a difficulty that has been met by the fiction of identity of person and in other ways not material here. Of course a covenantor is not to be held beyond his undertaking and he may make that as narrow as he likes. (Arkansas Valley Smelting Co. v. Belden Mining Co., 127 U. S. 379.) But when he has incurred a debt, which is property in the hands of the creditor, it is a different thing to say that as between the creditor and a third person, the debtor can restrain his alienation of that, although he could not forbid the sale or pledge of other chattels.”
No attempt was made here to assign the contract or any part thereof. What was intended to be assigned to both the plaintiff and to Zucker was money due or to become due under the terms of the contract. The testimony shows that the consideration of
An exhaustive examination of the authorities cited by counsel in their several briefs and research otherwise has revealed no case determinative of the precise issue involved here. The dicta would seem to indicate that the assignment held by the plaintiff and the order in favor of defendant Zucker, which to all intents and purposes may be treated as an assignment, should be upheld; nor are they in violation of any of the provisions of section 41 of the Personal Property Law.
It seems to me, therefore, that notwithstanding both instruments were executed and filed prior to the date of the completion of the work on November 15, 1935, and that neither had the approval of the designated authority, they should be held valid as transferring to those respective parties certain portions of the fund concededly in the possession of the comptroller as the balance due under the contract as completed by the contractor.
In arriving at a determination in this case the court has not overlooked the fact that the contract under consideration was one for a public improvement, and that the funds for same were secured from the Federal authorities. No liens or assignments have been filed either with the Triborough Bridge authorities or elsewhere, other than those concerned in this proceeding and now before the court affecting contract No. 44, as conceded at the trial.
It is my opinion, therefore, that the respective claims and liens should be determined in the following manner: The plaintiff is awarded judgment against the defendant Triborough Bridge Authority in the sum of $2,000, with interest from September 25, 1935, and statutory costs to lie paid out of the fund in the possession of the comptroller of the city of New York to the credit of contract No. 44.
The defendant Zucker Water & Sewer Service Corporation is awarded judgment against the Triborough Bridge Authority in the sum of $769.14, with interest from November 12, 1935, to be paid out of the fund above mentioned, and judgment against the defendant Max Hochman for the sum of $400, with interest from November 12, 1935, and statutory costs.
That the defendant Harold H. Tompkins is awarded judgment against the Triborough Bridge Authority in the sum of $575, with
That the defendant Offenberg Brick Corporation is awarded judgment against the Triborough Bridge Authority in the sum of $110, without interest and no costs.
No additional allowance is made to any of the parties.
The counterclaim of the Triborough Bridge Authority against the plaintiff was withdrawn at the trial.
Submit findings.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.