Kingsley v. City of Brooklyn
Opinion of the Court
The appeal by the defendant brings up the question whether the referees erred in ordering the judgment that was entered ; the appeal by the plaintiffs, the question whether the referees should have directed judgment only for an amount equal to the unexpended part of the original appropriation, and if not, the further question whether we have the power to modify the judgment by ordering that it be increased to the sum found due.
We take up, as first in order, the case on the defendant’s appeal.
The legislature had imposed upon the permanent board of water and sewerage commissioners the duty of preparing and submitting to the common council of the city of Brooklyn a plan for furnishing an increased supply of water for the city, including such extension of the present works and the construction of such further reservoirs, conduits and other structures as might be necessary for that purpose, together with an estimate of the probable cost thereof, and directed them to acquire, in the name of the city, the title to such lands, ponds and streams as might be necessary (Laws of 1870, ch. 652).
A plan was prepared, submitted to the common council, and approved.
Before proceeding to contract for the work, and upon the advice of the chief engineer, Mr. Adams, the commissioners obtained from contractors estimates and bids for the different kinds of work proposed to be done, but the engineer advised the commissioners not to accept either of the bids, as the price charged for excavation was considered too high. He stated that the bid of Kingsley & Keeney was the lowest of the five estimates received, and that, if they would reduce the charge for excavation to fifty-five cents per cubic yard, the contract should be given to them; that their bid would then be $44,675 lower than that of either of-the other parties, and in that statement and recommendation, Mr. Kirkwood, the other engineer, concurred. The proposed reduction having been assented to, the agreement under which these plaintiffs have performed work and furnished materials, as found by the referees, was executed, under date of January 9, 1872.
The first question is as to the validity of that agreement.
There was no call for bids with a view to public competition, nor need there have been. A board of commissioners charged with the duty of contracting could do so as at the common law, save when expressly directed and restrained (Hobert v. City of Detroit, 17 Mich. 246; Miller v. City of Milwaukee, 14 Wis. 642).
The charges of fraud, collusion, conspiracy and favoritism set up in the answer to impeach the contract and what was done under it, appear to have been duly considered by the referees. In their opinion they discuss the matter, and in their report find that there was no proof to support those charges. I have carefully gone over and analyzed the testimony and the papers in these appeal books, and sought to apprehend the force, effect and relation of the circumstances, and am satisfied that the referees were correct in the conclusion stated by them.
As the city could not, in the exercise of its inherent and implied powers, pledge its credit in acquiring and improving lands outside of the city limits, the legislative direction given was to be respected ; this contract so framed as to carry out substantially the purpose of the legislature. It was as the case of an agent acting on the instructions of a principal. As suggested by one of my brethren on the argument, a corporate authority to expend $1,400,000 would not support an agreement to pay $2,000,000, and the parties acting were bound to know the terms of the statute. In this point of view, it is material that the probable expense of the work, as estimated and reported by the engineer, including the cost of 300 acres of land at Hempstead, was $1,393,743, and that the work was let to the plaintiffs for a less sum. It further appears that, with the damages assessed and paid for the additional land, the whole expenditure, as proposed, was within the limit of $1,400,000. We have no means, nor had the referees, of revising those estimates, no evidence tending to show that the parties had reason to doubt their correctness.
As the arrangement for the work did not involve the exercise of power greater than had been conferred
The questions raised on the argument relate to what was done under the contract as well as to the contract itself. The learned counsel for the defendant claim that the plan approved by the common council, July 11,1870, should have been adhered to strictly ; that departures from and extensions of it were without authority. The land area in that plan having been fixed at 300 acres, it is not easy to reconcile the restrictive policy now suggested with the authority given by the act of 1871 to acquire, in the name of the city, the title to such lands, streams and ponds as might be necessary. Nor can we reconcile that policy with the extension of that land area from the 300 acres thus stated, to more than 500, including the so-called Nichols pond, now a part of the reservoir. The city acquired and paid for the increased quantity of land, and in resisting in the supreme court the plaintiffs’ application for an injunction, and in showing cause for a mandamus against the water board, prevailed by alleging that the title to the land had been duly acquired, and claiming the consequent right of possession. It is quite apparent that yet more land might have been taken under the act of 1871, had that been necessary. It would seem, therefore, that neither the legislature nor the city intended to adhere very closely to the plan of July, 1870. The extension of the land and of the water area may not have been of equal necessity or importance,- but the power and the election to do either deserve attention in considering the claim now presented on behalf of the defendants. That claim, if sound and enforced, would disaffirm the title of the city to the land except the 300 acres, as well as prevent a recovery for work done thereon, and would justify the reclamation of the money paid for what is now alleged to be an excess of labor and an excess of land.
It appears, from the proofs in the case, that several methods for securing an increased supply of water for the city had been proposed prior to the legislation to which we have referred. That of a storage reservoir was finally approved. That was the plan which the act of 1871 directed to be carried out, and the word plan, thus used, distinguishes this method from the other projects which had been suggested. The legislature intended that the title to the necessary land, 300 acres or more, should be acquired, that the Hempstead reservoir should hold one thousand' million gallons of water, .and taking the statute as it reads, cost not to exceed fourteen hundred thousand dollars. Of the mere details of the work and materials, how much of each and how applied, — matters depending upon practical skill and experience, — the legislature could not well have taken cognizance.
We might agree with the learned counsel for the defendant, if it were material, that a municipal corporation cannot be held on an implied undertaking. ' But here was an express agreement, So, too, if we overlook cases like the Harlem Gaslight Co. v. Mayor, &c. of New York, 33 N. Y. 309, and Muller v. The same, 63 Id. 353, we might agree that “the principle of quantum meruit cannot be applied.” But the prices for this work' were fixed, and the method of fixing the prices of extra work, if any, prescribed. So also, we accept the definition of the word “specification” as given on the argument. But the criticism is of no moment. The paper called a specification had
According to the thirteenth section of the specifications, the dam at the southern end of the reservoir was to be placed on such ground as the engineer should direct. It was placed about 200 feet further south than had been at first contemplated. That added to the space within the reservoir, but not to the expense of construction. The same section provides for an intermediate dam, “ should such division dam be considered necessary.” It was not found to be necessary, and was abandoned, thus avoiding an expense of from $230,000 to $240,000, and, as the referees find, without prejudice to the reservoir. It was well that the questions as to the location of one dam and the building of the other were held for mature consideration. But had it been otherwise, the objections that dispensing with a useless dam, and removing the other to a better site than that first selected, were departures from the plan, would not be entitled to much respect.
The propriety, and, in an undertaking of this extended character, the necessity of reserving the right to make changes in the construction and work clearly appear in relation to the dam at the Nichols pond. That dam was to have been the northern boundary of the reservoir. It gave way, was repaired, gave way
One of the most delicate, if not difficult questions arising in the course of the work had relation to the height of the new dam, and, of necessity, to that of the water to be held by it. In what is called the plan, the flow line, representing the surface of the water, the reservoir being full, was put at thirty-two feet above the tide. Many citizens, including Mayor Kalbfleisch, were apprehensive that the dam, built at the height required by that flow line, would not be safe. So, after much consideration by the engineers, the line was lowered from thirty-two to twenty-nine, the dam to be conformed to that reduction. The consequences were an increased amount of excavation at great expense, the saving of the cost of building a portion of the dam three feet high and fourteen hundred feet long,' the contributions of water from the springs reached by the deeper excavations, and the unquestioned benefit of a dam safer and more durable than it would otherwise have been.
All the changes made in the work have been fully stated and considered by the referees. After careful deliberation, we agree with them that “the chief engineer deemed each and every one of those changes to be necessary and proper, and in directing them to be made, he acted in good faith ; and none of the changes were directed or made with the intention of increasing the profits of the plaintiff's, or for the purpose of benefiting them in any manner;” that “the additions, omissions and changes did not, nor did either of them, change the substantial plan for furnishing an increased supply of water for the city of Brooklyn, adopted by the common council,” and that “none of the changes made by Colonel Adams, which the plaintiffs carried out under his direction, were outside of the plan authorized by the common council in such a sense as to defeat the plaintiff’s right to recover.”
We have had occasion to say that the contract was valid and could have been enforced. The case of Clark v. Mayor, &c. of New York, 4 N. Y. 338, would suffice to show that agreements in such form are not regarded with disfavor. It was there held that, in a contract as to a section of the Croton aque
These plaintiffs were at work on the dam when they were directed to quit: in the expressive language of the referees, “were driven from it.” That order, which plaintiffs were bound to obey, as the city had the right to take possession of its property, was given under the erroneous impression that the money appropriated for the work had been exhausted. It would seem that the dam had been nearly completed. We take extracts, as to the state of the excavation and of the dam, from the deposition of Mayor Schroeder used before the supreme court, and, as matter of record, before the referees. Thus he says, “Thatsuch excavation is complete to the extent requisite to the holding of 1,000,000,000 of gallons of water, but the stone wall or dam has been erected to the height of only twelve feet,” . . . “ and all that is necessary in order to attain the object for which the said reservoir was constructed, and to develop its full efficiency, is to complete said stone wall or dam, which can be done at a cost not exceeding $20,000.” General Slocum, president of the board of city works, gave a like estimate of the cost. They were both speaking, no doubt, with reference to the reduced prices of labor in the market. In the contract which they afterward gave to Brady, he undertook to finish the dam, build the gate-house and other necessary works connected with the dam, for $22,799.60. At the time the plaintiff’s work was stopped there was more than $57,000 of the appropriation In the treasury, and other sums had been misapplied.
We are disposed to hold firmly to the distinction which exists between municipal and other corporations in respect to inferences or imputations of assent, adoption, ratification, and the like. But there are certain rules of conduct, principles so equitable as to command almost universal respect, worthy of observance by a municipal government. In contracting for, and
The referees state that there was substantially no dispute before them as to the performance of the work and the furnishing of the materials, as claimed in the plaintiffs’ bill of particulars. On the argument before us one of the learned counsel for the defendant made a like statement, with the suggestion that, for that reason, a compulsory reference should not have been ordered. It is well known that the application to refer would not have been granted if it could have been foreseen that the case would be thus tried on the mere questions as to the liability of the defendant, or if a stipulation, admitting the account as stated, but reserving the other questions, had been filed. But the
The referees find that there remains unpaid to the plaintiffs on account of the work, after the deduction of payments, the sum of $167,799.77, irrespective of interest. That is a finding of fact, and cannot be regarded as against the weight of evidence. It was strictly in accord with the proofs, and we have no power to reverse it. It must, therefore, stand.
I am of opinion that, the referees were correct in stating the account of sums which were to be regarded as misapplied, and in the restorations thus made to the fund. They regarded that fund, the $1,400,000, as the limit of the appropriation for this work, and found, as a necessary result, that the judgment in this action could only be entered for the balance thereof remaining unapplied, with interest. The defendant prevails thus far, and that determination, in a strictly legal sense, was correct. We concur with the referees and with the defendant’s counsel in their construction of the act of 1871 in respect to the limit of the appropriation. Whatever ground of complaint the plaintiffs may have, regarding the amount of the judgment as inadequate, the defendant has no legal cause to complain. It cannot be said that the contract was ultra vires, as if it provided for an expenditure greater than the appropriation.
I am of opinion that the act of 1875 (L. 1875, ch. 258), which authorized the city to issue its bonds to the amount of $500,000 for the completion of the reservoir, was a ratification of the prosecution of the work.
The questions as to the supposed obligation of the plaintiffs to return money received, and as to the effect of voluntary payments, need not be considered.
After a careful examination we think that none of the exceptions were well taken.
As to the appeal of the plaintiffs, we have only to say that the provision of the code giving an appellate court power to reverse, affirm or modify a judgment appealed from, involves a limitation and does not au
McCue, J., concurred.
In Miller v. Milwaukee (14 Wisc. 643, [1861]), opinion by Dixon, Ch. J., it was held that the general powers possessed by municipal corporations at common law, these words occurring in the defendants’
“We are of opinion that the counselors and aldermen possess the power, and that it was rightly exercised. Municipal corporations are instituted for the advancement and regulation of trade, the local administration of justice, and the better government of their particular vicinities. And for these purposes they are by the common law invested with the power of making- ordinances and by-laws. Willcock on Mun. Corp. 16 (12 Law Library, 10). They may also elect, govern, and remove their members, and regulate their franchises and property. Id. 298 (12 Law Library, 164). They possess power to lay out, open and repair streets and highways, to establish companies to protect the property of the citizens from destruction by fire, and to levy taxes to defray the expenses.”
In Sturtevant v. Alton, 3 McLean, 393 (1844, opinion by McLean, J.), — Held, that a municipal corporation having power to grade streets, has necessarily power to make contracts respecting the same and every incidental power necessary thereto.
In Rome v. Cabot, 28 Geo. 50 (1859, opinion by Lumkin, J.),— Held, that the construction of water-works is within the general power conferred on a municipal corporation to make all contracts which they deem necessary for the welfare of the city.
Where, under the provisions of a city charter, a contractor is only payable out of a particular fund, the city will be liable to him if that fund is misappropriated by the common council. Lansing v. Van Gorder, 24 Mich. 456. And see 6 Id. 51.
A warrant for the payment of a sum named, “out of money in the treasury not otherwise appropriated,” — Held, to mean that the payment should be made out of money not appropriated to special purposes, and that the creditor need not show that there was money in the treasury, before suing, as the county was liable, whether there was any there or not. Campbell v. Polk, 3 Iowa, 467.
Where money belonging to the drainage fund of a town has been paid to the treasurer thereof it continues to be in the town treasury in contemplation of law until legally paid out therefrom; and the fact that the supervisors had used it, without legal authority, for another purpose, before entering into a contract for drainage, will not relieve the town from liability on such contract. Holil *. Westford, 83 Wis. 334.
Where a contractor to erect a public building, after the dismission of the committee through whom the contract was made, and a rescission of the order appointing it, and notice by the justices not to go on with the building, still continued to act under such committee, and, by its direction, made material departures from the specifications of the contract, — Held, that lie forfeited his right to recover the price agreed on in the contract. McCoy v. Harnett, 8 Jones (N. C.) L. 272.
Other cases heretofore referred to, it will be seen, do not sustain the view that a municipal contract is void as ultra vires, because it requires more money than had been appropriated; and this could not be justly sustained because the contractor would then be liable to repay everything that he had received from the beginning; if there be a prohibition on exceeding a certain entire cost, the contract may be ultra vires as to the excess. See also Jackson County v. Hall, 53 Ill. 440.
To same effect, Hasbrouck v. Milwaukee, 21 Wisc. 217, 235.
As to uncompleted work, see Penn Township v. Perry Co., 78 Penn. St. 457.
Dissenting Opinion
[Dissenting]. — As I do not concur in the decision to be given in this case, it is, perhaps, proper that I should make a brief memorandum, stating in general terms the ground of my dissent.
The only authority for the construction of the work upon which the plaintiffs were employed, is to be found in the act of 1871, which provides that “it shall be the duty of the permanent board of water and sewerage commissioners of the city of Brooklyn, to proceed to carry into effect the plan for furnishing an increased supply of water for said city, and for such extension of the present water-works of said city, and for the construction of such further reservoirs, conduits, and other structures, as may be necessary for that purpose, heretofore submitted by said board to the common council of the city of Brooklyn, and approved by a resolution of the board of aldermen of said city on the eleventh day of July, 1870, provided, the whole expense thereof shall not exceed the sum of one million four hundred thousand dollars,” etc. To that end, the said board is authorized to acquire in the name of, and for the city of Brooklyn, title to such lands, ponds and streams, as may be necessary therefor, and upon the acquisition of the same to “cause the necessary work, to carry said plan into effect, to be done.”
It is plain that “the whole expense,” which is not to exceed the specified sum, is the entire cost, not only of acquiring the necessary lands, ponds and streams,
The bearing of this will very shortly appear..
At the time the contract with plaintiffs was entered into, certain expenditures had been made out of the amount authorized and appropriated as above stated, including the sum of $110,000 for lands, ponds, and streams designed for the reservoir. When the plaintiffs entered into their contract, they were bound to take notice of the limitation upon the power of the city to contract with them, and of the condition of the fund at that time. They could not bind the city by any engagements contravening the law under which its officers and representatives acted. If the contract had stipulated for a gross sum as plaintiffs’ compensation for the construction of the reservoir, and that sum had been in excess of the appropriation, or of the part thereof then at disposal, thus in terms disregarding the limitation, it would have been illegal and the plaintiffs could not have enforced it.
Instead of that, it provided for the performance of certain itemized work at detailed prices, subject to the directions of the engineers of the water board. It also provided for extra compensation for haulage beyond a given distance, an item which turned out to be over $100,000 (See 23rd and 25th findings of referees), and for modifications and changes by the chief engineer during the construction of the work (See 15th finding).
It is obvious that under a contract so elastic, the possibilities were unlimited. The plaintiffs, having-contracted upon these terms, are responsible for the natural results that flow from them. According to the findings of the referees the results are these : The plaintiffs have already performed work and furnished
It is no answer to say that the aggregate has been increased by reason of directions given by any of the
The referees hold that the plaintiffs must be limited in their recovery to the unexpended balance of the $1,400,000, so far giving effect to the limitation contained in the law, yet they award the plaintiffs the whole of that balance, leaving a very large and material portion of the work undone or incomplete. In this I think they were in error.
As we have seen, the statute required that the sum of $1,400,000 should cover the whole expense of carrying the work to completion. It seems to me, that it is as much a violation of the statute to use all the appropriation for a part of theworlc, as it would be to finish the work and exceed the appropriation. Of course, before the work can be completed a new appropriation must be made, and, in fact, legislative aid has already been invoked to that end. If the restriction in question is valid for the purpose of limiting the plaintiffs’ recovery, I cannot see why it should not prevent their recovering at all. By the present judgment the city is compelled to pay the full price of a completed enterprise for an unfinished work which it has upon its hands. To me this looks like nullifying the law.
It is claimed, however, that the act of 1875 ratifies whatever had been done in excess of authority previously given. The section from which this result is argued, is as follows:
“§ 1. Upon the approval of the plans, specifications and estimates therefor, by the common council of the city of Brooklyn, the board of city works of said*40 city are hereby authorized to complete the Hempstead reservoir, and for that purpose the said' city is hereby authorized to issue such bonds as said common council may deem necessary, not exceeding $500,000 in amount; and no such plans, specifications and estimates, shall be approved, nor shall such work be done, except upon a stipulation, under suitable penalties, that the work aforesaid shall be fully finished and completed for the sum aforesaid.”
This recognizes the fact that the city has an unfinished reservoir upon lands which it owns, and is designed to meet the necessities of the case, by authorizing the city to raise money to complete it. It does not refer, even by implication, to any previous or then existing contracts, and I am unable to see how it can be construed into a ratification of such contracts, or a condonation of their illegality. The law simply regards the physical fact of an unfinished reservoir on city lands, and the absence of a fund to complete it. I have said it does not refer to contracts already made by the city. Perhaps, however, the latter part of the section, exacting a stipulation under penalties, that the work “shall be fully finished and completed” for the sum specified, was prompted by the fact that a former limitation had proved ineffectual. But this can hardly be considered a ratification of what the legislature was now attempting to prevent the repetition of, by additional guards.
With this view of a controlling principle in the case, it is not needful to discuss any of the other questions, especially such as might relate only to the amount of recovery.
Finding myself not in accord with my brethren, nor -with the report of the referees, I must, of course, distrust my conclusion ; and yet it appears to me so inevitable that I feel compelled to adhere to it, unpleas
NOTE on municipal contracts.
I. Necessity of inviting proposals (see p. 1).
The obligation to let to the lowest bidder does not exist unless imposed by express law, nor even then, according to the better opinion, is it an inflexible rule to be applied against public policy, upon a literal construction of the act, and beyond its apparent intent. The following recent cases, and the authorities referred to in them, illustrate the question:
Matter of Dugro, 50 N. Y. 513 (1872, opinion by Allen, J., all concurring). Although the charter of New York requires all work (over $1,000) to be let by contract to the lowest bidder, yet the ancient power of the city over the streets must not be impaired by doubtful construction; and if the city desire to use a patent pavement, the fact that advertising for bidders became necessarily an empty form, does not affect the validity of the contract.
To same effect, Hobart v. City of Detroit, 17 Mich. 246, 253, opinion by Cooley, Ch. J.
Bennett v. City of Jefferson, 21 La. Ann. 143 (opinion by Howe, J., 1869). The city of Jefferson has the right — under its general powers, conferred in the usual form, to control and improve streets, and raise the expense by tax or loan, — to lay a patent pavement; but when it proceeds under a clause allowing property owners to petition for an improvement to be made partly at their expense, provided that such work shall be done by contract by the lowest bidder, then they cannot adopt a patent pavement, for this precludes all real competition. The court say that the New York and Michigan cases rest on public policy, under a statute, which if literally pushed to the extreme, would cut off the cities from any patent however desirable.
Yarnold v. City of Lawrence, 15 Kans. 126, 131 (1875, opinion by Brewer, J., all concurring). Where the only provision of law as to advertising was, that before any contract for street improvements should be let, the city engineer should make and submit to the council an estimate of cost, and that in advertising for bids such estimate should be published (without expressly requiring advertising):—Held, that the city might contract without advertising; and if they advertised, were not bound to accept the lowest bidder.
County commissioners who are required by law to let to the lowest
Section 123 in the charter of Elizabeth of 1863, — which directs that all contracts for doing work, or furnishing materials for public works, exceeding $100 in amount, shall be advertised, and given to the lowest bidder, —is inconsistent with a resolution of the common council to use the Stow foundation pavement, and advertising for proposals for the same; because it is patented, and one firm has the exclusive right to use it in the city. State v. Elizabeth, 35 N. J. 351.
Where the common council of a city, having advertised for bids for paving a specified distance, subsequently entered into a contract with the lowest bidders to pave a portion only of the distance, “or further if ordered,” and after that was completed, ordered the remainder to be done by the same contractors, — Held, that the whole work was covered by the original contract, and it was not necessary to advertise for proposals a second time for the completion of the latter portion of the work. Brevoort v. Detroit, 24 Mich. 322.
Proposals for a public contract, and an acceptance of them by the government, may be held to constitute a complete contract, although they contemplated that a written agreement should be subsequently executed, which was not done. Adams v. United States, 1 Ct. of Cl. 192.
Under 1 L. 1870, p. 876, § 13, — which authorized the commissioner of public works of New York to cause water meters to be placed in certain establishments for the purpose of ascertaining the water rate, — the commissioner has power to contract independent of the requirements of the charter (L. 1870, p. 366, § 104), passed shortly before, requiring contracts made or let by the heads of departments to be by public proposal. People ex rel. Navarro v. Van Vorst, 64 Barb. 205. S. P., Greene v. Mayor, &c. of N. Y., 60 N. Y. 303; rev’g 1 Hun, 24.
“It is a sufficient objection to a naked unexecuted contract made by an officer of the government, that he has neglected to comply with the provisions of an act of congress which requires that advertisement for proposals shall precede the letting of the contract. But, after a party has entered into a contract with the government in good faith,
As to changes where bids are required, see p. 2, ante, note.
,11. Power to malee changes in the plan or in the wo?de (see p. ).
In the case of the Milwaukee harbor, the statute authorized the city to construct a harbor, and required the common council to file accurate plans and let the contract to the lowest bidder ; and authorized them, after popular vote, to issue bonds therefor to the amount of $50,000. The contract reserved the right to the city to direct alterations or extra work. The city subsequently modified the plan, increasing the cost far beyond $50,000, and thereafter the legislature authorized them to issue such amount of bonds as might be necessary to complete the harbor, and this act the city accepted. Held, that it ratified their previous conduct in altering the plan. Hasbrouck v. Milwaukee, 21 Wis. 217, 235.
In the Rochester Sewer case, the commissioners of public works of Rochester passed an ordinance for “deepening and enlarging of Platt street sewer from, &c. to, &c. by enlarging that portion under said mill, constructing the tunnel under the race and deepening that portion of the sewer in Mill street and Platt street, to the west line on said street, said sewer to be not less than 7 feet square, and an arch cover, except that portion which is tunneled, and to be at least 25 feet deep at State street, &c.;” and ordered an assessment of $23,000, the estimated expense. They advertised for proposals accordingly, and one Spaulding made an alternative proposal, — one alternative
The supreme court held that the commissioners’ ordinance having provided for a cut or merely deepening of the sewer in the streets named, they could not afterward change the plan and award a contract in the same proceedings for a tunnel sewer, and hence owners of real estate liable to assessment could enjoin the proceedings. 5 Hun, 67.
The court of appeals reversed the judgment, holding that as the general purpose of the ordinance was for a sewer, the board had ample authority to contract in a mode different from that first adopted, although it increased the expense, especially as they did so on petition of parties liable to be assessed. 1876, Op. by Miller, J., all concurring, Lutes v. Briggs, 64 N. Y. 404; rev’g 5 Hun, 67.
A preliminary estimate of the cost of a street improvement, made for the purpose of determining who is the lowest bidder, will not prevent the city from assessing a larger actual cost on the property benefited, where the discrepancy is without fraud. In such assessment, the cost of neceesary surveying and improvement certificates, collection expenses, and interest may be included. The fact that a penalty to be incurred by the contractor for delay, has not been exacted from him, to reduce the cost of the improvement, will not invalidate the assessment, when the facts are such that the proper city officers may have honestly determined that such penalty ought not to be enforced. State v. Town of Guttenburg, 38 N. J. 419.
The inhabitants of a town voted to build a town-house according to a plan and specifications agreed upon, and appointed a committee to contract for and superintend the erection of the same, “with power to make any slight alterations in the plan, which should in their wisdom be deemed just and proper.” Held, that whether the authority given to the committee to make such slight alterations would justify them in employing an architect to draw plans for the purpose, was a question for the jury. The court in effect held, that if the intent of the resolution was to authorize them to modify the exterior, or the expenditure therefor, they might employ plaintiffs. Upjohn v. Taunton, 6 Cush. (Mass.) 310.
A municipal contract providing that the work shall be done under
A municipal corporation forbidden by law to make any additional allowance beyond the legal claim under any contract with them, may nevertheless waive a forfeiture incurred by a contractor by not completing performance by the day named in the contract. People ex rel. Cunningham v. Brennan, 18 Abb. Pr. 100.
The plaintiff agreed to do the cutting and filling necessary to reduce a street to a certain grade, under tire direction and supervision of the defendant’s engineer. Held, that the contract referred to the decision of the engineer in determining the manner in which the work should be done, and that, if by his direction the plaintiff blasted to below the required grade, and then filled up to it, the city were to pay for all that work. Blake v. Dubuque, 2 Iowa, 492.
Where an application was “for re-opening a communication between Albemarle sound ... by the construction of a breakwater, ” Attorney-general Cushing advised that the breakwater was but an incident or means, and the approjrriation could be used without reference to whether a break-water was constructed or not. 6 Op. Att.-Gen. 19.
In the case of the Milwaukee harbor, held, that under the power of the harbor committee and city engineer to oversee and direct as to the best manner of executing the contract, a “protection work,” so-called, and apparently necessary to the economical building of the harbor, was within their power to direct, and the city were liable for a quantum meruit. Hasbrouck v. Milwaukee, 21 Wis. 217, 285.
Where a charter authorized the city council to construct sewers of such dimensions as they should prescribe by ordinance,' — Held, that an ordinance authorizing the construction of a sewer, “to be of such dimensions and of such materials as may be deemed requisite by the city engineer,” was invalid. St. Louis v. Clemens, 43 Mo. 395.
So, where a resolution of a county board of supervisors for the removal of the county seat, provided “suitable guarantees ” should be given for the erection of county buildings at the new location, free of cost to the county, was passed by a two-thirds vote as required by law, and the next day the approval of the guarantees was referred to a committee of the board by a majority, but not a two-thirds vote, — Held, that the resolution could not operate as an absolute authority for removal, until the condition was performed and suitable guarantees given, and that the board could not thus, by a mere
Sections 62 and 64 of L. 1843 (R. S. Ind. c. 16), — which authorizes boards of county commissioners to enter into contracts in writing for building bridges over watercourses, and to appoint one or more persons to superintend the same, — do not empower such commissioners to appoint agents to make such contracts. Potts v. Henderson, 2 Ind. 327.
Where a contract is to deliver a specified quantity of lumber to the government, and the words “ more or less ” are added, with.no reference to any other method of determining more exactly the quantity intended, or removing the uncertainty, the parties will be held to a quantity approximate to that named, allowing only a variation reasonable under the circumstances. But when the words “more or less ” have a reference to something by which the exact quantity intended can be ascertained, and the uncertainty removed, then the words will limit or extend the quantity named to that which may be ascertained and determined by the reference. Brawley v. United States, 11 Ct. of Cl. 522. Compare Harrington v. Mayor, &c. of N. Y., 10 Hun, 248.
The power vested in the head of an executive department of the government, to make contracts for work or materials for the government, does not imply power to rescind or alter such contract when made. 9 Op. Att-Gen. 80.
Where the employer reserves to itself in the contract, the privilege of changing the plan, its making such a change does not necessarily entitle the contractor to cash payment in lieu of the mode pre scribed by the contract. Hasbrouck v. Milwaukee, 17 Wis. 266.
Power of the street superintendent to enlarge the time for the completion of a contract for street improvements. Conlin v. Seamen, 22 Cal. 546; Houston v. McKenna, Id. 550; Taylor v. Palmer, 31 Id. 240.
A building contract in writing contained a stipulation, that the employer reserved the right of making alterations in the plan of the work during its construction, the expense of which should be agreed on at the time; but that no extras should be allowed for, under any pretext whatever. Held, that the employer was not liable for the increased cost of the work, occasioned by alterations made by the builder, to which the employer assented, where there was no bargain as to the price of such alterations, according to the terms of the
If a contract with a railroad company for constructing its road provides that the contractor shall not deviate from the contract, nor receive any pay for extra work, unless a written order for the same is made and signed by the engineer, the contractor cannot recover for extra work done on the verbal order of the engineer, even if there is another clause in the contract which provides that the engineer may direct alterations in and additions to the work. White v. San Rafael, &c. R. R. Co., 50 Cal. 417.
In an action to recover for labor and materials furnished under a contract to build four houses, which were destroyed before completion by the falling of a stone wall on another part of the defendant’s lot, — Held, that the contract itself implied an undertaking, on his part, that the place chosen was free from danger, unless the plaintiff had assumed the risk of danger from the condition of the property. If the loss was occasioned by an accident that could have been prevented by reasonable care, skill and expense, it should be borne by defendant. Sinnott v. Mullin, 82 Penn. St. 333. Compare School Trustees of Trenton v. Bennets, 27 N. J. L. 513; Dermott v. Jones, 2 Wall. 1.
Where a contract provided that the claimants shall erect shops,' sheds, &c., for the defendant’s workmen “ on the written order and under the direction of the party of the second part,” (the supervising architect of the treasury), — Held, that it was not enough, in an action on the contract, to allege that certain barns, boarding-houses, &c., were erected for the defendant’s workmen, “.with the full knowledge and consent of the officers of the United States, and upon their requirement, and were necessary,” &c. Dix Island Granite Co. v. United States, 12 Ct. of Cl. 624.
Plaintiff claimed to recover for rock excavation made outside the lines of the street, in sloping the sides, which the referee found to have been necessary to effect the excavation within the street. Held, that the outside excavation was not included in the contract, and as it was only necessary as a means for accomplishing the work contracted for, plaintiff was not entitled to recover therefor. Voorhis v. Mayor, &c. of New York, 62 N. Y. 498.
A made a contract to execute certain “excavation, refilling and repaving,” for B, and B agreed to pay as a “ compensation for such excavation, refilling and repaving,” as follows: “for executing the digging” and refilling, seven cents per cubic yard; and for repaving &c., four cents per square yard. A considerable portion of the work was through hard-pan and rock, worth from seventy-five cents to one
The plaintiff entered into a written contract to make excavations, and commenced work, but afterwards gave notice to the defendants that he could not go on at the price named in the contract, and must abandon the work unless defendants would allow him more than the contract price for a portion found extra difficult. The defendants told him to quit that portion of the work until some arrangement could be made in regard to it; and the plaintiff did quit it for about two weeks, when it was" resumed under a new agreement, by which the plaintiff was to receive a reasonable compensation for excavating the hard material. Held, that this was such a rescission of the original contract in respect to that portion of the work, as would have precluded the defendants from maintaining an action to recover damages for its non-performance, afterwards. The new agreement was binding, and must control. Hart v. Lauman, 29 Barb. 410.
Where the plaintiff contracted in writing “to excavate and build a good, firm, and substantial sewer,” specifying particularly the prices to be paid for “all the excavation, whether hard-pan, quicksand, caves or otherwise, and “for the blasting and removing of rocks,” and claimed in this suit extra payment above the contract pi’ice, which he admitted had been paid, — Held, that no evidence was admissible to show that extra work had been done, or to show that it was rendered necessary by the discovery on the line of the sewer of a kind of rock not before known in New York, and much more difficult of removal than those usually found, and of a quality which could not possibly have been contemplated in making the contract. Devlin v. Mayor, &c. of New York, 4 Duer, 337.
The original plan for a piece of work was abandoned, and a new one adopted, which increased the expense to such a degree that the original plan could not be followed as a guide, even to the extent of the expense estimated on such original plan. The contractor, in making his estimates, acted under the directions and with the knowledge of the employers. Held, that it was not necessary for the contractor, in order to recover, to show what work and materials were embraced in the original contract, and what was extra work. Hasbrouck v. Milwaukee, 31 Wis. 217, 235.
III. Ratification or estoppel (see p. 5 ).
§ The general principle of implied contracts, and of ratification by express assent; or by acts or conduct inconsistent with any other
The foundation of the exception is that statute restrictions and inhibitions cannot be evaded by resorting to estoppel by assent of officers, &c. McDonald v. Mayor, &c. of N. Y., 68 N. Y. 23; Inhabitants Weismer v. Village of Douglas, 64 N. Y. 91. Unless the city has actually collected the fund which equitably belongs to the contractor. Nelson v. Mayor, &c. of N. Y., 63 N. Y. 535; rev’g 5 Hun, 190. Where it had power to act, a municipal corporation may estop itself like other parties to a contract. County of Randolph v. Post, 93 U. S. (3 Otto) 502, 513, and cases cited. Even the State and its agents may be estopped. Peck v. Burr, 10 N. Y. 294.
The distinction is, perhaps, best illustrated in two recent California cases. In Argenti v. San Francisco, 16 Cal. 255; cited in 63 N. Y. 544 (1860, opinion by Cope, J., and Field, J., concurring in the result), it was held that a municipal corporation having had the benefit of a contract for work and materials, could not, in an action founded on the contract, contest its validity, on the ground of want of delegated authority in the officer who made the contract. The court concede that an executory contract made without authority cannot be enforced, but say that a different question arises where the contract has been executed and the corporation has received the benefit of it. In such a case they held that the law interposes an estoppel and will not permit the validity of the contract to be called in question. It appeared in that case that the improvements, — the grading and planking of certain streets, — were constructed for the exclusive benefit of the city and its inhabitants ; that they were of valuable and permanent character, and constructed in pursuance of contracts entered into with an officer of the corporation in his official capacity; that in making the improvements reliance was placed on the validity of these contracts, and the obligation of the city to pay as provided, and that the improvements were made under the immediate supervision of an officer of the city government, and when completed were approved of and received by him on behalf of the city ; that the
Reld, that although there was no evidence that the agent who signed the contracts was expressly authorized to do so, the knowledge and silence of the city authorities was equivalent to a direct sanction (reviewing and relying on the New York and California authorities).
Field, J., was of opinion that as the charter vested in the common council the authority to order the improvements, and a general ordinance had designated the officer under whose supervision on behalf of the city the work should be done, and an ordinance had indicated an intent of the common council to make the improvements, and advertisement was made, proposals received, and the work awarded, the question whether the officer executing the contract on the part of the city had authority, was of no moment; the contractor, having performed as if there had been a formal contract, could recover.
In Zottman’s case, 20 Cal. 96 (1862, opinion by Field, J., Cope, J., concurring), held that where a charter prescribes a mode in which all contracts shall be made, by ordinance requiring bids, a contract made in any other way cannot be made valid by ratification or acceptance of the work. In this case, a construction contract having been made, the superintendent under whose supervision it was required to be performed, and the special committee of the common council to whose satisfaction it was to be completed, found that extra work would be necessary, and accordingly ordered it in presence of various members of the city government, and the work was done to the knowledge of the common council.
Reid, that no ordinance authorizing the extra work having been proved, the contractors could not recover for it. Their employment with knowledge of the common council, and the fact that the corporation had received the benefit, could not create liability against the statute.
This conclusion was established by Field, J., in accordance with his views in Argenti v. San Francisco, 16 Cal. 255, and (in so far as the two are inconsistent) overruling that case with the concurrence of Cope, J., who withdrew from his former opinion and concurred with Field, J.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.