Goodwin v. McCormick
Opinion of the Court
This action was brought to foreclose a mechanic’s lien affecting premises located in Brooklyn. The appellant, Kate McCormick, is the owner of the property. The respondent Feldmann was the contractor for the erection of five houses on the premises, and the other respondents have mechanic’s liens. The case was tried before a referee, who found that Feldmann, in August, 1885, entered into a contract with one James Gardner, the general agent of said Kate McCormick, the owner, to erect the five houses for the sum of $23,400, to be paid for in installments as th'e work progressed, the final payment, when the work was completed, to be $5,400. The referee further found that, after the work was commenced, the contract was, by mutual consent of the owner and contractor, so far departed from, as to the work to be done, that, as a whole, the work was not substantially that called for by the contract; that such departures involved serious and material increase in the cost; and that the parties did not agree that the work should be done for the contract price, nor for any certain price, nor that the houses should be completed as a condition for the payment of any part of the price. The referee also finds that Feldmann did not entirely complete said houses; that the value of the labor and materials done and furnished was $24,200, and that the payments amounted to $17,200, leaving a balance due of $7,000, with interest; that neither the original contract nor the evidence furnishes (Zato from which it can be ascertained what the parties originally estimated or agreed upon to be the value of such of the labor and materials done and furnished as the original contract called for, or what was agreed to be paid therefor, or that any certain sum was agreed to be paid- therefor. The referee orders judgment in favor of the lienors, and for the balance, after paying the liens, in favor of Feldmann, the contractor; and the owner, Kate McCormick, appealed from the judgment entered in conformity to the referee’s report.
The learned counsel for the respondents Goodwin and Feldmann quotes in his brief from 1 Add. Cont. foot pp. 585, 586, and the law applicable to the points raised on this appeal is there correctly and concisely stated. “If work has been agreed to be done, and materials supplied under a building contract for certain estimated price, and there has subsequently been a deviation from the original plan by consent of the parties, the contract and estimate are not on that account excluded, but are to be the rule of payment, as far as the contract can be traced to have been followed, and the excess only is to be.paid for according to the usual rates of charging; but if the original plan has been so entirely abandoned that it is impossible to trace the contract, and to say what part of it shall be applied, the workman may charge for the whole work by measure and value, as if no contract at all had ever been made.” We have quoted freely from the report of the referee, and in his own words, and shall also assume that the law is as stated in the foregoing quotation from Addison; but when we examine the testimony we are unable to agree to the findings of fact of the learned referee. It appears that there were many variations from the contract, that such changes were made by consent of the par
Case-law data current through December 31, 2025. Source: CourtListener bulk data.