Paddleford v. State
Opinion of the Court
On the 11th day of June, 1912, the claimants made a contract with the state, through the state commission of highways, for the improvement of county highway No. 705 in the county of Chenango. The claimants began the construction of the road promptly. Later, a steel bridge on said highway was found to be defective and in such condition that probably it was insufficient to carry the traffic after the improvement of the highway. The state’s division engineer directed the resident engineer to arrange with the town of Sherburne for the construction of a concrete bridge, to replace the steel bridge, and abutments, the town to build the top, or “ slab,” and the state the remainder, that is, the abutments, pier and wing walls. This arrangement was made. The resident engineer, pursuant to instructions from the divi
The state contests the claim on two grounds. '
First. That the items for which claim is made were not included within the original contract of June 11, 1912, and were not provided for by any supplemental agreement in writing, executed by the commission, and therefore constitute no claim against the state.
Second. That the said items were unauthorized by
This inquiry involves no doubt concerning the good faith of the claimants. It is not denied that the work was done properly, and that the amounts claimed are reasonable, and that the claimants have not been paid. Naturally, the facts tend to create some sympathy for the claimants, in their predicament, but the court has no other recourse than to determine the rights of the parties, in consonance with the law applicable thereto.
The Highway Law reads, “All contingencies arising during the prosecution of the work shall be provided for to the satisfaction of the commission and as may be agreed upon in the original or by a supplemental contract executed by the commission. "Laws of 1909, chap. 30, § 130, subd. 9. There is a suggestion in the brief of the claimants ’ counsel that this work was done under the original contract, because the latter contained provisions for the alteration of the plans and specifications, and for changes in quantities and because this work was of the same character as that covered by one of the unit prices in the original contract. There is no merit to this contention. These provisions in the original contract refer to work fairly within the purview of the latter, although, perhaps, differing in detail, measurements or quantity from that originally contemplated. The original contract, plans and specifications contained no provision for the construction of any bridge. No bridge was then contemplated by the parties. The claimants’ proof shows, and their brief says, that this work was done pursuant to the arrangement made subsequently to the execution of the contract, to which we have referred, and for which plans and specifications were made long afterward.
. -The provisions of the contract, which are quoted bi-
It is patent, therefore, that the work for which claim is made was not provided for in the original contract. The statute requires that it shall have been provided for by a supplemental contract, executed by the commission, if recovery is to be had. The claimants are not able to produce such a supplemental contract, as authority for the performance of the work, and as a basis for their claim. Not only did the commission omit to execute a supplemental contract for this work, but the commissioner expressly refused to do so, and signed the supplemental contract tenderéd for his signature, only after the excision of these items therefrom,
The claimants rely on the last clause of subdivision 9 of section 130 of the Highway Law, which reads as follows : “ Such supplemental contract shall not be binding unless it be approved by the commission in case of a state highway and in case of a county highway, by
The absence of a supplemental contract, executed by the state highway commission, as a basis for recovery, is fatal to the claim. Stanton v. State, ante, p. 221.
The second objection raised by the state is equally conclusive against the claimants. This bridge has a span of fifty-six feet. The statute says, “A highway, within the provisions of this chapter shall be deemed to include necessary culverts, sluices, drains, ditches, waterways, embankments, retaining walls and all bridges having a span of five feet or less.” Laws of 1909, chap. 30, § 2, subd. 5. It is in accord with an elementary rule of construction, that the specific mention of all bridges having a span of five feet or less excludes from the definition of a “ highway,” all bridges of greater span. The statute, therefore,
But the claimants contend that they have discovered that such statutory authority is vested in the division engineer. They quote subdivision 8 of section 125, chapter 30, Laws of 1909, which reads as follows: “ He may provide for such other work as may be required to complete the construction or improvement in a proper manner.” This quotation is made out of its context. Section 125, and the subdivision thereof referred to, relates to ‘ ‘ maps, plans, specifications and estimates. ’ ’ Such is the title. It treats of the powers of the division engineer, in connection with these details, and defines what he shall do in that connection, and in the preparation of the maps, plans, specifications and estimates, as the statute specifically says, “ In respect to such highways.” It is in this connection, and in this sense, that subdivision 8, upon which the claimants rely, must be read. It confers no authority on the division engineer to do anything except ‘ ‘ in respect to such highways, ’ ’ and certainly no authority to obligate the state, without restraint, or otherwise, for the construction of bridges. It is irrelevant that
Ackersoh, J., concurs.
Claim dismissed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.