Murray v. State
Opinion of the Court
This claim arises out of a contract entered into by the claimant with the State known as “ Erie Canal — Contract
There had been prepared certain plans and specifications for the sewer prior to the advertisement for bids, which were open for inspection by any prospective bidder. The sewer was originally planned, and so appears upon the plans, to follow the bed of the feeder, and vn such plans were the records of certain borings or tests made by the State or its agents as to the character of material to be encountered by the successful bidder in the course of the work. These borings or tests were made in the bed of the feeder and showed soft material with a certain quantity of rock. Prior to the bids being received, the plans were changed, and a portion of the sewer was taken out of the feeder and thrown along the bank. This change was made before the bids were received and was well known or could have been ascertained by any person desiring to bid on said contract. The claimant was the low bidder and the contract was awarded to him.
This claimant now makes a claim composed of several items. First, he claims that by reason of the changing of the line of the sewer from the bed of the feeder to the bank, he encountered much more rock than was shown on the plans and, therefore, the State made false representations which misled him. We will deal with this item first.
There were no borings or tests made after the change in the line of the sewer from the feeder bed to the bank and the contract contains what is known as paragraph 10 which reads as follows:
“ The contractor agrees that he has satisfied himself by his own investigation and research regarding all the conditions affecting the work to be done and labor and material needed, and that his conclusion to execute this contract is based on such investigation and research, and not on the estimate of quantities or other information prepared by the State Engineer; and that he shall make no claim against the State because any of the estimates, tests or representations of any kind affecting the work, made by any officer or agent of the State may prove to be in any respect erroneous.”
Any tests shown on the plans and specifications for rock were made on the opposite side of the feeder from that along which the sewer was constructed and the feeder was of considerable width.
This claimant was a contractor of some forty years of experience and testified he was perfectly competent to judge by examination the character of the various strata of- the earth. He was particu
The bank of the feeder was dry, perfectly accessible to a prospective bidder, and this claimant by reason of his superior knowledge gained by forty years’ experience in and about Rochester, and especially gained by the laying of the water main and the building of the bridge on the immediate site of his work, could know by the most casual inspection what he was to encounter in carrying out his contract. It might also be said that he needed no inspection. He knew in his own mind. We do not think he is entitled to any allowance because of rock excavation because of there being more rock than might have been estimated by the engineer.
The contract also contained this provision as to excavations near water mains: “ The contractor will be required to exercise particular care to prevent the displacement of, or injury to, any of the water works, stop gates, water service boxes, or other water works construction, gas mains, gas services, electric systems, sewers, or other underground systems that may be exposed by the trenching.”
The authorities of the city of Rochester protested against blasting
The other items of the claim are all bound up in extra work caused by a flood and extra back fill.
It does not appear to us that there was any extra back fill as it is testified that considerable of the material excavated was left upon the bank and not used at all, and, of course, to back fill, the back fill is made by the material being excavated ahead.
Now, we come to the flood. This claimant for many years had always lived in and about Rochester and was as familiar with the characteristics of the Genesee river as any small boy is with the “ Old swimming hole.” He knew that with heavy rain and especially during spring freshets, it would overflow. He knew that feeder gates formerly had been maintained by the State to control the water of the Genesee river in connection with the old canal. He knew, or could have ascertained by the most casual inspection, that the bank between the “ Old Feeder ” and the canal had been washed out in certain places to almost a level with the bottom of the feeder, and knew that in case of a flood, water would come through the break in the bank of the feeder (and the whole feeder was on the site of the claimant’s work), and nothing was done to' prevent this. It is a fair inference to say that if the so-called bulkhead in the Lehigh Valley crossing had never been disturbed, the water would have come in just the same. It is really more than an inference. It is almost a conclusion.
The contract provided that the claimant should keep the site of the work so that the sewer pipes should be laid in the dry. He knew that the Genesee river might flood him. Therefore, it was a hazard of the contract and he should have provided for it. He attempts to excuse this because he says the State removed some logs or sticks that formed a sort of bulkhead in the Lehigh Valley
We, therefore, believe that this claimant has not brought himself within the doctrine of knowingly making false representations as laid down in the Jackson and Stewart cases, and, therefore, is not entitled to recover.
We, therefore, believe that the claim should be dismissed on the merits.
Potter, J., concurs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.