Bishop v. Jackson
Opinion of the Court
It is necessary, preliminarily in this case, to ascertain and determine the precise state in which the relation and obligations of the parties to this action to each other stood in May, 1863, after the plaintiff had accepted the iron plate bending machine made by the defend
The original contract must, therefore, be considered as having been entirely abandoned in May, 1863, except so far as regarded the work to be done, and the prices to be paid for it, and in reference to so much of the former, as related to the legs of the derrick, unmanufactured iron plates were to be furnished by the defendants, but shaped into such legs by the plaintiff, instead of by themselves, thus taking them out of the former contract. There is, therefore, of course, no room for complaint by either party, as to the non-completion of the bending machine in time, the plaintiff having superintended its construction, and accepted and used it, when it was finished, and the defendants furnishing a workshop and workmen. So, too, in regard to the iron plates, actually furnished by the defendants, the plaintiff accepted and made use of them, and thereby waived any objection as to time, although, in consequence of the delays of the defendants, he refused to- receive any more.
The only serious claims of the plaintiff in this case, therefore, are for services in the defendants’ employment; for damages in being obliged to procure elsewhere the materials and parts of his derrick which the defendants neglected to furnish, and for bad workmanship in some of that which ■ they furnished, and the expense of rectifying it, and for injury by their delay in furnishing it in a reasonable time. There was no evidence in the case of any injury by the delay, as the government completed and accepted the derrick, and only withheld the last payment, because it had furnished part of the iron and caused part of the work to be done, which was to be deducted from the last installment.
The articles omitted to be supplied by the defendants were, iron plates for the derrick legs, boom rod suspensions, lateral boom rods, cast iron couplings and patterns for them, and'diagonal rods and rivets. The iron plates furnished by the plaintiff instead of those so omitted, weighed 30,000 pounds, for which he paid from five and a half to
The value of this claim of the plaintiff for extra work, caused by the insufficient work furnished'by the defendants, was from $3000 to $4000; whether this was a fair test of the inferior value of the articles furnished to that of those agreed for, is quite immaterial, as no exceptions were taken on the trial to any refusals to charge, and the jury were, therefore, at liberty to take that into consideration.
The plaintiff testified that the defendants agreed to pay him for his services in making drawings and superintending the work, and the jury passed upon that question. He also testified that such services were worth from $4000 to $5000 a year, and he was engaged eight months, being from $2700 to over $3300. The jury, therefore, might under the evidence, have brought in a verdict of nearly $9000 as damages for all the losses. of the plaintiff, whereas they only found $6000 damages. They must also be considered as
I see no reason for interfering with the verdict. The new trial asked for must be refused, -with costs.
An order refusing a new trial was accordingly entered; from which the defendants appealed to the general term.
In this case it is not necessary to add much to the opinion delivered at special term, which I approve of.
A few observations may, however; be proper. The defendant claims that the plaintiff should not be allowed compensation .for services in superintending and furnishing plans, because under the contract he was to perform those services without charge.
Whether these services were covered by any contract, so that he was bound to perform them without compensation, was a question of fact for the jury. They have found in the negative, on conflicting evidence, and there is no reason for interfering with their' verdict.
Again, the defendants say that the plaintiff should recover no damages arising out of the unskillful performance of the work by the defendants’ workmen, because he gave directions and furnished the plans for the work, and superintended it, and, therefore, if the work was not properly done it was his own fault. And for the same reason it is claimed that if the work is improperly done the plaintiff is not entitled to compensation for giving directions, drawing plans and superintending, even if a valid contract to give a compensation therefor had been made. This depends on the solution of four questions.
Was the doing of the work improperly, the result of erro- • neous directions and plans given by the plaintiff? Or was
If the 1st, 2d and 4th of these questions, or any one of them, be affirmatively answered, then the defendants’ proposition is correct; if they are all answered negatively, and the 3d is answered afiirmatively, then it is wrong.
These four questions were questions of fact for the jury. The claims of the defendants upon the subjects covered by them, it appears from the portion of the charge contained in the appeal papers, were presented in general terms to the jfiry. There is conflicting evidence on them, and the jury have answered the 1st, 2d and 4th, negatively, and the 3d affirmatively. Their verdict should not be disturbed.
Again, the defendants say that the plaintiff broke the contract on his part by not making payments as agreed. The evidence does not support this. The agreement was to make Jackson & Brother, the attorneys of the plaintiff, to make collections from the government so far as the payments became due under the contract.
Whatever difficulty'may have existed as to the second payment, it was waived by the parties.
The third payment was not countermanded until after the plaintiff had refused to continue the contract, which refusal the jury have decided to be justified.
Judgment affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.