Board of Water Commissioners for City of Detroit v. Burr
Opinion of the Court
We are confined to an examination of the legal character of the exceptions taken on the trial.
So much has been said for the purpose of considering a request to charge made by the plaintiffs, which was refused by the court. It was “ that the alleged defects in the construction or bracing of the building constituted no default on plaintiffs’ part, unless the contractors notified the plaintiffs of such defects as being calculated to prevent the successful working of the machinery.” This the court properly refused to charge. If we suppose that (as to which we have seen the plaintiffs made no question) their engineer knew what the engines were meant to be by the contractors, or if we suppose even that the contractors, being bound to give information .as to the engines, failed so to do, the contractors were not at all bound to inspect the building as it was being -constructed, or the plans for the same, and to point out
I conclude, therefore, that the request involved an affirmance as a rule of law, that the contractors should notify the plaintiffs of the existence of defects, which the plaintiffs had covenanted should not exist, and that the court was right in refusing to charge it.
I think the request as made refers to the building after it was constructed and offered in performance for the erection of the machinery. In such case, it was-to be judged of, just as it then stood, and the contractors could not be bound to notify of any defects, inasmuch as the engineer of the plaintiffs was as capable of estimating its qualities as were the contractors. It is not entirely clear that such was the intended meaning of the request, because it was followed by a request now to be stated.
The plaintiffs further requested the court to charge,' “that any suggestions on this subject to the plaintiffs’ “ engineer, prior to the execution of the contract, did “not operate as such a notification, and must be disregarded by the jury.” I take this to have implied that if what was suggested before the contract would have operated as a notification on the subject if it had been given after, it was insufficient because not given after. This does not seem to be correct. The act of notification in such circumstances is only so to inform the mind of the person to be notified, that he may, intelligently and with understanding of the exigencies of the situation, do what he is called upon to do. It is
On this subject it is worth while to see how far the United States Courts have gone. In the case of The Distilled Spirits, 11 Wall, p. 356, Judge Bradley, delivering the opinion of the Supreme Court, said, “that “in England the doctrine seems to be established, that “if the agent, at the time of effecting a purchase, has “knowledge of any prior lien, trust or fraud affecting “the property, no matter whén he acquired such ‘6 knowledge, his principal is affected thereby. If he ac- ■“ quire the knowledge when he effects the purchase, no “ question can arise as to his having it, at that time ; if “ he acquired it previous to the purchase, the presump“tion that he still retains it, and has it present in his “mind, will depend on the lapse of time and other cir- “ cumstances. Knowledge communicated to the principal himself he is bound to recollect, but he is not “bound by knowledge communicated to his agent, “ unless it is present to the agent’s mind at the time of “effecting the purchase. Clear and satisfactory proof “that it was so present, seems to be the only restriction ‘£ required by the English rule as now understood. With “the qualification, that the agent is at liberty to com“municate his knowledge to his principal, it appears to “us to be a sound view of the subject.” I therefore think it would have been error to have charged that the suggestion, if given before the making of the contract, ■could not for that reason have operated as a notification .after the contract was made.
The contractors were not bound to prescribe a plan ■or method of the building. They could not be bound to explicitly require that a plan that they were not bound to make should be carried out. The request to
The plaintiff took exception to a part of the court’s charge in these words : “I do not think it material in “this case whether Dickerson and Sickels, after that “ suggestion of the column work, made any further suggestion as to the bracing of the walls, or whether they “made any complaints about their not being braced or “the bracing not being sufficient, except so far as these “matters tend to affect the credibility of the witnesses “upon that question.” The suggestion here referred to was the sketch which we have already noticed, and which contained buttresses, as a means of strengthening the side walls. There does not seem to be any doubt that this was an assertion by the contractors to the plaintiffs’ engineers, that in ca,se the iron columns were used, then special means should be used, to strengthen the side walls. The court was right in saying that it was not material whether other suggestions of the same kind were made. If made once, they were not bound to repeat, any more than in case of a repetition they would be bound to state them a third time.
There were other exceptions taken to the charge, which cannot be deemed valid, because they were general in their scope, and were applied to parts of the charge, containing several propositions, some of which were, in each instance of these exceptions, correct (Ayrault v. The Pacific Bank, 47 N. Y. R. p. 576). In such case, if we suppose the charge to be in part incorrect, the exception is likewise so, and cannot be sustained. But in the charge, or the parts here referred to, there was no misdirection of the jury in relation to the questions which were submitted to them..
A great deal of testimony was given, under objection and exception by the plaintiffs, as to interviews, and arrangements between the contractors and the plaintiffs’ engineer concerning boilers, before the contract was made. The defendants sought to prove, by this testimony, that the'boilers were made at Detroit, at the request of plaintiffs’ engineer ; the latter assuming, in behalf of the plaintiffs, to guarantee that the boilers, when made, would satisfy the terms of the agreement in respect of them. It can hardly be debated, that it was within the scope (really or apparently) of the engineer’s authority as an agent for the purpose of attending to the execution of the contract in plaintiff’s behalf, to subvert an important part of the contract by such an arrangement. The evidence tending to show that was not admissible for such purpose. That it was admissible for any purpose does not clearly appear (Riley V; The City of Brooklyn, 47 N. Y. R. p. 446). The court, however, afterwards withdrew from the jury the issue made by the answer, in respect of the boilers, in effect determining it in. the plaintiffs’ favor. The admission of the testimony in regard to the boilers, had no bearing upon the issue of fact presented to the jury, as to whether the sole cause of the failure of the engines was the deficiency of the building. It could not have harmed the plaintiffs unless it tended to confuse the minds of the jury in passing on the issue as to the building, or unless it affected the credibility of some
Bor was the credibility of any witness affected by the testimony. It did not contradict any of plaintiffs’ witnesses. In fact, Mr. Houghton, the plaintiffs’ engineer was not examined as to interviews about the boilers before the making of the contract. The letter written by him, especially that of June 24, 1856, put in evidence by the plaintiffs, did not make a question as to the credibility of Mr. Houghton as a witness.
If these matters, so put in evidence, had been an impeachment of Mr. Houghton’s integrity, they might have improperly injured him with the jury. His good faith and honesty were not involved in those transactions. At most, it appeared he exceeded his power as plaintiffs’ agent, but not with an evil mind or a dishonest purpose.
Inasmuch as we can see that the testimony alluded to did not affect the verdict of the jury, its admission does mot call for a reversal (Rundle v. Allison, 34 N. Y. R. p. 183; Erben v. Lorillard, 19 N. Y. R. p. 302; 57 .Barb. p. 99).
The admission of Mr. Houghton’s declaration (at the time he procured the defendants’ consent to the extension of the time for the performance of the contract),
The specifications contained a provision that, during the construction and erection of the engine, the engineer of the plaintiffs’ was to have access at all times to the' work, and to have power to reject inferior work, and to cause good work to be substituted, and to condemn any material going into the machinery which should not be of the best quality. This made admissible all the testimony that was given of the engineer’s interviews, letters and statements in respect of the work,, which took place or were made after the contract.
The evidence given by experts on behalf of defendants as to the capacity of the engines, had a definite bearing upon the inquiry, whether the engines failed, because of the character of the building furnished by the plaintiffs. It was the proper basis of an argument, that the proof showed that everything was right so far as the engines themselves were concerned, and the failure could only be explained by relying on the testimony that the building was not suitable.
On the whole, it does not clearly appear that, there was any error in the rulings and charge excepted to, and judgment should be ordered for defendants on the verdict, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.