Williams v. Boehan
Opinion of the Court
This action was brought to recover damages for the breach of a building contract. Messrs King & Small, architects, at the request of plaintiffs, had prepared plans and specifications, setting forth the character and extent of the mason and stone work required to be done. These plans and specifications were given into the possession of the defendants to enable them to estimate the cost of the work, and make a bid therefor. The defendants had no other information as to the nature of the work or materials necessary for the same. Their estimate was based thereon, and they agreed with plaintiffs to do the work for $5,827, “ in accordance with said plans and specifications.” The work consisted of alterations for
The defendants had a right to refuse to continue under their contract, if the work which the plaintiffs required under the “ working plans ” was substantially different from that which had been submitted to them and upon which they made their estimate. If the defendants could establish this, there was no breach of contract on their part, and hence no cause of action in the plaintiffs; and if this right to abandon their contract was satisfactorily established by a preponderance of evidence, the defendants were entitled to recover under their counter-claim. Was there a substantial variance? This ‘disputed question was submitted to the jury by the learned trial judge, with perfect fairness to the litigants, and with .a -concise, clear and accurate statement of the law applicable thereto. The jury were at liberty to, and under the evidence properly could, render a verdict for either the plaintiffs or defendants. Their verdict under the charge, which we have already said was correct in this respect, depended upon the conclusion that they reached as to the degree of variance. The jury found .in favor of the plaintiffs, and assessed the damages at $800. ....
.... But the learned trial judge, in his charge to the jury on the question of defendants counter-claim, used the following language: " So far as the defendants’ counter-claim is concerned, it seems to me that when they discovered that these plans were different from what they supposed they were, if they did discover that, that they had what is called in law a locus jocenitentice —place for repentance—had time for repentance : they could either go on with the contract, or go off. They
On the disputed question as to the degree of variance, the learned judge said in his charge to the jury : “ If you find that there was a material and substantial difference, one not justified by the usages and customs of the trade, and that the defendants and their sub-contractors were in consequence deceived to their injury—induced to take a job and make a bid they never would have taken or given—the defendants had the right to withdraw from their contract, and are entitled to a verdict, in their favor.”
The defendants were entitled in this connection to have their counter-claim submitted to the jury for determination. The court should have instructed the jury substantially as follows: That in the event of their reaching the conclusion that there was a substantial variance between the “ working plans ” and the “ elevation plans,” and therefore that the defendants were justified in abandoning their contract, that it would then be their duty to determine the defendants’ right to the counter-claim.
It was error, therefore, on the part of the trial judge to refuse to submit to the jury the question arising upon the counter-claim, as herein stated. But in view of the facts established by the verdict, the error is not available to the defendants. The verdict established that there was no substantial variance, and that the defendants were not justified in abandoning their contracts. From this it follows that the jury never reached the question relating to the counter-claim ; and that, even if they had been correctly instructed in respect to it, they would have been bound to disallow the counter-claim.
Freedman, P. J., concurred.