McSorley v. Prague
Opinion of the Court
"In this action the plaintiff seeks to recover the sum of $2,341.81 for a balance due on contracts for plumbing work, and for work done and moneys expended and goods sold and delivered at the defendant’s request between March 1, 1888, and October 1, 1889. The defendant denies the several allegations of the complaint, and then alleges, by way of counter-claim, that between July 1, 1887, and
“ It is admitted that the contracts above referred to amounted to the sum of $61,200.00, and that the plaintiff has been paid by the defendant the sum of $69,167.-81. The hills—108 in number—rendered by the plaintiff for extra work and materials amounted to $8,741.91. The defendant concedes that they are correct to the extent of $7,606.28. Forty-nine of these 108 bills— amounting to $1,689.87—were produced by the plaintiff upon the trial, and he testified that they were accurate and true hills, and that they had not been paid. Twenty-five of them are not disputed by the defendant; to the remaining twenty-four he urges the following objections:
“ He objects that they include bills—amounting to $322.51—for services rendered upon houses belonging to D. Willis James. The defendant denies that these services, with the exception of a single item, were rendered at his request or at the request of any person authorized by him. They were charged to James in
“ The defendant further objects that the said bills include charges—amounting to $221.85—for moneys expended :by the plaintiff without request or authority on the part of the defendant. This item was paid by the plaintiff to the department of public works for ‘ building purposes,’ or ‘ building permits,’ or permits for building purposes ’—by which I understand permits to connect the defendant’s premises on 86th and 87th streets with the croton mains. Mr. Prague testified that he ‘ did not order him (the plaintiff) to pay them; ’ that it must have been done by the mason for water purposes ; ’ that ‘ it was paid for the mason—lie used the water there; ’ that it is outside of me altogether; ’ and that ‘ I don’t know anything about it, except that he paid for the water for the mason, and there is a bill
“ Another objection is that the defendant is charged with the sum of $110 for work, materials and expenditures which the plaintiff was bound to do and furnish by the terms of his contract. Included in this is an item of forty dollars paid by McSorley for sewer permits. He says that he obtained these permits at the request of the defendant, who promised to repay him the money expended. This is not denied by the defendant, and he admits that the permits related to buildings on the Ninth avenue mentioned in the contract of June 25, 1888, and were obtained by the plaintiff prior to the making of that contract. His claim, stated in his own language, is as follows: ‘ He (the plaintiff) was on the ground there and had commenced this work. If he hadn’t got the job, he would have been paid for that work outside of any contract; but as long as he took the job it flowed on and was included in the' contract. We always do that.’ He was asked—‘Will you state how the $40 comes to be included in the contract of June 25, 1888, that appears to have been paid two months prior to that time, and before you had ever entered into a contract with McSorley' for plumbing
“ The last objection to the plaintiff’s claim, under the bills put in evidence by him, is an alleged over-charge of $6.50 in exhibit number 13. The proof does not sustain it.
“ The plaintiff’s alleged cause of action is, therefore, in my opinion, established to the extent of the sum of $1,689.87, the amount of the said forty-nine bills for extra work. Whether the plaintiff is also entitled upon this accounting—for this action is substantially that— to be credited with the whole or any part of the $600 retained by the defendant out of the contracts of August 29, 1887, and February 18, 1888, will be considered in connection with the matters alleged in the way of counter-claim by the defendant.
" The brief submitted by the learned counsel for the defendant, points out with great clearness the grounds of the defendant’s objections to the plaintiff’s alleged cause of action, and also the grounds of the defendant’s counter-claims. It has been of great assistance to me in the examination of this case. Some of the objections raised by it have already been disposed of; others remain to he considered.
" Objection is made that the 108 bills rendered by the
“ Another objection is that the bills contain overcharges for materials furnished, amounting to $258.11. The testimony on this point is unsatisfactory on both sides. I have examined it with care and patience, especially that of Mr. Napier, which was given with great frankness and intelligence. My conclusion is that the objection is not sustained.
“ The defendant does not deny that the work and materials specified in the bills 3-24-30-64-66 and 67 (produced by him) and charged at $60.30, were done and furnished by the plaintiff, but insists that they are included in the written contracts, although he admits that he does not know where part of the work charged for was done. I have not been referred to, nor do I find, any clause or provision in contract or specifications which seems to support the defendant’s claim. The plaintiff testifies that the charges are all for extra work rendered at Mr. Prague’s request.
: “ A further objection is that the defendant should not be charged with the sum of $33.34, the items of which are set forth in defendant’s exhibit 28. The facts, as I understand them, are as follows: The defendant purchased of Elliott Zabrowski a lot on the north side of 86th street, east of the 9th avenue, and erected a house thereon. A small wooden building stood upon the lot, which the defendant (so he testified) moved upon land adjoining, which belonged to Zabrowski. This fact fairly warrants the inference that the building was reserved by Zabrowski in his contract with defendant, and that defendant assumed the duty of removing it to the adjacent premises. It had connections with the Croton main. The disputed services were rendered in severing these connections before, and in restoring them after, the building was removed. • The work was done by the plaintiff’s men, by direction of the defendant’s
" The defendant’s final claim is that the plaintiff did not fully perform his said contracts with the defendant; that some of the work was done in an unworkmanlike and defective manner; that some of the materials furnished were of an inferior quality, and not such as the contracts called for; and the defendant has thereby sustained damages in the sum of $2,219.89. This sum, according to a schedule submitted by the defendant, is composed of four items, the first of which is an item of $665.43 for repairs to the plumbing work in the nineteen houses and three flats mentioned in the contract of January 24, 1889. The defendant’s testimony is that in July, 1889, he had a conversation with the plaintiff about defective work and allowances to be made by the plaintiff therefor; that plaintiff said ‘ to go ahead and make good what I could of it,’ and that he Avould make whatever allowances were right; and that after-wards he (the defendant) " paid a lot of bills.’ McSorley denies that such a conversation took place. I am. unable to find any satisfactory proof that the work done by McSorley upon the building referred to was so defective as to require this outlay to put it in good condition or make it conform to the requirements of his contract. The terms of the contract were explicit and peculiar. The plaintiff Avas required to finish the plumbing work ‘ in a good, workmanlike, and substantial manner, to the satisfaction and under the direction of the said John Gf. Prague, to be testified by a writing or certificate under the hand of the said John Gf. Prague,’ and payment was to be made by the defendant as follows: ‘ As the work progresses 75 per cent., and the balance when the whole work is fully completed, agreeable to plans and specifications—provided that in each of the said cases a certificate shall be obtained and signed by the said John Gf. Prague or his superintendent of works.’
" Another item of the schedule above referred to is the sum of $891.31 for ‘ difference in quality of materials.’ I have carefully examined the testimony upon this point. It does not, in my judgment, warrant the allowance of this claim. Moreover, these materials were furnished and used by the plaintiff from time to time during the progress of his contracts, and were open to the inspection of the defendant, and of his agent, an experienced sanitary engineer, who was employed to look after the plumbing work, and who made examinations of that work several times a week for" more than a year before it was completed, and, as already mentioned, the plaintiff left the work and .received full payment of the contract of January, 1889, without objection on the part of the defendant. The rule declared in the case of Oregon Improvement Co. v. Roach, 117 N. Y., 531, would seem to preclude the allowance of this claim, even if it were sustained by satisfactory proofs.
“ The same objections apply to another item of the
“ The fourth and last item in the said schedule is an item of $84.65 for resetting water closets in eleven of the nineteen houses mentioned in said contract of January, 1889. This is disallowed for reasons already stated.
“ My conclusion, upon all the testimony, is that there was a substantial, if not an exact, performance by Mc-Sorley of his several contracts with the defendant; that he is therefore entitled to recover in this action the balance remaining unpaid on the contracts of August 29, 1887, and February 18, 1888, and that no part of the over-payments and counter-claims alleged by the defendant has been established. Crediting the plaintiff with $69,818.89 (the amount of the contracts and his claims for extra work and materials and moneys expended), and charging him with $69,167.81 (the amount of moneys paid to him by the defendant), the balance appearing to be still due to him is the sum of $651.08. He, however, contends that the $69,818.89 does not represent or include all of the defendant’s indebtedness to him, on account of which the $69,167.81 was paid. His claim is that by' direction of Mr. Prague he put double plumbing ’ in five of these houses on 86th street, east of the Ninth avenue, for which Mr. Prague agreed to and did pay him the sum of $1,500, which sum is not included in the bills rendered by him to Mr. Prague, but is included in the above amount of payments. The testimony shows as follows:
“ There is no dispute over the meaning of ‘ double
“The plaintiff also claimed upon the trial that he should be credited in his account against the defendant with the sum of $300 paid to one Brahm for marble, by defendant’s direction. The proof shows that such payment was made by him, and that the money was refunded to him by the defendant. It is credited to the defendant in the plaintiff’s books, but does not enter into the $69,167.81 which the defendant claims to have paid and the plaintiff admits having received.
“ The other marble bill, over which there was some dispute, amounting to $1,417.98, is bill number 108
“ The plaintiff is entitled to judgment for the sum of $2,151.08, with interest.”
We find no errors in the rulings of sufficient weight to warrant a reversal. The testimony satisfactorily sustains the findings of the referee and justifies the judgment rendered.
For the reasons set forth in the opinion of the referee the judgment is affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.