Hurd v. Newbrook
Concurring Opinion
I concur in the result reached by TITUS, C. J., upon the ground that the guaranty in this case is to be construed as referring to the building contract to determine the time when payments fell due, and for no other purpose; and, as it appears that the contract was finished to the extent of entitling Walty to two payments, it then became the right of plaintiffs, under the guaranty, to demand pay thereon, and that, upon the proof here, without reference to the subsequent acts of Walty, for, if all the damage occasioned by Walty’s breach of contract be deducted, there still remained, and was paid to him, a sum sufficient, and more than sufficient, to discharge plaintiffs’, debt. Under this construction, it is clear that a time came when Walty was entitled to demand a sum of money, due upon the contract, exceeding the amount of plaintiffs’ bill. When that moment arrived, defendant’s guaranty attached, and his contract then was to see plaintiffs paid. There is no hardship in this, for defendant then had it in his power to protect both himself and plaintiffs. He chose to permit payment to be made,, to
Opinion of the Court
This action was brought in the municipal court to recover against the defendant for a bill of lumber furnished to one Abraham Walty on a guaranty of payment. It appears that on the 23d day of July, 1891, William G. Newbrook, son of defendant, George New-brook, contracted with Abraham Walty to build him a house according to certain plans and specifications contained in a contract, the work and material to be furnished by Walty. It was agreed that Walty should receive $1,450 for the job,—$500 when one third of the work was done, and $500 more when two thirds of the work was done, and $450 to be paid to said Walty when the house was completed, and ready for occupancy. Some days after the date of this contract the plaintiffs made out a bill of lumber necessary to build the house, and presented the same to George Newbrook for his approval and guaranty. The defendant wrote upon the bill the following:
“I approve of the above bill, amounting to $460, and agree to see it paid, according to the terms of payment agreed to in the building contract. [Signed] George Newbrook. July 29, 1891. ”
Thereupon the plaintiffs furnished to Walty the necessary materials for building the house. On the 19th of October, and before Walty had completed his job according to his contract, he absconded, leaving the
The validity of the liens and the amount unpaid to Walty, in the view which I have taken of this case, cannot be of. much importance. The liens can only be enforced to the extent of any unpaid balance due the contractor, and it is apparent that at the time of filing the liens the contractor had been overpaid. It thus appears that William G. Newbrook lias paid the whole contract price for building his house, leaving the $119.02 of the plaintiffs’ claim unpaid. But I do not think the question is to be determined either from the fact that the contract price has been paid, or of the failure of Walty to complete the work according to the terms of his contract. It is claimed that the guaranty was without consideration, and cannot be enforced against the defendant. I think the delivery of the lumber was a sufficient consideration for the guaranty. Before the plaintiffs would deliver the lumber, they had a bill of it made out, and submitted to the defendant for approval. On his approving and agreeing to see that it would be paid, the lumber was delivered to the contractor, on the faith of the guaranty. Under the authorities, it was a sufficient consideration to uphold the undertaking of the defendant. Beakes v. Da Cunha, 126 N. Y. 293, 27 N. E. Rep. 251.
According to the contract of guaranty, the defendant agreed to see the amount of the bill paid according to the terms of the contract, and it is necessary to examine the contract to determine how the payments were to be made. It appears that $500 was to be paid when the work was one third completed, and $500 more when two thirds of the work was done, and $450 was to be retained by Newbrook until the work was finally completed, so that, when the house was completed the whole
WHITE, J., concurs in result.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.