McNeal v. Clement
Opinion of the Court
The foundation of the plaintiff’s action is a written contract to make certain alterations and repairs upon a building belonging to the defendant, with a further and additional parol contract providing for certain changes in the original plan. The referee in his findings, after stating the making of the contracts and that the plaintiff entered upon the performance thereof, finds that “ during the time that plaintiff was engaged in said work the defendant lived in said house, and in some things directed the manner of its execution; and also directed that certain other work not mentioned, in either agreement.with said plaintiff, be done,” and that said extra work was done, etc. The finding then proceeds as follows: “And I further find that some of the materials, as furnished by plaintiff to defendant, were not of as good quality as those called for by the agreements of the parties, and that some of the work performed as aforesaid was not performed in a good and workmanlike manner, by reason of which defendant suffered damages in the sum of $431.20.” The referee then finds that the materials furnished and work performed by plaintiff for the defendant was worth the sum of. $1,459.80, of which sum there was paid by the defendant to the plaintiff, from time to time during the continuance of the work, the sum of $752.32, and as a conclusion of law he finds that the defendant owes the plaintiff $707.48, with interest from the 24th day of May, 1872; for which sum he directs a judgment: On the settlement of the case, the referee inserted therein, on the request of the defendant’s counsel, the following additional finding: “That, by the contract made between the plaintiff and defendant, plaintiff
On looking into the evidence, it appears that these findings by the referee were unavoidable, and that the violations of the contracts on the part of the plaintiff were important and willful. It seems to be quite clear that the referee, in holding that the plaintiff is entitled to recover in such a case, has wholly mistaken the rules of law applicable to actions on contract. Where there is a special contract for work, labor and materials upon one side, and payment upon the other, the due performance of the contract is a condition of the right to recover, and builders have no immunity from this rule of law. The idea that a party who makes a contract with a builder is wholly at his mercy, and is not protected by his contract against the neglects, refusals and reckless and willful violation of its terms by the other party, has frequently been considered and uniformly condemned by the courts of this State.
The report of the referee in this case is quite similar to that in the case of Smith v. Brady, 17 N. Y. 173. And the opinion delivered by Judge Comstock in that case, and concurred in by all the court, is quite applicable to the case at bar. A part of the opinion is as follows: “ The particulars in which the referee found the contracts not performed are not stated in his report, but they could not have been so unimportant that the law will refuse to notice' them, because, in the same report, the value of those particulars is ascertained to be over @200. Nor is it found that the plaintiff intended to perform his contract. Eor aught that appears, the omissions and defects were intentional and willful; and in the absence of all explanation, the presumption is that they were so. * * * To conclude, there is, in a just view of the question, no hardship in requiring builders, like all other men, to perform their contracts in order to entitle themselves to payment. * * * If he fails to
In Smith v. Brady, the whole amount of the contract was $4,900, and the referee found the damages sustained by the defendant, for deficiencies in work and materials, to be $212.57. In the case at bar, the whole amount of the contract, both written and by parol, was $1,550, and the damages sustained by the defendant, for deficiencies in workmanship and materials (to say nothing of the items wholly omitted to be done in any manner), is $431.20
In the leading case of Jennings v. Camp, 13 Johns. 94, the court held that the rule that, if there be a special agreement and work done under it, the plaintiff may recover on a quantum meruit, has no application to such a state of facts as exist in this case. That the rule referred to supposes a performance of the contract with variations from the agreement, probably with the assent of both parties, and was never intended to embrace the case of a willful dereliction from the contract when partly executed by one of the parties without the assent and against the will of the other. The fact is, as intimated in Smiths. Brady, supra, it is not the office of courts to make or alter contracts, or to undertake to say that a party, who has bargained for one thing, shall accept and pay for another in lieu thereof. If the party entitled to a performance sees fit to waive a full and strict compliance with the terms of the contract, such is his right, and, as a question of fact, courts and juries put a very liberal construction upon such acts of the parties as have a tendency to show an intent to waive strict performance. But a clear and willful violation of the contract, where performance is not waived, is as complete a bar to a recovery on a contract for building as on any other. The case of Smith v. Brady was followed in Bonesteel v. Mayor of New York, 22 N. Y. 162; and in Cunningham v. Jones, 20 id. 486; which latter case, like the one at bar, was an action to enforce a mechanic’s lien. The same principles were fully recognized and adopted in Pike v. Butler, 4 N. Y. 360; in Pullman v. Corning, 9 id. 93; and in Tompkins v. Dudley, 25 id. 272.
The referee does not find that the defendant, in this ease, waived the performance of the contract, in regard to the particulars in respect to which the plaintiff violated it. It is true he finds certain
It being necessary to reverse the judgment upon the merits, there is no necessity of examining the numerous exceptions taken by the defendant in the course of the trial.
Judgment is reversed and new trial ordered, costs to abide the event, and a new referee to be appointed.
Judgment accordingly.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.