McMillan v. Seneca Lake Grape & Wine Co.
Opinion of the Court
The case contains several exceptions besides those insisted on by the appellant’s counsel. Upon examination, we think those omitted were properly waived on the argument, and we shall not discuss them.
The objection that the notice of lien did not accurately specify the amount of the claim, we think was properly overruled. An amount was stated, and the addition of the words, “ with interest,” . did not vitiate the notice, because, if need be, they may be rejected
When the plaintiff; rested, enough had been shown to establish, prima facie, that the defendant was indebted in some amount to Coe, the contractor. The operation of the lien law is to transfer to the lienor the contractor’s claim against the owner pro tanto. It is a form of equitable subrogation. The plaintiff having proved the contract by which the defendant agreed to pay eighty per cent of the value of the work as it progressed, and that the contractor had performed it in part, the indebtedness of the defendant to him appeared, and it was incumbent on the defendant to prove that it had been discharged. (Phil. Mech. Lien, § 63.) The work was in progress under the contract when the suit was commenced, and twenty per cent of the value of it would become due thereafter. The plaintiff was clearly entitled to intercept the payment of a part of that. There was no error, therefore, in denying the motion for a nonsuit.
In the course of the trial, the defendant offered to prove that, on the very day the lien was filed, the contractor became unable to complete the building, or to advance the necessary funds to purchase materials therefor, and to pay laborers thereon, and that the defendant, in order to complete the building, was forced to and did purchase materials therefor and pay laborers thereon, to an amount exceeding the price agreed to be paid in the contract. This evidence was properly rejected, for the reason that the offer did not embrace the proposition that the contract had been abandoned. Won constat the acts of the defendant were done under an agreement with the contractor, that the sums so expended should be treated as payments under the contract. Indeed, such appears to have been the fact. If, when a notice of lien is filed in a case like this, the contractor has been folly paid for all work done prior to that time, and, for any cause, the contract is mutually abandoned, the lien will be defeated, for nothing can thereafter become due to the contractor. The statute expressly limits the
These payments not being available to defeat the lien, it remained; and if the contractor could have recovered them in case they had not been made, the plaintiff may do so notwithstanding they were made. The fact that they were made under the contract, is satisfactory evidence, in the absence of proof of fraud or mistake, that they were due. The referee has so found in substance, and it is immaterial to inquire whether other propositions embraced in his findings are erroneous or not.
The judgment must be affirmed.
Judgment affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.