Bowery National Bank v. Mayor of New York
Opinion of the Court
This is the third trial of this action. On the first trial the plaintiff had judgment which was reversed by the General Term.
That the work was duly performed, and its completion certified by the inspector, December 13, 1870. That the water purveyor caused the work to be entered on his books as completed, December 10, 1870. It also appeared that on January 19,1871, a preliminary injunction was obtained by property owners, returnable January 25, 1871, restraining the defendants “from laving or confirming any assessment for paving said street, and from doing any act or thing toward making or confirming said assessment, or making the same a lien.”
That a demand was subsequently made upon the water purveyor for the certificate, who refused, stating “ that he was prevented from giving it by this injunction obtained by the property owners.”
That the assessment for this work was advertised and forwarded to the boards of revision and correction, September 11, 1871, and the matter was referred by them to the Comptroller to assess the
In addition to these facts the plaintiff proved on this trial as follows: That the papers in the injunction suit were served January 24, 1871, and were returnable January twenty-fifth. That the preliminary motion was argued March 20, 1871, but there was no record in the corporation counsel’s office of its having been decided.
That nothing further was done by defendants until October 24, 1872, when the contract having become valid by the action of the contract commissioners, an order was obtained to show cause, on October 28,1872, why a supplemental answer should not be served in that case, setting up the certificate aforesaid given under the act of 1872 (swpra), and the injunction be modified so as to allow the laying of the assessment. That this motion was not regularly argued, but permission was granted “ to do what was moved, for,” and such a supplemental answer was served November 23, 1872. That prior to this the injunction suit had been placed in the hands of special counsel, but nothing further was ever done to vacate the injunction or dispose of the issues, it never having been noticed for trial or placed upon the calendar, up to March 15, 1876.
That the case belonged upon the equity calendar of the Common Pleas, which was made up monthly and disposed of every term. That the corporation counsel, his two assistants and managing clerk knew nothing further about the injunction suit. That on September 24, 1875, the corporation counsel was notified that as the injunction was used as a defense to the plaintiff’s claim herein, they insisted it should be disposed of at once, and that he still took no action in regard to it.
.It also appeared that Mr. Strahan, the special counsel of the defendants in this case, refused to give his reasons why the case was not tried, because the defendant objected, and his refusal was sustained by the court.
Plaintiff also proved that it was customary among lawyers to notice a ease, and place it upon the calendar as soon as the answer was served. And that if not noticed, or put upon the calendar by the plaintiff, it could be dismissed for want of prosecution. The defendants offered no evidence except to prove that the pavement did not last, which was excluded.
The defendants had November, December, January, February and until the 17th of March, 1873, to remove the injunction, if it had not already been modified or dissolved, or to initiate some proceeding thereto. The view thus stated as to diligence, is independent of the effect of the motion of October twenty-fourth (sujpra), to obtain such modification of the injunction as to allow the assessment to be laid, and which seems to have been granted.
The delay.of the defendants, thus shown, not only prevented the assessment but it prevented the plaintiffs from obtaining the certifi
When the appeal in this case in the Court of Appeals was decided, it was substantially held, in reference to the certificate of the water purveyor, that the plaintiffs had done all they were required to do, and that the refusal to give it under the circumstances was unreasonable. The question involved on this appeal is, whether the laches of the defendants, in regard to the Tooker suit, does not deprive them of the defense, that the assessment had not been laid which was contemplated by the agreement between the plaintiffs’ assignor and them.
The learned justice presiding on the trial presented it as a question of fact to the jury on this trial, stating to them, that if, in fact, the injunction remained in full force at the time of the commencement of this action, notwithstanding the exercise of proper diligence and effort on their part to obtain its removal, they were not liable. The learned justice also suggested that the question arose as to why the assessment had not been confirmed, whether it was because of any collusion, fraud, negligence or other improper act on the part of the corporation.
The testimony on this subject, however, was all one way. There was no conflict, no doubt, and the finding of the jury that reasonable diligence characterized the defendants’ management of the Tooker suit was unwarranted by the evidence. But it must be said further, that the question of reasonable diligence is one for the court and not for the jury where the facts are undisputed, and especially where its subject-matter, namely, a law-suit, is one of which the court can take judicial cognizance. (Alexander v. Parsons, 3 Lans., 333, 337; Wakeman v. Gowdy, 10 Bos., 208, 213;
There are no questions presented on behalf of the defendants which affect this view, and it must he adopted.
Ordered accordingly, with costs to abide event.
Judgment reversed, costs to abide event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.