Hagar v. Clark
Opinion of the Court
The judgment appealed from was for the amount held to be due upon a charter-party, made on the twenty-seventh day of July, 1865, for a voyage of the steamer Ha,gar from New York to New Orleans and back. The defendants resisted the recovery because of the failure of the boiler of the steamer soon after she entered upon the voyage, by reason of which she was delayed in reaching New Orleans for so long a period of time as to render them unable to obtain for her a remunerative return cargo. The foundation of the claim was that the charter was merely a contract for affreightment, and that the responsibility for the delay -was legally upon the plaintiffs as the owners of the steamer. But the referee held otherwise and that the steamer was hired to and navigated by the defendants, and for that reason the loss occasioned by the delay must be borne by themselves. This delay and consequent loss arose out of what the learned referee in his report held to be an accident; but in the further findings added upon the settlement of the case, it -was stated: “ That the cause of the giving way of the boiler of the Hagar, was the negligence of the engineer on watch at the time in allowing the water in the boiler to get too low.” It has been urged that this was inconsistent with the statement made in the report attributing the injury to an accident. But it is not very material to inquire whether this criticism is well founded or not, for if the fact was that the boiler gave way because of the negligence of the engineer on watch at the time, the responsibility for the delay created by that circumstance would still bo upon the defendants if he was their servant in their employ, as he was, if they possessed and navigated the steamer. This conclusion, as it was last stated, was supported by the evidence, and for that reason it is not necessary to consider the effect of the presumption arising as to the
But it has been strenuously maintained that no such disposition was made of this steamer, because of the existence of a clause in the charter excepting from the right to use the whole of her for freighting purposes, “ the necessary room for the crew and storage of provisions, sails and cables.” That exception, however, was not made in a form reserving that room to or for the plaintiffs. But it was simply for such uses as were required in the ordinary and proper navigation of the steamer, and for the benefit solely of the persons exercising that control over her during the prosecution of the contemplated voyage. There was no serious inconsistency in its 'existence with the fact that the management and possession of the steamer was at the same time designed to be given to the defendants. And it has been so held in other cases that are regarded as sound authority upon this subject. (Trinity House v. Clark, 4 Man. & S., 288; Sherman v. Fream, 30 Barb., 478; Christie v. Lewis, 2 Brod. & B., 410.)
This is a circumstance from which, with others when they exist, it may be inferred that the navigation and control of the vessel have been retained by her general owners, but it has in no instance been alone considered as conclusive. In the case of Clarkson v. Edes (4 Cow., 470), which has been regarded as an important authority in
In the present instance no such duty was, in any form, imposed upon tlie plaintiffs as the general owners of the steamer. They merely agreed that she should be tight, staunch, and strong, and in every way fitted for such a voyage. And that part of their agreement they performed by delivering her in that condition to the defendant. They did not bind themselves to keep her in that condition, but merely that she should be so at tlie time when they surrendered her for the performance of the terms of the charter. What they agreed in terms to do, was to charter the whole of the vessel, or sufficient room, subject only to the exception already stated, for tlie cargo afterwards mentioned. And that was such a cargo of lawful merchandise as the charterers might deem it proper to laden her with. In that respect tlie charter differed from tlie one which was before the court in the case of Hooe v. Groverman (1 Cranch, 124), where the charterers simply had the use of the whole tonnage of tlie vessel; while here they had the whole of the steamer for whatever lawful cargo they chose to lade her with, except that required for the convenience of the crew and the stowage of provisions, sails and cables, and even that was also necessarily enjoyed by them for those purposes. Besides, they were to, and in fact did pay all the expenses beyond the sum of $7,000, which was the stipulated
The case cannot be affirmed to be a clear one against the defendants, but enough appears to render it reasonably certain that it was the intention of the paifies in making the charter that they should have the possession, control and direction of the steamer for the time mentioned in it. The governing point in the determination of this class of cases has been considered to be whether there has been an entire letting, or parting with the possession of the ship, so that during the voyage, the absolute owner has surrendered his control over her. If such possession has been agreed upon (and that seeing to have been done in this instance), then the charterer receiving her under the agreement must be considered her owner for the stipulated employment. (Christie v. Lewis and Leary v. United States supra ; Gracie v. Palmer, 8 Wheaton. 605.)
The evidence very directly tended to show, and the referee found from it, that in point of fact, the possession of the steamer with her officer son board was turned over to, and accepted by, the defendants. The agent acting for them in the procurement and execution of the charter, distinctly testified to the existence of those facts. And the residue of the crew were either employed by the defendants or the officers on board the steamer, acting for them after that time. She sailed under their direction, and received such merchandise for transportation as they could obtain for her. And they were in no respect interfered with by the plaintiffs. Their acts under the charter were consistent with the existence of no other intention than that they were to, as they did, have possession of the steamer during its continuance. And that, in a case of doubtful construction, is a circumstance of importance in ascertaining and determining the design governing the parties in the making of their agreement. (Reed v. Proprietors of Locks, etc., 8 How. [U. S.], 274.)
The clause in the charter that the cargoes to be received and delivered should be placed within reach of the steamer’s tackles, at the ports of loading and discharging, must be conceded to be in conflict with the construction now given to that instrument. For there would seem to be no reason for the general owner’s solicitude on that subject, if the steamer was to be delivered over to the exclusive control and possession of the defendants. But the other stipulations at variance with this provision, and the unequivocal acts of the parties themselves, indicating their understanding of the agreement they had made to be that of a letting of the vessel, are too decisive in their effect to permit this to control the disposition which should be made of the case. There was but one contingency upon which responsibility or expense was placed on the plaintiffs, and that was only for accidents to the steamer’s machinery. In all other respects the burthens, as well as the
It-has also been urged that the recovery of $1,250 allowed for detention beyond the time mentioned in the charter was unwarranted. But there was evidence in the case from which it could be very well found, that such detention was caused solely by the default of the defendants’ agent at New Orleans. The referee relied upon that evidence and found the fact accordingly, and there is nothing in the case on which it can be held that he acted erroneously. Neither did he improperly decline to find other facts supported by the evidence and material to the disposition of the case. The judgment seems to have been rightfully directed, and it should, therefore, be affirmed.
Judgment affirmed.