Moore v. Taylor
Opinion of the Court
There was some controversy on the trial in respect to the quantity of work performed under the contract. The accuracy of the estimates presented by the evidence of the respective parties was the subject of fair criticism. Those furnished on the part of the plaintiff were made without measurements, and those on the part of the defendants were estimates aided by partial measurements only. Thus was presented an apparent conflict in the evidence. No actual measurements or estimates were made by the defendants or their engineers, or those of the railway company prior to August first, of the work done up to July twenty-fifth, and there is some evidence tending to prove that then and thereafter there were difficulties in the way of making accurate measurements or estimates of the work done, occasioned by various causes, for which the plaintiff was not responsible, and that the measurements made on the part of the defendants and estimates founded upon them were not necessarily accura'e ; that the plaintiff himself and another engaged in the work were civil engineers, and that they made estimates with knowledge and observation of the work as it progressed. The estimates, so made by them were sufficient in extent to cover the amount of work found by the referee. The evidence, as a whole, in this respect presented a question of fact, and we cannot say, in the light in which he was permitted to view the evidence as it was adduced, that his finding is so against the weight of evidence as to justify the disturbance of his finding. We think his conclusion, as to the quantity of work done, was permitted by the evidence.
There is not a very clearly defined division of the work into that, done before and that done after the 25th July, 1882, but there is some evidence on the subject, which enabled the referee to make the severance and to support his conclusion in that respect.
The defendants allege the abandonment by the plaintiff of the work which he undertook to perform under the contract, and that a large number of persons gave notice to the railway company of their claims for labor done, and filed liens against the company for materials furnished and used in the work of construction under the contract in question ; that the defendants paid such claims, amounting to $6,910.10, and took assignments. They sought to charge
There was no specific contract between the railroad company and the defendants produced or proved upon the trial, but it appeared incidentally, in various ways, that they were contractors with the company for the construction of the road, and it was evidently assumed upon the trial that they had such relation to it. Their privity by contract was with the plaintiff only; and assuming that
The proceeding attending the act of payment, of having notices served upon the engineer of the company under the statute, and taking assignments, was evidently taken as a matter of precaution, so that the payments might be deemed as made to discharge the company and its property from a liability to pay, and thus protect themselves from liability to it. And while the apparent effect of the assignments was to vest in the defendants the title to the claims as against the parties primarily and personally liable to pay them, the purpose evidently was to take such title only as a means of making more effectual their purpose to apply the moneys, so advanced, upon the amount of compensation which they, by their contract, had agreed to pay the plaintiff for the work of construction of the railroad, and not with any view to create a liability of any other party to them for the amount so paid. They in this may have done, and probably did do, more than was necessary to put themselves in a position to charge the plaintiff with the payment so made, although the question of voluntary payment otherwise might have been raised. (Senear v. Woods, 74 N. Y., 615.) The question presented here is not without some difficulty, but we think these payments should, and may, be allowed to the defendants in this action number one. Proceedings were taken to charge the company, and it is not important what the inducement was to cause it, if it was legally done. This afforded to the defendants the right to step in and protect themselves by relieving the company. If they had not done this the right of the company would arise to pay and seek relief from the defendants and they, in turn, to charge the plaintiff, and if Moore & Sullivan, as his subcontractors, were first liable to pay, he could require allowance by, or reimbursement from, them to him. This circuity of action could result
This action is brought upon the contract between the plaintiff and defendants to recover for this work, and as between them it was deemed done by the plaintiff in performance of such contract. It was on account of this work that such payments were made, and they were made with the consent of Moore & Sullivan, who were in some manner acting through or under the plaintiff in the per-3’ormance of the contract between the latter and the defendants. We think the amount of these payments so made by the defendants properly should and can be allowed to the defendants by way of abatement of the plaintiff’s recovery.
The evidence about fares, etc., of the men, said to have been paid, by Moore & Sullivan, is somewhat indefinite. Nothing appeared on the' pay-rolls in that respect. They say they informed’the defendants’ agent that deduction should be made on that account from the moneys earned by the laborers, which he denies. Moore & Sullivan, knowing that the defendants were pi’oceeding to pay the men, and consenting to it, gave no information to enable them to
It is contended on the part of the defendants that the plain,tiff, without cause, abandoned the work before full performance of his contract, and that such fact should go in defense of action number one, as the provision of the contract for intermediate payments must be deemed conditional and dependent upon its complete performance. It is true that the agreement to pay in installments from time to time as the work progressed, rates of prices for it founded upon estimates was so far conditional that the payments should not exceed in amount the bulk price to be paid for the entire work, yet, inside of that, the plaintiff had the right to recover the installments provided for on performance, to the time and extent required by the contract, to enable him to demand payment of them, subject only to the right of the defendants to allege and establish, by way of abatement, such damages as they may have sustained by any subsequent breach of the contract on his part, which is the extent of the defense that could be made, founded upon such alleged abandonment. (Sickels v. Pattison, 14 Wend., 257; Snook v. Fries, 19 Barb., 313; Tipton v. Feitner, 20 N. Y., 423.) No facts are found, and none necessarily established by the evidence, which require the consideration in action number one, of the question of the alleged abandonment by the plaintiff or any further question in that • action.
But in action number two such abandonment, its cause and effect, have some importance. The referee finds, and it is assumed here, that the defendants refused to pay to the plaintiff, on the 1st day of
The important question arising upon this state of facts is whether the plaintiff, in consequence of this breach of the contract, was entitled to recover, by way of damages, prospective profits or such profits as would result to him from a complete performance of the contract. The referee found that by this refusal to pay the plaintiff he was deprived of “ the means to pay off his laborers, and procure their continuance at work.” And, as conclusion of law, adds that such refusal was a violation and breach of the contract on the part of the defendants, which absolved the plaintiff from further performance; that he had the right to abandon the work and recover whatever damages he had sustained by reason of such breach, and then-proceeds to award him as such damages the difference between the contract-price and the estimated cost of the unperformed work of the contract. This was the corrrect rule for the measurement of damages if the plaintiff was, by the defendants, prevented from proceeding to complete performance, unless there was something in the contract to defeat the application of that rule. (Masterton v. The Mayor, 7 Hill., 61.) It is contended by the defendants’ counsel that the right reserved to the defendants by the provision of the contract, to the effect that in the event they should, for any reason, fail to continue the work, and should notify the plaintiff to suspend or cease operations, a measurement should be made of, and payment made for, the work done at specified rates, operated to defeat the right of the plaintiff to recover damages, or to claim anything otherwise than is provided for as compensation by the contract. That provision evidently, had reference to a suspension or discontinuance of the work by the defendants for some cause which might arise. They had no purpose to discontinue the work of construction. They urged the plaintiff to proceed, and, on his refusal to do so, they caused the work by other means to go on to completion.
The situation did not come within the provision last referred to of the contract. (Danolds v. The State, 89 N. Y., 36, 43.)
The more serious inquiry remains and is, whether, in any view which may be taken of the evidence, the plaintiff was permitted to recover, as damages, the prospective profits which the completion of performance by him of his contract would have given him ? The right to such relief does not arise out of every breach of a contract for the performance of services, but is dependent upon that which operates as a denial of the right to proceed to completion of the work contracted for. Mere default in payment of an installment, when it becomes due, is not a denial of the right of the contractor to continue in the performance of the service, and although it may be a breach which would permit him to abandon the work, and recover for that already done, it would not enable him to recover the damages which the law would give for refusal to let him proceed in performance of the contract.
There was no obstruction put in the way of such performance, other than the effect of the refusal to pay the installment due the first of August. The referee has found that the provision for payment, as the work progressed, “was a very essential condition,, bearing directly upon the performance of the contract by the plaintiff,” and that Moore & Sullivan were “ unable to go on with the same, in consequence solely of defendants’ refusal to pay the moneys
An agreement to make payment is generally an essential one, and the consequences of default in payment may, in fact, be more or less prejudicial, according to circumstances, but in. legal contemplation they are the same. The pecuniary condition and responsibility, of the parties have no bearing upon.this question. The rights at law flowing from or produced by a breach of contract arise at once from it and will support an action. If default in payment alone would afford a remedy as for exclusion from further performance, the right of action and of recovery of the entire value of the contract would immediately follow failure to pay, although it arose from mere temporary want of readiness to make payment. In this case the legal right of the plaintiff to proceed in the performance of the contract was not affected by the default of the defendants. But it is said that the defendants sought to and did embarrass the plaintiff by inciting the laborers to insist upon payment fortnightly, when otherwise they would have been content to take their pay monthly. There is no finding on that subject in this action number two to that effect, and in view of the evidence there is no occasion here for considering that question as bearing upon the proposition now under consideration. The men became insubordinate and
It amounted to.................................. $22)761 43
The recovery in action number one, $12,854, and payment, $5,000........................:........ 17,854 00
The balance unpaid is........................ $4 > 907 43
This result is reached by giving to the plaintiff the benefit of the payments provided by the contract to be made on the final estimate of the work when completed, in stock, for which the breach of the contract, as found by the referee, permits the allowance to the extent of the work performed. (Pinney v. Gleason, 5 Wend., 393.) This computation makes the amount awarded by the referee, as damages, $11,080.94.
If these views are correct the j'udgment in action number one should be reversed and new trial granted, costs to abide the event, unless the plaintiff stipulate to deduct from the amount of the recovery $6,940.10, and interest thereon from August 5,1882; and in that event the judgment be so modified, and as modified affirmed, without costs of this appeal to either party. And in action number
So ordered.