Pierson v. Crooks
Opinion of the Court
The ac'tion was brought by the plaintiffs to recover back moneys paid by them for freight, duties and other charges, on iron which the defendants contracted to sell and deliver to them. The contract was made through the agency of brokers representing the defendants, who were merchants in the city of Liverpool. The contract is as follows:
“New York, February 11, 1880.
“ Sold to Messrs. Pierson & Co., New York, for account of Messrs. Robert Crooks & Co , Liverpool:
*573 “ One hundred (100) tons W. I. W., or equal hoop iron, at £10 per ton.
“ One hundred (100) tons W. I. W., or equal sheet iron, at £11,15,0.
“Fifty (50) tons R. G., or equal sheet iron, at £16,5,0, all free on board Liverpool, payment by 60d st. 131. exchange against shipping documents here, less two and one-half per cent. Immediate specification.
“ WHITE & DRUMMOND, uBro7cers.
“ Accepted.
“ Pierson & Go.”
And the 100 tons of hoop iron mentioned in it were after-wards increased to 150 tons. Specifications were supplied by the plaintiffs for the shipments and delivery of the iron in three or four different parcels. The defendants were not manufacturers of the iron, but it was designed that they should, as they afterwards did, obtain that from the manufacturers which they afterwards shipped to the plaintiffs, The 100 tons of sheet iron proved to be satisfactory and acceptable and was received and paid for by the plaintiffs. And so was a certain portion of what is called the R. G. sheet-iron, subject to certain allowances and deductions which were made. The controversy in the action has, in this manner, been limited to the hoop iron and the final shipment of the R. G. sheet iron amounting to nearly forty-one tons. As to all the hoop iron, and this residue of the R. G. sheet iron, the plaintiffs objected to receiving it upon its arrival in New York where the hoop iron was-unladen, and in Brooklyn where the R. G. sheet iron was unladen. The objection taken to the acceptance of the hoop iron was that it was very much inferior in quality to that which the plaintiffs were, by the terms of the agreement, entitled to receive. Two of the shipments which were made of the hoop iron were also accompanied with shipments of sheet iron. These were made upon the steamers Germanic and Arizona. Other shipments of hoop iron were made by the steamers City of Chester and Abyssinia. Upon these two steamers were laden no portion of either quality of sheet iron, and upon the arrival of the City of Chester and the unlading of the iron, the
’ There appears to be nothing unreasonable in the delay which took place at the city of New York in the examination of the iron after its arrival. It was not done as speedily as that might be done, but, as the circumstances were made to appear, there was no unreasonable delay on the part of the plaintiffs in subjecting* the iron to these examinations. And as the law has required no more than reasonable diligence in the examination of property shipped, or offered, to the purchaser after its arrival, its requirement was observed by the plaintiffs in this instance. They were not required to dispense with the other demands of their business and devote immediate attention to this iron, but it was their duty to proceed reasonably as they would be expected to do with other urgent matters of business. And that duty does not seem to have been neglected as the facts of this case have been disclosed.
It is insisted, however, on behalf of the defendants, that this right to examine the iron and reject, or accept it, as it was found not to conform with the contract, could not be made after it was received and shipped at the city of Liverpool; that the agreement designated
This right of inspection and examination preceding the obligation to accept the property is maintained by all the authorities where the sale is executory, and the property itself is unascertained or separated, as were the facts in this case. This was the conclusion of the court in Sprague v. Blake (20 Wend., 61), where it was said that “ when the party comes under such a contract, to deliver an inferior unmerchantable commodity, which lies open to inspection, then is the time for the vendee to take his ground. He must then refuse acceptance, or at least so soon as he discovers what the quality of the article is, and offer to return it.” (Id., 64.) And as much as this was held in Reed v. Randall (29 N. Y., 358), for there it was stated in the prevailing opinion that the vendee “is not bound to receive and pay for a thing that he has not agreed to purchase; but if the thing purchased is found, on examination, to be unsound, or not to answer the order given for it, he must immediately return it to the vendor, or give him notice to take it back and thereby rescind the contract, or he will be presumed to have acquiesced in its quality. He cannot accept the delivery of the property under the contract, retain it after an ojiportunity of ascertaining its quality, and recover damages if it be not of the quality or description called for by such contract.” (Id., 363.) And Gurney v. Atlantic, etc., Railway Company (58 N. Y., 358) proceeds upon the same principle. There
In the'ease of Pope v. Allis the examination and inspection of the property was deferred to a much longer and more remote point of time, and still it was sustained by the court and the vendee was relieved from the obligation to receive and' accept the 'property under the agreement. As to these two shipments, by the City of Chester and Abyssinia, therefore, the plaintiffs clearly maintained their right to recover the amounts awarded to them by the referee in his report, for, while the iron on the Abyssinia was not actually inspected or examined by the defendants, the evidence in the case justifies the conclusion that it was of the same quality as that delivered from the City of Chester. It was not contended to be otherwise by the defendants, and the plaintiffs, assuming from the three preceding shipments that the hoop iron was all of the same quality, notified the defendants of their refusal to receive any more of that quality of iron; and this was communicated to the defendants before the iron by the Abyssinia was entirely laden or the ship had left the city of Liverpool. In this refusal they certainly seem to have been justified by the principle proceeded upon in Pope v. Porter (102 N. Y., 366), for, as the defendants had shipped to them only this inferior quality of iron, the facts supported them in the conclusion that no better quality could be expected to be received under the agreement.
As to the hoops shipped by the steamers Germanic and Arizona,
This principle, applied in this manner, is entirely in accordance with the general legal rule that where an agreement is to be rescinded it must be rescinded wholly, or not at all, for the plaintiffs did not undertake to rescind the agreement relating to the shipments of hoop iron, except in the single instance of that which finally came by the Abyssinia. What they did was to refuse to receive the infei’ior quality of hoop iron shipped to them by the defendants for the purpose of performing their agreement. That did not rescind the contract or any part of it. It was still left, as a subsisting agreement between these parties, which the defendants might have fulfilled-by supplying the- plaintiffs with the proper qnality of
The payments which were made by the plaintiffs towards the purchase-price of the iron did not have the effect of waiving their right to insist upoft it that the quality should be the same as that mentioned in the agreement, for the first payment does not seem to have included any part of the hoop iron on the Germanic, which had then been discovered to be defective in quality, and it was made, as the agreement declared it should be, by a bill of exchange against the shipping documents produced and delivered to the plaintiffs, which it was essential they should possess in order to be able to obtain any control of the iron. This payment, including the invoice by the Arizona, as well as the succeeding payment, were made on account, and on the supposition that the contract had been, or would be, so performed as to entitle the defendants to the money. It was not a voluntary payment, in the sense excluding their right to recover so much of it back, as would protect the defendants against the obligation to restore so much of the money,
It has, however, by the judgment been determined that the-plaintiffs were not justified in refusing to accept so much of the R. G-. sheet iron as arrived by the steamer Rhubina. This iron was not laden on the steamer at Liverpool, but it was put on board of her at Cardiff, a port in Wales, on the Bristol channel. And because of its shipment in this manner, as well as objections taken to a slight excess in quantity, the plaintiffs refused to receive it. And the first of these objections certainly appears to have been warranted by the agreement, for the defendants agreed to ship the iron at Liverpool. They were not to insure it, but that was to be done, according to the specifications, by the plaintiffs, and, as they were not aware of this change in this port of shipment, the insurance effected by them upon it, if they did insure it, would have been worthless, if the iron had been injured or lost by a peril of the sea. This variation from the port of shipment would render the insurance invalid, and it did not create even a qualified delivery of the iron to the defendants, subject to their right of examination, under the rule sustained in Wilcox Silver Plate Company v. Green (72 N. Y., 17). For, to constitute even a qualified delivery of this description, the defendants were bound to ship the property as that had been provided for in their agreement, and having failed to do that, and no acceptance of the iron being made by the plaintiffs after its arrival, there was not even a qualified delivery of the iron shipped in this manner.
As to this iron the defendants failed to perform what the parties had agreed upon as one of the precedent attributes of their contract. And the performance of that condition was not waived by receiving and paying for the iron shipped at the same port on the Rhiwinda, as that payment was made without information on the part of the plaintiffs that the iron had not been shipped at Liverpool, and the defendants accordingly had no legal right to claim that this iron should be received by the plaintiffs. A point of this description was considered in Filley v. Pope (115 U. S.,
This part of the' judgment should, accordingly, be reversed, and the counter-claim of the defendants, including it, dismissed, unless a further trial of this part of the action shall be made to appear to be desirable on the settlement of the terms of the decision, and the plaintiffs should have judgment for the amount found to be otherwise due and owing to them by the referee and included in the judgment, and as so modified the judgment should be affirmed.
Judgment modified as directed in opinion, and as modified affirmed.